You are on page 1of 4

698 IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 17, NO.

3, JULY 2002

Unbalance Protection of Fuseless, Split-Wye,


Grounded, Shunt Capacitor Banks
Randy Horton, Member, IEEE, Ted Warren, Karl Fender, Member, IEEE, Steven Harry, Member, IEEE, and
Charles A. Gross, Senior Member, IEEE

Abstract—In recent years, a large number of electric utilities


have been implementing fuseless split-wye grounded capacitor
banks in lieu of the traditional externally fused bank. This
change in philosophy has forced many protection engineers to
research new methods of calculating the quantities needed to
apply unbalance protection. This paper presents a novel method of
calculating the unbalance current produced by fuseless capacitor
unit failures as well as some general background information
regarding fuseless split-wye grounded capacitor bank technology
and unbalanced protection.
Index Terms—Power capacitors, power system protection.

I. INTRODUCTION

P OWER system components consume reactive power


. For example, transmission lines, rotating electric
machinery, and transformers all absorb reactive power because
of their inductive nature. Since the system is reactive power
conservative, an equal amount of must be generated, either
by the system generators, or by compensating capacitors
located throughout the system. flow through a system
transmission path requires increased current. High current flow
causes two important problems: 1) increased real power losses
and 2) increased voltage drop. Hence, optimum location of
capacitor banks so as to minimize losses and voltage problems
is an important engineering consideration. Fig. 1. One phase of a split-wye grounded 115 kV–15 Mvar fuseless capacitor
Due to advances in capacitor manufacturing, many electric bank.
utility companies have found fuseless shunt capacitor banks
to be an economical and reliable means of providing reactive
ment is constructed of aluminum foil electrodes with a dielectric
power, and deploy them extensively, throughout their systems.
of electrical grade polypropylene. The element has three ratings:
Hence, there is an increased need for a reliable, practical, and
economical protection scheme for fuseless capacitor banks. 1) voltage , which is determined by the dielectric
Such a protection scheme will be presented in this paper. strength;
2) frequency, usually 60 Hz in the U.S.;
II. FUSELESS CAPACITOR BANK DESIGN 3) (or kvar), which specifies the reactive power flowing
out of the element when operated at rated voltage and
The all-film, high-voltage power capacitors used in fuseless frequency.
capacitor banks are constructed internally of smaller capacitors
called “elements” or “packs.” The basic power capacitor ele- Elements are connected in series and parallel combinations to
achieve the required voltage and kvar rating of the capacitor [1].
Fuseless split-wye grounded capacitor banks are comprised
of combinations of capacitor units called strings. Capacitor
Manuscript received July 9, 2001. bank strings are formed by connecting several capacitor units
R. Horton, T. Warren, and S. Harry are with Alabama Power Company, Birm-
ingham, AL 35203 USA. or cans, as they are commonly referred to, in series. Strings
K. Fender is with Cooper Power Systems, McGraw-Edison Power Capacitors, are then placed in parallel to form a phase of the bank and its
Greenwood, SC 29646 USA. required Mvar rating. One phase of a typical 115-kV, 15-Mvar
C. A. Gross is with the Department of Electrical Engineering, Auburn Uni-
versity, Auburn, AL 36849 USA. split-wye, grounded capacitor bank used by the Southern
Publisher Item Identifier S 0885-8977(02)05935-6. Company is shown in Fig. 1.
0885-8977/02$17.00 © 2002 IEEE
HORTON et al.: UNBALANCE PROTECTION OF FUSELESS, SPLIT-WYE, GROUNDED, SHUNT CAPACITOR BANKS 699

Fig. 2. Voltage distribution within a string due to a shorted series section.

