Professional Documents
Culture Documents
"SIMOPS, Intending to Break North Field Records in String Time per Well"
Anton Vos, Allan Cross, Bart Lismont, John van Venrooij, Roy Quaden, Sean Byrne / Qatar Shell GTL
This paper was prepared for presentation at the 2008 Abu Dhabi International Petroleum Exhibition and Conference held in Abu Dhabi, UAE, 3–6 November 2008.
This paper was selected for presentation by an SPE program committee following review of information contained in an abstract submitted by the author(s). Contents of the paper have not been
reviewed by the Society of Petroleum Engineers and are subject to correction by the author(s). The material does not necessarily reflect any position of the Society of Petroleum Engineers, its
officers, or members. Electronic reproduction, distribution, or storage of any part of this paper without the written consent of the Society of Petroleum Engineers is prohibited. Permission to
reproduce in print is restricted to an abstract of not more than 300 words; illustrations may not be copied. The abstract must contain conspicuous acknowledgment of SPE copyright.
Abstract
Historically, development wells in Qatar’s North Field have taken anywhere from 70 to 100 days to drill, complete, perforate,
stimulate and clean up in preparation for their long term production. To date, optimisations have predominantly focused on the
Drilling and Completion (installation) scope, as a mean’s of reducing the rig’s critical path. Although there have been
initiatives to minimize cost impacts by using cheaper alternatives to rigs for Perforation, Stimulation and Clean Up, these do
not address the total critical path impact that well delivery has on Project schedules. Pearl GTL’s Well Delivery initiative
“SIMOPS” could potentially address some of the imbalance.
“Undertaking drilling and completion operations with the rig, while simultaneously performing perforate, stimulation and
clean up operations on previously drilled and completed wells”
Pearl SIMOPS options included; being entirely rig based and running concurrent operations from the rig’s decks, upgrading
temporary wellhead decks such that the well service operations were ‘self sufficient’, and or use of a barge alongside rig /
temporary decks, and numerous variants/combinations of the afore mentioned.
Initially, SIMOPS value drivers focused on; HSE, innovation, and cost savings, which were used in part for justifying a high
specification jack up rig. Cost savings, based on rig days saved, were in the order of $60MM. Yet when the upfront well count
increased, during the planning phase prior to FID, schedule suddenly became a very significant value driver, Well Delivery
was now very much on the Project critical path.
Introduction
In October 2003 Shell signed a Heads Of Agreement with Qatar Petroleum for the development of a world scale gas to liquids
plant. This GTL plant consists of two separate trains which each produce 70,000 barrels of GTL products from 800 MMsCuft
gas feed. To establish the gas composition for the GTL plant design and to obtain early reservoir information to optimize the
area development plan one data and one appraisal well were drilled in 2004. The development drilling campaign called for two
platform locations with initially 8 wells each. Early 2005 the design and engineering for the development campaign was
started. In line with Shells well delivery process a “Value Challenge” was held in the Shell offices in Rijswijk, the
Netherlands. In such a value challenge the whole process to plan and design the project is studied and discussed with the
team, head office specialists and peers from other projects. Many ideas were generated to optimize the drilling and completion
of the wells, like driving the conductors instead of drilling a hole and cementing the conductor in place. Further time savings
were identified to reduce the drilling time by using high powered thin rubber mud motors, drilling the 16" hole section with
natural build assemblies and PDC bits etc. One part of the well construction process however looked more difficult to
optimize. The North field is by far the largest gas/condensate field in the world, and while structurally not complex it has some
features that make stimulating the reservoir section effectively a challenge. Firstly the Khuf reservoir in the North field is very
thick which leads to a very long effective reservoir along hole length for the around 55 to 60 degree inclined development
wells. Secondly the permeability's for the reservoir section ranges from sub milli-darcy's to several Darcy’s. To perforate,
stimulate and clean up effectively such a long reservoir section takes time, which with today's high rig rates is expensive.
