Professional Documents
Culture Documents
You are working on a project to develop Lab Management application. This application is to help students to improve their programming skills.
It would include the following capabilities:
Allow students to register for university-sponsored Lab classes such as C++ programming, Java Programming, Java Desktop
Programming, Java Web Programming, .NET Programming, Python programming classes.
Allow students to submit their work in the Lab class and to track their progress.
Allow teacher to manage his classes and to evaluate his students submitted work, to approve or to reject the work.
Allow teacher to generate the final report of his classes at the end of the semester.
Assume that the Level 1 category is called Software Project, and that the Level 2 categories are Initiating, Planning, Executing, Monitoring and
Controlling, and Closing. Under the Executing section, include Level 3 categories of Analysis, Design, Prototyping, Testing, Implementation, and
Support. The Support category includes Level 4 items for Training, Documentation, User Support, and Enhancements
Answer:
Request 2 - Deliverables
Identify at least five milestones mapped to the main deliverables for the project. For each milestone, write a short explanation of how to
measure its status completed or not.
All the requirements collected from the customer and baseline (Tất cả các yêu cầu thu thập từ khách hàng và đường cơ sở)
Planning completed:
Project approved and signed off for execution . project plan is ready ( Dự án được phê duyệt và ký kết để thực hiện. kế hoạch
dự án đã sẵn sàng)
- The design is approved by stakeholders (Thiết kế được chấp thuận bởi các bên liên quan)
Complete Development()
- All coding related work completed (Tất cả các công việc liên quan đến mã hóa đã hoàn thành)
Complete Testing ()
- The whole functionality is successfully tested and the reported defects fixed (Toàn bộ chức năng được kiểm tra thành
- All work as per scope is completed(Tất cả các công việc theo phạm vi được hoàn thành)
Training ()
- Training activities such as knowledge transfer to an operations team (Các hoạt động đào tạo như chuyển giao kiến thức
- The completed software and documentation provided to client to begin using (Phần mềm và tài liệu hoàn chỉnh được
Draw a network diagram and identify the project duration by applying critical path analysis
Answer:
ES Activity EF
LS Duration LF
4 C 5 6 E 14
2 2
6 2 7 8 9 16 17 H 22
0
23 J 30
4 B 6 7 F 16 17 6 22
1 A 3
0 0 End
0 9 I 10
Start 0
23 8 30
4 3 6 7 10 16
1 3 3 12
4 D 5 21 2 22
6 G 8
8 8
12 2 13 14 3 16
Define at least two solutions ordered by the choosing priority and include relevant explanation how it will help your project to be developed
faster to accomplish on time.
Using the LEAD – The successor can start BEFORE the predecessor completes ( decreases the amount of time between 2 actitvities) the next
actitvity can start 3 days before the predecessor completes (Prioritize activities that take more time and other activities that are dependent on
that activities ).
(kế vị có thể bắt đầu TRƯỚC KHI người tiền nhiệm hoàn thành)
Hire temporary members to speed up the completion of an activity ,and then make project to be developed faster
Request 5 – Cost Evaluation
Your project is scheduled for 5 years. There are six different teams working on five major functional areas. Some teams are ahead of schedule
while others are falling behind. There are cost overruns in some areas but you’ve also saved costs in others. Due to all this, it is difficult to
understand whether you are over or under budget. At the end of the month fifteenth of the project, while the total project budget is
$8,400,000, you’ve already spent $2,650,000. CPI is 0.95. Can you perform Earn Value management technique to analyze and determine the
status of your project and give some prediction about schedule and cost of the project at accomplishment date. Assume that, in your baseline,
you assigned the value of work to be completed each month in equal.
Schedule variance(SV)
Anegative cost variance means you are not on budget , you are over budget (under budget)
Key deliveries