You are on page 1of 2

Quiz 3

Operations Management

Section G2

Miss Mehreen Rahmani

Name: Muhammad Noyan

Roll Number: 17U00599

1) CPM method is being used here. Activity time is given on each node.

Activity Time Preceding Task


A 5 -
B 3 -
C 11 A
D 4 -
E 7 B
F 6 D
G 4 B
H 3 D
I 5 G,F
J 6 C,E,H
K 4 J

a. Calculate ES, EF, LS, LF


b. Identify the activities on the critical path.
c. What is the duration of the critical path?
d. Calculate the amount of slack time at activity H.
e. If activity I were delayed by eight time units, what would be the impact on the project duration?

2) Identify the techniques for improving service productivity by applying them to Uber.

3) What is the objective of critical path analysis?

Q1.
CODE TIME ES EF LS LF SLACK
TIME
A 5 0 5 0 5 0
B 3 0 3 6 9 6
C 11 5 16 5 16 0
D 4 0 4 9 13 9
E 7 3 10 9 16 6
F 6 4 10 15 21 11
G 4 3 7 15 21 14
H 3 4 7 13 16 9
I 5 10 15 21 26 10
J 6 16 22 16 22 0
Quiz 3

K 4 22 26 22 26 0

Critical Path

A -> C-> J -> K Time duration 26min

Slack time of H is 9

I can have early start of 10 and late start of 21, so delay of 10 would not matter in the process

Q3.

Critical path analysis shows that which path is the most important in the whole process and can not be
delayed or any delay in that particular process path can cause the overall project delay.