2 SPE 117848
Since it looked unlikely that the perforation/stimulation and clean up time could be reduced significantly the idea was born to
perform these activities "off-line" i.e. concurrently with drilling later wells. This method of perforating/stimulating/cleaning up
concurrently while drilling subsequent wells is what we refer to as SIMOPS.
Time savings
15 to 20days
Per Well
Well 1 Perf/Stim/Clean
Well 2 Perf/Stim/Clean Off-line operations
Well 3 Perf/Stim/Clean
Back in Qatar after the “Value Challenge” the team started to work out several different options to perform the
perforation/stimulation and well clean up offline. Several concepts were studied, for instance only drilling and completing the
wells with the expensive drilling rig and afterwards performing the perforation, stimulation and clean up scope with a cheaper
unit or even a well servicing barge. While these options will reduce the overall cost of the project, it does not shorten the total
well delivery time of the project. Since shortening the total amount of rig days per well was one of the drivers the concept of
performing the perforation, stimulation and clean up scope from the drilling unit concurrently with drilling of the wells was
selected. The first thing that was realized is that if more activities needed to be performed simultaneously more people,
equipment and materials would be required at the work place at the same time. If all these activities would be performed from
the drilling rig, a significantly larger drilling rig would be required then the commonly used drilling units for drilling
development wells in Qatar. Since such a unit was not readily available it was decided to tender for the drilling rig very early.
Since a larger drilling rig would undoubtedly more expensive then an conventional smaller unit the tender exercise consisted
of two options where by the development campaign would be drilled either with two standard jack up drilling rigs or with one
large high specification unit. The tender resulted to awarding the contract to Noble for a new build Friede and Goldman JU-
2000E design rig. Since the awarded rig still had to be built by the time the contract was awarded, the contract contained a
clause that if the new build rig would arrive after a certain cut of date, when drilling had to be started to meet project
milestones, a standard rig could be supplied to perform the initial drilling activities before the arrival of the high specification
rig. The addition of this clause to the contract has proven to be very valuable for two reasons. Firstly as with many new build
projects in today’s overheated market the new build high specification rig, the Noble Roger Lewis did not arrive as originally
planned in October 2007, but was delayed to February 2008. Secondly when finalizing the Area Development Plan during the
planning phase prior to FID, the total number of wells was increased to 22 wells, 11 from each platform location. These 11
wells would consist of converting the vertical data wells, which were drilled up front from with a mud line suspension system
to a vertical producer with 10 additional deviated wells, which roughly radiate out from the platform center in a circle with a
step out of around 3000 meters. This increase in well count meant that not all wells could be constructed from one rig
sequence. The contract for the standard rig, the Noble Gene house was therefore extended to additionally drill the top-hole
sections on the Pearl-2 location.
After the rig contract was awarded, Noble the drilling contractor joined the team to convert the SIMOPS plan to a conceptual
design. During this phase of the project it was concluded that it would be best to separate the online drilling and completion
activities as far as possible from the Offline stimulate, perforate and clean up activities. This meant that most if not all offline
activities would be performed from temporary drilling decks.
SPE 117848 3
A Quantative Risk Assessment (QRA) was performed on the concept of performing the SIMOPS in this set up. The QRA
confirmed that the risk with performing SIMOPS were in the acceptable range. The temporary platform decks were mainly
designed to perform work on the wellheads and x-mass tree's during the well construction. One additional deck was included
in the original temporary platform decks this part was intended to be used for testing activities for the main gas pipeline to Ras
Laffan. The decision to perform the perforating from the temporary platform deck under the rigs cantilever resulted in an
increase of the distance between the underside of the cantilever which in normal operations is just a couple of feet to a distance
of 90 feet. This increase together with the requirement for lifting and hoisting equipment led to most up grade requirements for
the drilling rig.
