Professional Documents
Culture Documents
NAME :
CLASS :
PMP Lesson 7
DATE :
16 Questions
a) Use product analysis techniques such as b) Decompose the system development work
product breakdown and systems analysis package now and decompose the system
to decompose the system testing work testing work package later
package
c) Break down the project into multiple d) Consult the project management plan to
phases so that the system testing work determine what to do in this situation
package goes into the second project
phase
2. The project manager and the team decide that the project
will be divided into ve-week iterations with two weeks in
between for retrospectives and iteration planning. Where is
this documented?
https://quizizz.com/print/quiz/5e8df1355aeedf001f2cc601 1/7
11/24/2020 PMP Lesson 7 | Print - Quizizz
a) Refund the customer for the value of the b) Begin the claims administration process
deliverable
c) Ask the project team to repair the defect d) Submit a change request to x the
deliverable
https://quizizz.com/print/quiz/5e8df1355aeedf001f2cc601 2/7
11/24/2020 PMP Lesson 7 | Print - Quizizz
a) Fund the project with equity since there b) Select the self-funding option since it
are no dividend obligations provides the lowest cost of capital
c) Recommend the termination of the project d) Perform an alternatives analysis since
since another project has a higher NPV there are multiple factors to consider
a) Make changes to activity duration and b) Ask the project team members to meet the
schedule incorporating the changed original schedule by putting in overtime, if
competency levels required
c) Inform the customer that the project is d) Make no changes to the schedule
behind schedule
https://quizizz.com/print/quiz/5e8df1355aeedf001f2cc601 3/7
11/24/2020 PMP Lesson 7 | Print - Quizizz
a) Resources b) Quality
c) Schedule d) Cost
a) 35 days b) 34 days
c) 33 days d) 32 days
https://quizizz.com/print/quiz/5e8df1355aeedf001f2cc601 4/7
11/24/2020 PMP Lesson 7 | Print - Quizizz
15. You have presented a unique and veri able product to your
customers for their approval. Approval of this product may
allow you to move on to your next phase. This unique and
veri able product is also known as:
a) A portfolio b) A deliverable
c) A project d) A plan
https://quizizz.com/print/quiz/5e8df1355aeedf001f2cc601 5/7
11/24/2020 PMP Lesson 7 | Print - Quizizz
a) Analyze the change‘s impact of the change b) Talk to the customer about the impact of
with the team the change
c) Change the risk management plan d) Include the expected monetary value of
the risk in the new cost estimate
https://quizizz.com/print/quiz/5e8df1355aeedf001f2cc601 6/7
11/24/2020 PMP Lesson 7 | Print - Quizizz
Answer Key
1. b 5. c 9. d 13. a
2. a 6. d 10. c 14. c
3. d 7. b 11. d 15. b
4. a 8. a 12. b 16. a
https://quizizz.com/print/quiz/5e8df1355aeedf001f2cc601 7/7