You are on page 1of 10

VEDANTA LIMITED

Cairn Oil & Gas

SULPHATE REMOVAL PLANT

HOT WORK PROCEDURE


Doc No: G225IEX-SRP-R-PRO-**

OWNER’S CONSULTANT & PMC

TRACTEBEL ENGINEERING PVT. LTD.

EPC CONTRACTOR

ION EXCHANGE INDIA LIMITED

B2 00-10-2018 Issued for Information PANKAJ AK KS

B1 00-10-2018 Issued for Information PANKAJ AK KS

Prepared Checked Approved Approved


Rev Date Purpose of Issue
by by By By
Doc No.
G225IEX-SRP-R-PRO-**

SULPHATE REMOVAL PLANT


Revision B1
HOT WORK PROCEDURE

Document Change History

Rev Date Editor Section Nature of Change


B1 19-10-18 KIRTI HSE Issued for Information
SINGH

This document contains controlled copies of the procedure listed above. Any copies made from this document,
in part or in whole, are uncontrolled and are therefore not subject to further review, revision or approval.
It is the responsibility of the Director of HSE & A to control and update the contents of this document.

Any concerns or queries regarding the contents or interpretation of this document should be addressed to:

ION EXCHANGE (INDIA) LTD.

Flat No.8, Block B, Local Shopping Center

Ring Road,Naraina Vihar

New Delhi-110028, India

Board; +911130543200s

Fax; +911125774837
Doc No.
G225IEX-SRP-R-PRO-**

SULPHATE REMOVAL PLANT


Revision B1
HOT WORK PROCEDURE

TABLE OF CONTENTS

Sr. No Description Page No.


1 PURPOSE 5
2 SCOPE 5
3 RESPONSIBILITY 5
3.1 SITE MANAGER 5
3.2 HSE MANAGER 5
3.3 CONSTRUCTION MANAGER 5
3.4 SUBCONTRACTORS PROJECT MANAGER 6
4 PROCEDURE 6-7
5 TRAINING 8
6 HOT WORK PERMIT 8
7 REFRENCES 8
8 APPENDICES 8-10
8.1 APPENDIX-A -HOT WORK CHECKLIST 9
8.2 APPENDIX-B-PERMIT FORM FOR HOT WORK 10
Doc No.
G225IEX-SRP-R-PRO-**

SULPHATE REMOVAL PLANT


Revision B1
HOT WORK PROCEDURE

ABBREVIATON

IEIL ION EXCHANGE INDIA LIMITED

CIL CAIRN INDIA LIMITED

SRP SULPHATE REMOVAL PLANT

HSE HEALTH SAFETY ENVIRONMENT


Doc No.
G225IEX-SRP-R-PRO-**

SULPHATE REMOVAL PLANT


Revision B1
HOT WORK PROCEDURE

1. Purpose

The purpose of this procedure and guidance information is to outline the requirements for safely
managing, maintaining and controlling sources of ignition to prevent the risk of fire and explosion.

2. Scope

This procedure applies to all hot work activities in use by IEIL and their subcontractors.

Examples of hot work activities include: -

 Electric or gas welding and cutting operations


 Brazing
 Soldering
 Bitumen boilers
 Portable electric or air driven tools used for drilling, grinding, wire brushing, chipping, hot bolting
etc.
 Equipment capable of generating static electricity i.e. during grit blasting
 Work on electrical equipment during pre-commissioning and commissioning

In addition to the above examples hot work involves any other equipment or work activities
producing heat, sparks or having naked flames.

3. Responsibility

3.1 Site Manager


In conjunction with the HSE Manager shall ensure the following:

 Ensure that adequate provisions are made for compliance with this procedure and that
arrangementsare in place for ongoing inspection of safe execution of all hot workactivities.
 In accordance with the overall Safety plan, introduce a ‘Permit to Work’ system for the control of
hot work.

3.2 HSE Manager


 To monitor compliance with this procedure.
 To monitor and maintain a record of all hot works permits and to monitor and audit
compliance with these issued permits.
 Those arrangements are in place for ongoing systems of inspection for all hot workactivities.

3.3 Construction Manager (Area Authority)


Doc No.
G225IEX-SRP-R-PRO-**

SULPHATE REMOVAL PLANT


Revision B1
HOT WORK PROCEDURE

 Responsibility for issuing the hot work permits rests with the Area Authorityassigned to check
the working area and approve the work activities.
 Ensure all signatories on the permit understand they have equal responsibility for instituting
safe workpractices.

3.4 Subcontractors Project Manager

 Subcontractors, including their subcontractors are responsible for the safety of their hot work
activities and will work in strict accordance with this procedure and within the parameters of the
hot work permit.
 To ensure that an appropriate permit to work is in place and a risk assessment has been
performed.
 To ensure personnel using the equipment are trained and competent for the tasks.
 To ensure that workers are issued and used approved PPE.
 To ensure that arrangement is made to enable the work place to be made ‘fire safe’.
 To ensure that protection such as screens (fixed or portable) is used to protect other persons
from any hazards.
 Ensure that provisions are made for suitable / safe equipment when all hot work activities are to
be carried out on the project.
 Ensure suitable firefighting equipment and resources are readily available in all areas of hot
work activities.