The original temporary platform deck is a deck to perform well head and x-mass tree installation operations during the well
construction process. These decks are only temporary since they will be removed once the well construction is complete prior
to the installation of the permanent platform topsides. These decks normally are mainly for access only during the limited time
of the well construction activities, and are therefore light and simple. Performing SIMOPS operations placed however much
higher requirements on these decks. Firstly they had to be much larger to give enough space for a slick line wire line unit, a
braided line wire line unit to perform the perforating, and enough space for wire line workshops, lubricators etc. To clean up
the well the well is produced at rates of 100 MM Scft/day to remove the completion fluid, clean up the perforation tunnels and
remove the spent acid after the stimulation. For this a well clean up spread is required. To separate the clean up equipment and
the wire line equipment it was decided to include a separate deck for this clean up equipment.
Figure 3 – The simple original temporary decks. Figure 4 – The large final temporary decks for SIMOPS.
4 SPE 117848
Normally during well tests and well clean up activities the flare booms that are required to burn the produced gas and
condensate are mounted on the drilling rig. The decision to separate the offline and online activities as much as possible mean
that these flare booms now had to be mounted on the platform. Heat radiation studies showed that a high specification deluge
system would be required to keep the heat radiation within acceptable levels. Optima as specialist company was contracted to
provide nozzles that create a fine mist instead of the common systems used in this area that use a water spray to cool down
parts of the installation that are heated up by the flare. The rigs deep well pumps are normally supplying the water for this
system. The deep well pumps on the rig however did not have enough capacity and instead of up grading the rigs system and
having to pump the water from the sea level to the rig in its high elevation, it was decided to mount a separate the water supply
system on the platform deck. This deluge water supply system consists of two deep well pumps and two booster pumps
capable of supplying the deluge system with 2500 Gallons per minute at 250 psi.
The cranes on the drilling rig can only reach the temporary decks when the derrick is skidded in and over to the port side. This
meant that equipment and supplies could only be transferred to the platform when drilling is shut down. Both for online and
offline activities point of view this was unacceptable. A 12 metric ton crane was therefore installed on the temporary decks.
Since this crane was not available in time to be installed during the installation of the temporary decks, it was installed by the
Noble Roger Lewis drilling rig in between well operations early on in the project.
Normally it would have been best to install all these systems in the yard during the construction of the temporary decks. Time
pressures to install the decks when the crane barge was available however meant that all these systems could not be included in
the temporary decks before they were installed offshore and had to be added during the drilling of the first wells before the real
SIMOPS could start. While these construction activities took a couple of months and probably could have done much more
efficient in the yard, it gave the crews offshore a chance to practice, albeit a different type, SIMOPS with its inherent
communication requirements before the real activities started.
Figure 7 – The temporary decks left just after installation and right just before the start of SIMOPS
The contract for the Pearl Project was awarded to a newly built high performance Jack Up drilling rig in November 2005.
Planning for SIMOPS started in February 2006 and from the onset it became clear that performing SIMOPS from the Jack-up
drilling rig would not be feasible, and off-line operations would have to be conducted from the platform. To support SIMOPS
however several rig upgrades were required, these upgrades were completed in shipyard in Sharjah, between October 2007 and
January 2008, prior to arrival of the drilling rig in Qatar waters.
Upgrade to facilitate access and egress from the temporary decks of the production platform
Normally the distance from the top of the hull to the top of the platform decks is around 10 foot and a simple set of stairs is
normally used for access from the rig to the platform. With a 90-foot distance between the top of the hull and the top of the
platform deck traditional stairs were not feasible any more. People working on the platform would need to walk 90 foot of
6 SPE 117848
stairs, comparable to 8 to 9 floors in a normal building every time they would need to go from the platform to the rig and vice
versa. An exercise that even for the very fit is not easy under the high temperatures encountered in this region during a large
part of the year. Therefore a stair tower was designed that consists of a frame with both stairs for emergency access and a
elevator like commonly seen on building sites for access during normal operations. With the rig to be positioned 40 ft away
from the platform, a bridge would give access from the stair tower to the platform. The staircase was designed by Slaton
engineering and build by the Lamprell shipyard prior to the arrival of the rig in Sharjah from China. The design allowed the rig
to work at high and low air gaps. The stair tower was split in 2 sections; the upper section is 40 ft long and covers the complete
length of the hull. The upper stair tower section by itself allows the rig to work at low air gaps and by adding the lower 60ft
section the total length of the stair tower is increased to 100 ft allowing the rig to work at the required 120 ft air gap. The
bridge can be attached to either the upper or lower sections.
