Project Proyecto3 Times(Proj.

days)
Due 100
Solve Critical 142
Slack 0
Change Gantt Late 42
Current 0
Critical Graph

Update Schedule

Activity Data
Time Activity
Critical Name Description Predecessors Color days Delay
1 1 Start Activity Start 0 0
2 1 A Activity A 4 0
3 1 B Activity B A 12 0
4 1 C Activity C B 20 0
5 1 D Activity D C 12 0
6 1 E Activity E D 15 0
7 1 F Activity F E 5 0
8 1 G Activity G F 15 0
9 1 H Activity H G 4 0
10 1 I Activity I H 5 0
11 1 J Activity J I 15 0
12 1 K Activity K J 17 0
13 1 L Activity L K 7 0
14 1 M Activity M L 3 0
15 1 N Activity N M 7 0
16 0 O Activity O J 6 0
17 0 P Activity P O 4 0
18 0 Q Activity Q P 6 0
19 0 R Activity R Q 4 0
20 0 S Activity S R 2 0
21 0 T Activity T S 2 0
22 1 U Activity U N 1 0
23 1 End Activity End 0 0
20
Schedule Decisions
Sched. Sched. Perc.
Slack Start Finish Finished
0 0 0 0%
0 0 4 0%
0 4 16 0%
0 16 36 0%
0 36 48 0%
0 48 63 0%
0 63 68 0%
0 68 83 0%
0 83 87 0%
0 87 92 0%
0 92 107 0%
0 107 124 0%
0 124 131 0%
0 131 134 0%
0 134 141 0%
11 107 113 0%
11 113 117 0%
11 117 123 0%
11 123 127 0%
11 127 129 0%
11 129 131 0%
0 141 142 0%
0 142 142 0%
Project Graphic Proyecto3

Start(1) A(2) B(3) C(4) D(5) E(6) F(7)


G(8) H(9) I(10) J(11) K(12) L(13) M(14)

O(16) P(17) Q(18)


N(15) S(20) T(21) End(23)

R(19) U(22)
Network Proyecto3

Activity on Node Network


Sorted Activity Nodes Sorted Precedence Arcs
From To From To Critical
Index Sort Name Level Depth Index Index Index Name Name Arc
1 1 Start 0 0 1 1 2 Start A 1
2 2 A 1 0 2 2 3 A B 1
3 3 B 2 0 3 3 4 B C 1
4 4 C 3 0 4 4 5 C D 1
5 5 D 4 0 5 5 6 D E 1
6 6 E 5 0 6 6 7 E F 1
7 7 F 6 0 7 7 8 F G 1
8 8 G 7 0 8 8 9 G H 1
9 9 H 8 0 9 9 10 H I 1
10 10 I 9 0 10 10 11 I J 1
11 11 J 10 0 11 11 12 J K 1
12 12 K 11 0 12 11 13 J O 1
13 16 O 11 1 13 12 14 K L 1
14 13 L 12 0 14 13 15 O P 1
15 17 P 12 1 15 14 16 L M 1
16 14 M 13 0 16 15 17 P Q 1
17 18 Q 13 1 17 16 18 M N 1
18 15 N 14 0 18 17 19 Q R 1
19 19 R 14 1 19 18 21 N U 1
20 20 S 15 0 20 19 20 R S 1
21 22 U 15 1 21 20 22 S T 1
22 21 T 16 0 22 21 23 U End 1
23 23 End 17 0 23 22 23 T End 1
Project Proyesto1

Solve

Change Gantt

Critical Graph

Update Schedule

Activity Data

Critical Name Description Predecessors Color


1 1 Start Activity Start
2 0 A Activity A
3 1 B Activity B
4 0 C Activity C
5 0 D Activity D A
6 1 E Activity E A B
7 0 F Activity F B
8 0 G Activity G A B C
9 0 H Activity H B C
10 0 I Activity I C
11 0 J Activity J D
12 1 K Activity K E
13 0 L Activity L F
14 0 M Activity M G H
15 0 N Activity N H
16 0 O Activity O I
17 0 P Activity P I
18 0 Q Activity Q J K L
19 0 R Activity R J K L
20 0 S Activity S J K L
21 1 T Activity T J K L M
22 0 U Activity U N O
23 0 V Activity V P
24 0 W Activity W V
25 0 X Activity X Q
26 0 Y Activity Y Q R S
27 1 Z Activity Z T
28 0 A1 Activity AA T U W
29 0 A2 Activity BB A
30 1 A3 Activity CC Y Z
31 0 A4 Activity DD X
32 1 End Activity End
47
Times(Proj. semana)
Due 100
Critical 94
Var. 22.889
SD. 4.7842
On Time Prob. 0.8951
Slack 6
Late 0
Current 0