4. Procedure

Before commencing any type of hot work consideration should be given amongst others to the
following precautions:

4.1 The working area and its vicinity must be cleared of any combustiblematerials.

4.2 Other non-moveable items of combustible materials should be covered and protected with non-
combustible material.

4.3 If work is to take place on one side of a wall or partition, the opposite side must be examined to
ensure no combustible material will be ignited by conducted heat.

4.4 Suitable extinguishers of appropriate types must be ‘on standby’ and a careful watch must be kept
for fire breaking out whilst work is in progress.
4.5 Fire blankets or flame resistant shields shall be used to prevent welding sparks/splatter or grinding
sparks from dropping down below onto persons/materials/equipment.

4.6 In addition to the items described above (4.5), it is strongly recommended that warning signs and
barricades are installed to prevent persons from accessing areas whilst any work, especially when
hot work is taking place overhead.

4.7 At least 30 minutes before the end of a work shift all hot work should cease to enable good
housekeeping to take place. This will assist in ensuring hot work has not caused any material to
Doc No.
G225IEX-SRP-R-PRO-**

SULPHATE REMOVAL PLANT


Revision B1
HOT WORK PROCEDURE

remain smoldering thus resulting, in the possibility of a large fire igniting after personnel has left
the working area.

4.8 When gas welding/cutting, all gas cylinders must be secured in a vertical position (preferably
located on a trolley for ease of movement in case of an emergency).

4.9 During gas welding/cutting, all gas cylinders must be kept out side of confined space. Similarly if
such work is to be conducted at height.

4.10 Associated permit for Confined space entry shall be required to be issued as per job requirement.
Similarly when such work is to be conducted at height then all necessary safety precautions must
be taken. Gas cylinders must be transferred using suitable basket in vertically claimed position.

4.11 Provide adequate ventilation or respiratory protection against all activities resulting in fumes, lack of
oxygen in the area, or dust.

4.12 Gas-welding equipment must be fitted with a flashback arrestor and special care to be taken in high
risk areas including:
 In a confined space.
 In general where access is difficult or the means of escape may be endangered by
fire/explosion.
 When welding adjacent to live operating plant.
 Near compressed air working.
 Gas hoses shall as be as per standard
 When persons are competent in welding practices.

For more detail information, refer to the procedure,-HSE-P31 (Welding Operations)

4.13 Bitumen boilers, lead heaters and similar equipment should only be taken onto roofs in exceptional
circumstances. In such cases a non-combustible, heat-insulating base must be provided to prevent
heat igniting the roof in addition: -
 An experienced person must always supervise heating equipment.
 Boilers etc should always be sited where spilled material can easily be controlled.
 LPG cylinders must be located at least 3.0 meters from the burner.
 LPG cylinders must be secured to prevent accidental movement.
 LPG cylinders must be stored in an upright manner.
 Armored hose should be used for supplying the gas to the burner.
 Every bitumen boiler shall be fitted with a lid.
 At least one appropriate fire extinguisher must be in the vicinity of the work.

4.14 Emergency response team should be ready to deal with any consequence due to break out of fire
during hot work job.

5. Training

All persons must be competent in the hazards of hot work before they commence such activity,
training to include: -
Doc No.
G225IEX-SRP-R-PRO-**

SULPHATE REMOVAL PLANT


Revision B1
HOT WORK PROCEDURE

 Good housekeeping practices.


 Protection of other persons and equipment.
 Correct use of welding equipment and associated gas cylinders.
 Inspection of the working area for smoldering material during and after completing the hot work.
 Correct use of fire extinguishers.
 Procedure for warning other persons in the event of a fire.
 Trained in accordance with the permit to work for hot work.

6. Hot Work Permit

A permit to work system provides formal written procedures and formal actions to ensure that
potentially hazardous activities are carried out as safely as possible.

6.1 The hot work permit is a written document and includes: -


 Competent persons to carry out the work activities.
 Warns of possible hazards associated with the hot work.
 Clearly states the HSE precautions to be taken for the work to be carried out safely.
 The permit specifies the particular equipment and construction methods to be implemented.
 Extent of the work.
 Conditions to be observed.
 Duration of the permit.
 The current hot work permit shall be clearly displayed in the area of the hot work.

6.2 The overall determination for issuing a hot work permit and reviewing the area for combustibles
rest with the designated personnel assigned to that scope of work. Before the issuing of a hot
work permit, considerations should be given amongst others to the following: -
 All other items as featured in this procedure.
 Emptying, purging and cleaning of equipment from combustible substances.
 Isolation, utilizing blinds, closed valves, lock out/ tag out etc.
 Location, condition and grounding of equipment to be used.
 Suitably trained and in position at all times ‘standby/rescue/fire watchmen’.
 Hot work in confined spaces will also require a permit to work for confined spaces and will call
for continual safety monitoring throughout the scope of work.

7. References

 The HSE Procedure, Permit to Work(---------)


 The HSE Procedure, Confined Spaces (----------)
 The HSE Procedure, Working at Height (--------)
 The HSE Procedure, Welding Operations (--------------)

8. Appendices

8.1 Hot Work Checklist


8.2 Permit Form for Hot Work
Doc No.
G225IEX-SRP-R-PRO-**

SULPHATE REMOVAL PLANT


Revision B1
HOT WORK PROCEDURE
Doc No.
G225IEX-SRP-R-PRO-**

SULPHATE REMOVAL PLANT


Revision B1
HOT WORK PROCEDURE

You might also like