All electrical cables and utility lines have been routed to the platform from the drilling rig via the stair tower and the bridge.
Accommodation Upgrade
While the original standard design for the rig included accommodation for 160 people, the rig was ordered as a copycat from a
rig build for a Chinese drilling contractor. This design did not include the intended 160 POB specification but only allowed
120 persons on the drilling rig. While planning SIMOPS activities, it became clear that a POB of 120 would not suffice. With
both drilling, and perforating/stimulation/clean-up operations ongoing more space would be required in the accommodation.
The most cost effective way was found to be to upgrade the accommodation to a POB of 130. This was mainly driven by the
required change out of the lifeboats. The existing 60 people lifeboats could be changed to 65 people lifeboats with a minimum
cost impact as these were available from the drilling contractor. Additional life rafts were purchased and placed around the rig
as required. Operations up to now have proven that this upgrade to 130 people is the bare minimum, and still requires shuttling
a lot of people on and off the rig. The original design with 160 POB would have made this operation a lot simpler.
The cranes can be moved forward / backward and lateral via a trolley beam system that was installed under the cantilever
deck. To be able to reach even the last row of wells when drilling activities take place on the front most row of wells the
beams stick out approx 20 ft past the end of the cantilever. This design also allowed for a parking space for the gantry cranes
during rig moves when the cantilever is skidded all the way back over the rigs hull.
The total length of these risers is 115 ft. Since this length is around 100 foot more than for a normal rig up a structural analysis
was performed on this riser by UWG. The analysis concluded that a normal riser was strong enough to carry the complete
weight of the BOP and that the only lateral support required was right at the top of the BOP where it is connected to the
diverter housing mounted below the rig floor.
Changing the Conductor Tensioning Platform (‘The Box’) to a more standard BOP platform.
The original design of the rig had a conductor tensioning platform (CTP) at the back end and inside of the cantilever, this so
called box could move up and down into this moon pool area, which in addition to the conductor tensioning provided some
protection while working in this area when the rig would be operating in free standing mode.
With the gantry cranes installed underneath the cantilever deck, it would be impossible to operate this CTP.
8 SPE 117848
Freede Goldman the designers of the rig were asked to design a more traditional BOP deck that would allow easy access to the
BOP’s and would provide a safe area to work. A 15” gap runs over the length of the BOP deck to allow access for the drilling
risers to pass through. The holes would be covered with deck hatches if not used.
This BOP platform was manufactured and installed in the Sharjah shipyard.
The project specific hazard analysis work and the QRA has concluded that:
• Thermal radiation and products of combustion from flaring well fluids up to 150MMSCF/D at the tips of the 85 foot long
burner booms, will not generate intolerable hazard levels at the well jacket or drilling rig.
• Unignited gas releases from the wire line head will disperse over a few meters to concentrations that are below lethal
considering the H2S concentrations.
• Quantified safety risks for SIMOPS at Pearl 1, with the rig positioned on the South side of the jacket, are tolerable by
Shell and project criteria
• The maximum calculated Individual Risk Per Annum (IRPA) for the base case SIMOPS job, is tolerable by Shell risk
acceptance criteria
• Total calculated Potential Loss of Life (PLL) for the SIMOPS operations are within the acceptable range.
• Document the research and decision making that has resulted in the HSE Case as demonstration that due diligence has
taken place
• Show that Senior Management have endorsed the SIMOPS HSE Case and agree that the SIMOPS as planned were safe to
proceed
Through the process of development of the SIMOPS HSE Case a number of deficiencies were identified resulting in remedial
actions. They form the basis for plans and implementation activities and contribute to the SIMOPS HSE Case being a ‘living
document’.