Activity Time Estimates Schedule Decisions


Most Time Activity Sched. Sched. Perc.
Min. Likely Max. Mean S.D. Var. semana Delay Slack Start Finish Finished
0 0 0 0 0 0 0 0 6 0 0 0%
2 4 6 4 0.6667 0.4444 4 0 10 0 4 0%
5 8 11 8 1 1 8 0 6 0 8 0%
4 9 14 9 1.6667 2.7778 9 0 14 0 9 0%
8 10 12 10 0.6667 0.4444 10 0 20 4 14 0%
7 11 15 11 1.3333 1.7778 11 0 6 8 19 0%
6 12 18 12 2 4 12 0 17 8 20 0%
12 15 18 15 1 1 15 0 14 9 24 0%
15 15 15 15 0 0 15 0 14 9 24 0%
14 20 26 20 2 4 20 0 38 9 29 0%
8 9 10 9 0.3333 0.1111 9 0 20 14 23 0%
9 18 27 18 3 9 18 0 6 19 37 0%
3 6 9 6 1 1 6 0 17 20 26 0%
4 5 6 5 0.3333 0.1111 5 0 14 24 29 0%
1 1 1 1 0 0 1 0 61 24 25 0%
5 10 15 10 1.6667 2.7778 10 0 47 29 39 0%
4 8 12 8 1.3333 1.7778 8 0 38 29 37 0%
7 14 21 14 2.3333 5.4444 14 0 13 37 51 0%
9 11 13 11 0.6667 0.4444 11 0 16 37 48 0%
8 8 8 8 0 0 8 0 19 37 45 0%
8 16 24 16 2.6667 7.1111 16 0 6 37 53 0%
6 10 14 10 1.3333 1.7778 10 0 47 39 49 0%
2 8 14 8 2 4 8 0 38 37 45 0%
11 13 15 13 0.6667 0.4444 13 0 38 45 58 0%
10 16 22 16 2 4 16 0 26 51 67 0%
14 14 14 14 0 0 14 0 13 51 65 0%
13 19 25 19 2 4 19 0 6 53 72 0%
2 4 6 4 0.6667 0.4444 4 0 38 58 62 0%
5 7 9 7 0.6667 0.4444 7 0 89 4 11 0%
22 22 22 22 0 0 22 0 6 72 94 0%
1 7 13 7 2 4 7 0 26 67 74 0%
0 0 0 0 0 0 0 0 6 94 94 0%
Project Graphic Proyesto1

Start(1) A(2) D(5) J(11) Q(18) W(24)

B(3) E(6) K(12) R(19) X(25)

C(4) F(7) L(13) S(20) Y(26)

G(8) M(14) T(21) Z(27)

H(9) N(15) U(22)

I(10) O(16) V(23)

A2(29) P(17)
A1(28) End(32)

A3(30)

A4(31)
Network Proyesto1

Activity on Node Network


Sorted Activity Nodes Sorted Precedence Arcs
From To From To Critical
Index Sort Name Level Depth Index Index Index Name Name Arc
1 1 Start 0 0 1 1 2 Start A 1
2 2 A 1 0 2 1 3 Start B 1
3 3 B 1 1 3 1 4 Start C 1
4 4 C 1 2 4 2 5 A D 1
5 5 D 2 0 5 2 6 A E 1
6 6 E 2 1 6 2 8 A G 1
7 7 F 2 2 7 2 11 A A2 1
8 8 G 2 3 8 3 6 B E 1
9 9 H 2 4 9 3 7 B F 1
10 10 I 2 5 10 3 8 B G 1
11 29 A2 2 6 11 3 9 B H 1
12 11 J 3 0 12 4 8 C G 1
13 12 K 3 1 13 4 9 C H 1
14 13 L 3 2 14 4 10 C I 1
15 14 M 3 3 15 5 12 D J 1
16 15 N 3 4 16 6 13 E K 1
17 16 O 3 5 17 7 14 F L 1
18 17 P 3 6 18 8 15 G M 1
19 18 Q 4 0 19 9 15 H M 1
20 19 R 4 1 20 9 16 H N 1
21 20 S 4 2 21 10 17 I O 1
22 21 T 4 3 22 10 18 I P 1
23 22 U 4 4 23 11 32 A2 End 1
24 23 V 4 5 24 12 19 J Q 1
25 24 W 5 0 25 12 20 J R 1
26 25 X 5 1 26 12 21 J S 1
27 26 Y 5 2 27 12 22 J T 1
28 27 Z 5 3 28 13 19 K Q 1
29 28 A1 6 0 29 13 20 K R 1
30 30 A3 6 1 30 13 21 K S 1
31 31 A4 6 2 31 13 22 K T 1
32 32 End 7 0 32 14 19 L Q 1
33 14 20 L R 1
34 14 21 L S 1
35 14 22 L T 1
36 15 22 M T 1
37 16 23 N U 1
38 17 23 O U 1
39 18 24 P V 1
40 19 26 Q X 1
41 19 27 Q Y 1
42 20 27 R Y 1
43 21 27 S Y 1
44 22 28 T Z 1
45 22 29 T A1 1
46 23 29 U A1 1
47 24 25 V W 1
48 25 29 W A1 1
49 26 31 X A4 1
50 27 30 Y A3 1
51 28 30 Z A3 1
52 29 32 A1 End 1
53 30 32 A3 End 1
54 31 32 A4 End 1