On a separate paper, draw a project network given the
information below. Complete the forward and backward pass, compute activity slack, and determine the Then, use the results to complete the table provided below, save project duration. the file and then submit it on E-learning. Activity ID Duration Finish-to-Start Finish-to-Start Additional Lag Lag Predecessor Lag Relationships A 4 None 0 Start-Start A to D 4 B 7 A 0 None 0 C 5 A 0 None 0 D 4 None 0 None 0 E 4 B 0 None 0 C 5 F 7 D 0 Finish-Finish F to G 5 G 6 C 4 None 0 H 5 E 0 None 0 I 6 F 0 Finish-Finish I to J 7 J 4 H 0 None 0 G 6
Student Name Amal ghrouz
Registration number 0178897
Activity ID ES EF LS LF SLK (Start) SLK (Finish)
A 0 4 0 4 0 0 B 4 11 10 17 6 6 C 4 9 5 10 1 1 D 4 8 4 8 0 0 E 17 18 17 21 3 3 F 8 15 8 15 0 0 G 13 20 14 20 1 0 H 18 23 21 26 3 3 I 15 21 17 23 2 2 J 26 30 26 30 0 0