Project EjemploYoutube

Solve

Change Gantt

Critical Graph

Update Schedule

Activity Data Activity Time Estimates

Critical Name Description Predecessors Color Min.


1 1 Start Activity Start 0
2 1 A Activity A 4
3 0 B Activity B A 2
4 1 C Activity C A 8
5 0 D Activity D A 4
6 0 E Activity E B 1
7 1 F Activity F E C 6
8 0 G Activity G E C 2
9 1 H Activity H F 2
10 0 I Activity I F 6
11 1 J Activity J D G H 4
12 1 K Activity K I J 2
13 1 End Activity End 0
15
Times(Proj. Weeks)
Due 40.167
Critical 40.167
Var. 10.028
SD. 3.1667
On Time Prob. 0.5
Slack 0.0003
Late 0
Current 0

Activity Time Estimates Schedule Limits


Most Time Activity Early Late Early Late
Likely Max. Mean S.D. Var. Weeks Delay Sort Start Start Finish Finish
0 0 0 0 0 0 0 1 0 0.0003 0 0.0003
8 10 7.6667 1 1 7.6667 0 2 0 0.0003 7.6667 7.667
8 24 9.6667 3.6667 13.444 9.6667 0 3 7.6667 8.0003 17.333 17.667
12 16 12 1.3333 1.7778 12 0 4 7.6667 7.667 19.667 19.667
6 10 6.3333 1 1 6.3333 0 5 7.6667 25 14 31.334
2 3 2 0.3333 0.1111 2 0 6 17.333 17.667 19.333 19.667
8 20 9.6667 2.3333 5.4444 9.6667 0 7 19.667 19.667 29.333 29.334
3 4 3 0.3333 0.1111 3 0 8 19.667 28.334 22.667 31.334
2 2 2 0 0 2 0 9 29.333 29.334 31.333 31.334
6 6 6 0 0 6 0 10 29.333 32 35.333 38
6 12 6.6667 1.3333 1.7778 6.6667 0 11 31.333 31.334 38 38
2 3 2.1667 0.1667 0.0278 2.1667 0 12 38 38 40.167 40.167
0 0 0 0 0 0 0 13 40.167 40.167 40.167 40.167
Schedule Decisions
Sched. Sched. Perc.
Slack Start Finish Finished
0.0003 0 0 0%
0.0003 0 7.6667 0%
0.3337 7.6667 17.333 0%
0.0003 7.6667 19.667 0%
17.334 7.6667 14 0%
0.3337 17.333 19.333 0%
0.0003 19.667 29.333 0%
8.667 19.667 22.667 0%
0.0003 29.333 31.333 0%
2.667 29.333 35.333 0%
0.0003 31.333 38 0%
0.0003 38 40.167 0%
0.0003 40.167 40.167 0%