You are responsible for managing a project.

On a separate paper, draw a project network given the


information below. Complete the forward and backward pass, compute activity slack, and determine the
Then, use the results to complete the table provided below, save
project duration.
the file and then submit it on E-learning.
Activity ID Duration Finish-to-Start Finish-to-Start Additional Lag Lag
Predecessor Lag Relationships
A 4 None 0 Start-Start A to D 4
B 7 A 0 None 0
C 5 A 0 None 0
D 4 None 0 None 0
E 4 B 0 None 0
C 5
F 7 D 0 Finish-Finish F to G 5
G 6 C 4 None 0
H 5 E 0 None 0
I 6 F 0 Finish-Finish I to J 7
J 4 H 0 None 0
G 6

Student Name Amal ghrouz


Registration number 0178897

Activity ID ES EF LS LF SLK (Start) SLK (Finish)


A 0 4 0 4 0 0
B 4 11 10 17 6 6
C 4 9 5 10 1 1
D 4 8 4 8 0 0
E 17 18 17 21 3 3
F 8 15 8 15 0 0
G 13 20 14 20 1 0
H 18 23 21 26 3 3
I 15 21 17 23 2 2
J 26 30 26 30 0 0

Project Duration 30