III. FUSELESS CAPACITOR BANK UNBALANCE PROTECTION


A. Introduction
In general, the purpose of capacitor bank protection is to in-
crease the availability of the capacitor bank. This is accom-
plished by alarming maintenance personnel of possible prob- Fig. 3. A 115-kV, 15-Mvar, split-wye grounded fuseless capacitor bank.
lems with the bank and removing it from service before severe
damage occurs. voltage of the bank; the higher the rated voltage of the bank, the
Phase overcurrent protection for a fuseless bank is similar to more series sections there are per string. Banks must be able to
that of externally fused banks. Phase overcurrent protection, as operate with one series section failure without excessive over-
well as ground overcurrent protection, is recommended for all voltage. For this reason, fuseless banks are typically not prac-
split-wye grounded fuseless capacitor banks. See [2] for further tical below a system voltage of 34.5 kV.
details regarding the application of overcurrent protection. The required rated voltage of a series section can be calcu-
The most common cause of failure of a capacitor unit is the di- lated by dividing the rated voltage of the capacitor unit by the
electric failure of one of its elements, which fails in the short-cir- number of series sections of parallel connected elements in-
cuit mode. When an internal series element fails, it shorts the ternal to the unit. Fig. 1, shows the internal connections of a
other parallel elements within that group, which in turn causes typical 16.6-kV, 625-kvar capacitor unit used by the Southern
the system voltage to be applied across the healthy capacitor el- Company. For this unit, each series section is rated at 16.6 kV/8
ements in the string. Such failures produce little change in phase 2.075 kV.
current magnitude and are therefore undetectable by normal To cover the condition created by bushing flashovers and
phase overcurrent relaying. For this reason, unbalance protec- major insulation failures, the protection scheme must trip the
tion is required to protect the bank from cascading failures. bank when one can is shorted. In most cases, there will be more
than adequate protection for this situation since only partial in-
B. Protection Scheme ternal shorting of a capacitor unit will normally result in an
unacceptable overvoltage condition. This should be confirmed
The objectives of an unbalance protection scheme are when calculating the relay settings.
1) to detect a single internal element failure, and activate an Unbalance protection of a split-wye grounded, fuseless ca-
alarm; pacitor bank is implemented by placing an overvoltage relay in
2) to detect and trip for multiple element failures that result parallel with a resistor located in the differentially summed sec-
in excessive overvoltage across healthy elements; ondary of the neutral current transformer circuit, as shown in
3) to detect and trip for bushing flashovers and major insu- Fig. 3. When an unbalance condition occurs ,a
lation failures. difference current flows through , producing a voltage across
In Fig. 2, a shorted series element causes the phase-to-ground the relay coil (device 59). When this voltage reaches the desired
system voltage to be redistributed across the remaining 31 ele- set point, the relay will either alarm maintenance personnel or
ments. Assuming the bank is operating at 1.0 p.u. voltage, this trip the bank off-line.
failure results in an overvoltage of 32/31 103%; two shorted Unbalance protection must deal with other causes of unbal-
elements will cause an overvoltage of 32/30 107%, etc. ance. Unbalanced system voltages and inherent unbalance of the
It is desirable to notify maintenance personnel in the event capacitor unit impedances will also cause nonzero neutral cur-
of the first series section failure and automatically remove the rent. Because of these nuisance unbalances, precautions must
bank from service when the voltage applied to the remaining be taken when applying unbalance protection schemes. System
series sections exceeds 110% of their rated voltage. Removal unbalance can be nullified by differentially summing the cur-
from service typically occurs after the second series section has rent transformer’s secondary circuits, as shown in Fig. 3. With
shorted; however, this is not always the case. The number of se- this configuration, any system unbalance affects both wye con-
ries sections contained within a string is a function of the rated nected sections equally resulting in the primary current of each
700 IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 17, NO. 3, JULY 2002

neutral current transformer being equal. When the current trans- maximum continuous system voltage is important since oper-
former secondary circuits are differentially summed as shown, ating voltages in excess of nominal will result in capacitor over-
the resulting current flowing through the resistor, and therefore voltage without a failure within the bank).
the voltage “seen” by the neutral overvoltage relay will be zero. For this bank, we wish to determine the appropriate over-
voltage relay settings for both the ALARM and TRIP condi-
C. Calculations tions. The unbalance calculations for two shorted series sections
are as follows.
To determine the appropriate settings for the overvoltage
The current flowing through the neutral of the capacitor bank
relay, calculate
due to two shorted series sections is found using (1)
1) the voltage present across the remaining capacitor ele-
ments in a faulted string; kV
kV
2) the resulting voltage developed across the neutral resistor.
The practical approach in determining adequate overvoltage
relay settings is to develop a table for various numbers of
failed series sections. From this table, it will be obvious as to
k
how many failed elements will cause an excessive overvoltage
condition.
Equations (1)–(5) can be used to solve for the quantities
needed to set the overvoltage relay

(1) A

with the neutral current known, the voltage developed across the
(2) neutral resistor can be found using (2)
(3)

(4)
V
(5)
The percent overvoltage experienced by each remaining se-
where ries sections within the faulted string is found using (3)
neutral current, A;
neutral resistance, ;
neutral current transformer ratio;
voltage developed across , ;
system maximum operating voltage, kV;
rated voltage of each capacitor unit (can), kV;
reactive power rating of capacitor can, Mvars; To aid in setting the relay, the calculations should be per-
impedance of capacitor can, ; formed for multiple element failures. The results of these cal-
number of series sections per capacitor can; culations are shown in Table I.
impedance of capacitor element, k ; 1) ALARM Setting
number of series—connected capacitor cans per The results of the calculations indicate that two se-
string; ries sections can be shorted without subjecting the re-
number of shorted series sections in one string. maining series sections in the faulted string to excessive
overvoltage. If the voltage relay has a separate alarm set
point, then it should be set such that the relay will alarm
D. Application Example for one shorted series section. The exact setting is a matter
The example capacitor bank is a 115-kV, 15-Mvar, split-wye, of preference. Allowing for some margin of error is ap-
grounded fuseless bank consisting of two parallel strings of four propriate. An alarm setting of 70–80% of the calculated
series-connected capacitor units per phase (see Fig. 3). Each ca- relay voltage for one shorted element will most likely pre-
pacitor consists of eight series sections of three parallel-con- vent false alarms due to inherent unbalance while assuring
nected elements each. Each capacitor is rated at 16.6 kV and that one shorted series section is detected.
625 kvar. Each capacitor is also rated to withstand a continuous 2) TRIP Setting
overvoltage of up to 110%. The neutral current transformer ratio Two situations must be considered when deriving the
is 25:5 and the neutral resistor is 10 . The maximum contin- trip setting. First, the bank must be removed from ser-
uous power system voltage is determined to be 118 kV (The vice before the remaining series sections in the faulted
HORTON et al.: UNBALANCE PROTECTION OF FUSELESS, SPLIT-WYE, GROUNDED, SHUNT CAPACITOR BANKS 701

TABLE I and economical means of providing reactive power to a system.


