Project Management Precedences; 1 time estimate

Data Immediate Predecessors (1 per column)


Activity Time Pred 1 Pred 2
A 5
B 2A
C 4A
D 5B
E 5B
F 5C
G 2E F
H 3D
I 5G H

Results
Activity Early Start Early Finish Late Start Late Finish Slack
A 0 5 0 5 0
B 5 7 6 8 1
C 5 9 5 9 0
D 7 12 8 13 1
E 7 12 9 14 2
F 9 14 9 14 0
G 14 16 14 16 0
H 12 15 13 16 1
I 16 21 16 21 0
Project 21

Early start computations


A 0 0
B 5 0
C 5 0
D 7 0
E 7 0
F 9 0
G 12 14
H 12 0
I 16 15

Late finish computations


A B C D E F
A 21 21 21 21 21 21
B 6 21 21 21 21 21
C 5 21 21 21 21 21
D 21 8 21 21 21 21
E 21 9 21 21 21 21
F 21 21 9 21 21 21
G 21 21 21 21 14 14
H 21 21 21 13 21 21
I 21 21 21 21 21 21
5 8 9 13 14 14

Graph Critical Activit Noncritical ActSlack 10 Graph


A 0 5 0 0 9I
B 5 0 2 1 8H
C 5 4 0 0 7G
D 7 0 5 1 6F
E 7 0 5 2 5E
F 9 5 0 0 4D
G 14 2 0 0 3C
H 12 0 3 1 2B
I 16 5 0 0 1A
Gantt Chart
A
B
C
D
E
F
G
H
I
0 5 10 15 20 25
Time

Column H Critical Activity


Noncritical Activity Slack

G H I
21 21 21
21 21 21
21 21 21
21 21 21
21 21 21
21 21 21
21 21 21
21 21 21
16 16 21
16 16 21

Critical Activit Noncritical ActSlack


16 5 0 0
12 0 3 1
14 2 0 0
9 5 0 0
7 0 5 2
7 0 5 1
5 4 0 0
5 0 2 1
0 5 0 0
Project Management Precedences; 1 time estimate

Data Immediate Predecessors (1 per column)


Activity Time Pred 1 Pred 2
J 10
K 8
L 6
M 3
N 2
O 7
P 5

Results
Activity Early Start Early Finish Late Start Late Finish Slack
J 0 10 0 10 0
K 0 8 2 10 2
L 0 6 4 10 4
M 0 3 7 10 7
N 0 2 8 10 8
O 0 7 3 10 3
P 0 5 5 10 5
Project 10

Early start computations


J 0 0
K 0 0
L 0 0
M 0 0
N 0 0
O 0 0
P 0 0

Late finish computations


J K L M N O
J 10 10 10 10 10 10
K 10 10 10 10 10 10
L 10 10 10 10 10 10
M 10 10 10 10 10 10
N 10 10 10 10 10 10
O 10 10 10 10 10 10
P 10 10 10 10 10 10
10 10 10 10 10 10

Graph Critical Activit Noncritical ActSlack 8 Graph


J 0 10 0 0 7P
K 0 0 8 2 6O
L 0 0 6 4 5N
M 0 0 3 7 4M
N 0 0 2 8 3L
O 0 0 7 3 2K
P 0 0 5 5 1J
Gantt Chart

0 2 4 6 8 10 12
Time

Column H Critical Activity


Noncritical Activity Slack

P
10
10
10
10
10
10
10
10

Critical Activit Noncritical ActSlack


0 0 5 5
0 0 7 3
0 0 2 8
0 0 3 7
0 0 6 4
0 0 8 2
0 10 0 0
A B C D E F
1 Project Management/Start & End Nodes (AOA network)
Project Management Precedences; 1 time estimate

Data Immediate Predecessors (1 per column)


Activity Time Pred 1 Pred 2
A 3
B 4A
C 6A
D 6B
E 4B
F 4C
G 6D
H 8E F

Results
Activity Early Start Early Finish Late Start Late Finish Slack
A 0 3 0 3 0
B 3 7 5 9 2
C 3 9 3 9 0
D 7 13 9 15 2
E 7 11 9 13 2
F 9 13 9 13 0
G 13 19 15 21 2
H 13 21 13 21 0
Project 21

Early start computations


A 0 0
B 3 0
C 3 0
D 7 0
E 7 0
F 9 0
G 13 0
H 11 13

Late finish computations


A B C D E F
A 21 21 21 21 21 21
B 5 21 21 21 21 21
C 3 21 21 21 21 21
D 21 9 21 21 21 21
E 21 9 21 21 21 21
F 21 21 9 21 21 21
G 21 21 21 15 21 21
H 21 21 21 21 13 13
3 9 9 15 13 13

Graph Critical Activit Noncritical ActSlack 9 Graph


A 0 3 0 0 8H
B 3 0 4 2 7G
C 3 6 0 0 6F
D 7 0 6 2 5E
E 7 0 4 2 4D
F 9 4 0 0 3C
G 13 0 6 2 2B
H 13 8 0 0 1A
Gantt Chart
A
B
C
D
E
F
G
H

0 5 10 15 20 25
Time

Column H Critical Activity


Noncritical Activity Slack

G H
21 21
21 21
21 21
21 21
21 21
21 21
21 21
21 21
21 21

Critical Activit Noncritical ActSlack


13 8 0 0
13 0 6 2
9 4 0 0
7 0 4 2
7 0 6 2
3 6 0 0
3 0 4 2
0 3 0 0