Technical Assurance
An independent technical team consisting of Shell Group Completions and Well Intervention senior personnel, Pearl GTL
project HSE personnel plus a senior representative from a Contracting Company carried out a 5-day technical assurance
review during the preparation phase. This to verify that operations where planned and executed against Group and industry
HSE and Technical standards. Recommendations were carried forward during final preparation. It was this review team, with
intimate knowledge of the planned operations and environment, who finally sanctioned the start of SIMOPS, after satisfying
themselves that all risks were appropriately addressed with all controls in place.
Action Register
To ease implementation of the SIMOPS HSE case, HAZOP and recommendations from the Technical Assurance review a
detailed action register was developed, whereby individual actions/control measures were ranked on priority and risk. This
‘live’ register formed the basis of internal and external meetings with the Contracting Companies. The action register was also
key in tracking progress versus schedule.
The action register was also the basis for the final review with the Technical Assurance team to start take SIMOPS from the
Define into the Execute phase (as per the Shell Well Delivery Process).
It was also this action register that was carried forward into the execution phase to capture learning’s and actions of After
Action Reviews (AAR), Shell’s operational evaluation tool.
SIMOPS audit
Operations to date have proven that the systems and equipment perform well. To further verify the effectiveness of the
implementation plans and procedures a SIMOPS audit will be carried out by Shell Group about 2 months after start up.
Conclusions
Drilling optimizations identified in the value challenge have reduced the drilling time from an average of 61 days at the
concept selection time to 45 days that are being used for the AFE for Pearl GTL. While the drilling campaign is still ongoing
results up to now indicate that this AFE time is realistic and can be met. Historically 12 to 45 days were required for the
stimulation, perforation and well clean up work scope, which lead to a total well duration of 70 to 100 days
The stimulation technique selected for the Pearl GTL projects utilises Visco-elastic Diverting acid combined with hydrolysable
fibers. This has reduced the over all time for the perforation stimulation clean-up work scope to 15 days.
Since Pearl GTL performs the perforating, stimulating and clean-up activities off line concurrently while drilling and
completing subsequent wells this results in using only 45 string days per well compared to 70 to 100 days historically.
SIMOPS has enabled the Pearl GTL Well delivery team to deliver Top Quartile performance on a for Shell must win project.
During the development of the SIMOPS concept some additional advantages became apparent. Since the off-line activities are
not on the critical path and the fact that the wells do not need to be stimulated straight away after the perforation operations are
completed the timing when the stimulation vessel would be required became more flexible.
Clean-Up duration
Stimulation /
Perforation /
As a result of this the project contracted a stimulation vessel on a call off contract basis rather than a commonly used dedicated
contract. Operating rates for a call off contract are lower than a dedicated contract since it enables the stimulation contractor to
increase the utilization of his vessel by using it on call of jobs during the unused time on a dedicated contract.
Installing and testing the x-mass tree is normally done with the rig and takes around half a day. This activity can now be done
offline utilizing the gantry cranes and the platform crews. Over all the SIMOPS project has been very successful, projected to
save around 300 rig days for the Pearl project.
Figure 13. Flaring during well clean-up from the platform while drilling continues from the rig.
Acknowledgements:
Qatar Petroleum (QP), Shell International Exploration and Production (SIEP), Qatar Shell Gas To Liquids (QSGTL - a Shell Gas and Power
entity) Leadership Team, QSGTL Well Engineering / Subsurface / and Platforms Teams
QSGTL Contractors - CW International HSE, Halliburton, JRM McDermott, Noble Drilling (and their Third Party Contractors; Slaton
Engineering, Seacor Industries, Kone Cranes, Dalian and Lamprell shipyards), Optima, P-EWI, Schlumberger, UWG, Weatherford
References:
Hazard analysis & QRA for SIMOPS at Pearl 1 by the Roger Lewis Jack-Up Drilling Rig / PEWI-QS-P1,2-SIMOPS-QRA-01 / Petrokon-
EWI Sdn Bhd (P-EWI)
Heat radiation study Flaresim modelling Optima Solutions UK Ltd.
Structural Analysis of High Pressure Drilling Risers on Pearl Platform Wells - UWG UK Ltd
SIMOPS HSE case QATAR-WE HSE-SP-0055
QSGTL SIMOPS Operations Programme Rev 01