CALCULATION RESULTS FOR MULTIPLE SERIES SECTION FAILURES Because of the increased usage of fuseless power capacitors, an
unbalance protection scheme that can be easily understood and
implemented by protection engineers is needed. The unbalance
protection scheme presented in this paper can be easily applied
using the information provided herein.

REFERENCES
[1] F. Karl and M. Jack, “The use of high-reliability capacitor units
with fuses in high-voltage substation banks,” in Cooper Power Sys-
tems. Greenwood, SC: McGraw Edison Power Capacitors.
[2] IEEE Guide for the Protection of Shunt Capacitor Banks, IEEE Std.
string are subjected to an excessive overvoltage condition. C37.99-2000, 2000.
Second, the bank must be promptly removed from ser-
vice if an entire capacitor unit is shorted, e.g., a bushing
flashover or major insulation failure.
From the data in Table I, it is apparent that the remaining Randy Horton (S’95–M’96) was born in Birmingham, AL, in 1973. He re-
ceived the B.S.E.E. degree with specialization in power systems from the Uni-
series sections in the faulted string will be subjected to an ex- versity of Alabama at Birmingham in 1996, and is currently pursuing the M.E.E.
cessive overvoltage condition once three series sections become degree at Auburn University, Auburn, AL.
shorted. However, it should be noted that the failure of two se- He is currently a Protection Engineer at Alabama Power Company, Birm-
ingham. His current technical interests include protection of large capacitor
ries sections will result in nearly 10% overvoltage. Using sound banks, transformers, and HV and EHV transmission lines.
engineering judgement, it seems appropriate in this case to trip Mr. Horton is a registered Professional Engineer in Alabama.
the bank off-line for two shorted elements. Note also that pro-
tection will be provided for a shorted capacitor unit since eight
series sections are effectively shorted for this scenario.
Selecting a trip setting that is greater than the resulting relay Ted Warren received the B.E.E. degree from Auburn University, Auburn, AL,
in 1993.
voltage for one shorted series section, yet less than that for two Currently, he is a Protection Engineer at Alabama Power Company, Birm-
shorted elements will suffice. Again, an exact setting is a matter ingham. He has also worked as a Protection Engineer with Alabama Electric
of preference. Some margin should be considered since a set- Cooperative, and has worked in the industrial automation field.
Mr. Warren is a registered Professional Engineer in Alabama.
ting that is too low, combined with inherent unbalance due to
manufacturer’s tolerances, may result in a false trip. A setting
that is too high, combined with an unexpectedly high operating
voltage, could subject the bank to sustained overvoltage beyond Karl Fender (M’93) received the B.S. degree in electrical engineering from the
the continuous rating. A setting of 80% of the calculated voltage University of South Carolina, Columbia.
has been used successfully. Currently, he is Manager of Application Engineering at Cooper Power Sys-
tems, McGraw-Edison Power Capacitors, Greewood, SC. He joined Cooper
The unbalance protective relaying scheme will compensate Power Systems in 1993 after five years in the U.S. Navy. He has held several
for system unbalance, and thus is not required to coordinate with positions within Cooper Power Systems in both design engineering and mar-
the clearing of a “close in” line-to-ground fault. Also, since the keting. and is a Member of several capacitor-related IEEE working groups.
bank has no fuses, the unbalance protective relaying scheme is
not required to coordinate with the operation time of an external
fuse. Therefore, a trip time delay of 0.5 s or less is recommended
Steven Harry (S’96–M’01) received the B.E.E. degree and the M.S. degree
[2]; however, longer delays have been used successfully. with a specialization in power systems from Auburn University at Birmingham
For the preceding example, the following relay settings were in 1995 and 2000, respectively.
chosen: He is currently a Protection Engineer at Alabama Power Company,
Birmingham. His current technical interests include power system protection,
switching transients, and substation automation.
Alarm Setpoint V Mr. Harry is a registered Professional Engineer in Alabama.
Alarm Time Delay s
Trip Setpoint V
Trip Time Delay s Charles A. Gross (S’68–M’69–SM’75) received the B.S. degree in physics,
and the B.S. degree in electrical engineering from The University of Alabama,
Tuscaloosa, and the M.S.E.E. and Ph.D. degrees from the University of Missouri
at Rolla.
IV. CONCLUSION He has extensive academic, industrial, and consulting experience in electric
power engineering, and is the author of the textbook Power System Analysis
Due to its simple design and the invention of the all-film ca- (New York: Wiley, 1986). He is currently Square D Power Professor at Auburn
pacitor unit, the fuseless capacitor bank has become a reliable University.

You might also like