ENGINEERING MANAGEMENT
(GE 404)

TUTORIAL # 7
PROJECT TIME CONTROL

GE 404 (Engineering Management) 12/26/21


Measure and Report Progress
Methods
Methods
 Estimatednumber
Estimated numberof
ofworking
workingdaysdaysreq.
req.totocomplete
completethe
theactivity.
activity.
 Estimated%
Estimated %completion
completionof
ofthe
theactivity.
activity.
 Quantitiesof
Quantities ofwork
workunits
unitsput
putininplace.
place.
Equations
Equations
 Working
 Workingdays
daysto
tocomplete
complete==dd(1
(1--P/100)
P/100)
 Working
 Workingdays
daysto
tocomplete
complete==dd(1
(1––(W/T))
(W/T))
Where
Where
d=total
d= totalactivity
activityduration
durationininworking
workingdays
days
PP==estimated
estimatedpercentage
percentageof ofcompletion
completion
W=number
W= numberof ofwork
workunits
unitsput
putinto
intoplace.
place.
T=total
T= totalnumber
numberof ofwork
workunits
unitsassociated
associatedwith
withthe
theactivity.
activity.

Basedon
Based onthe
theassumption
assumptionof
ofstraight-line
straight-linevariation
variation
betweentime
between timeand
andwork
workaccomplishment
accomplishment
GE 404 (Engineering Management) 12/26/21
Example1:
3

The initial AON diagram for a small engineering project is shown below with
its planned activity times in weeks.
At the end of the 5th week, the field progress report gives you the following
information:
 Activities “B, C, D and E” have been completed on schedule.
 Activity “F” is ready to start at the beginning of the week 6.
 Remaining duration of activity “H” is 4 weeks.
 Remaining duration of activity “I” is 3 weeks.
 Activity “G” will not start until end of week 7.
 Volume of work in activity “L” has been increased by 33% approximately.
 Activity “J” has been omitted
 It is decided to shorten activity “K” by 2 weeks.
Construct the updated schedule indicating the critical path and showing new
activities times.
2 2 4
E
14 16

0 2 2 2 6 8 8 2 10
B F J
3 5 5 11 16 18

0 0 0 0 5 5 5 6 11 11 7 18 18 2 20
START C G K N
0 0 0 5 5 11 11 18 18 20

0 3 3 3 6 9 9 3 12
D H L
6 9 9 15 15 18

3 4 7 9 2 11
I M
12 16 16 18
GE 404 (Engineering Management) 12/26/21
At the end of the 5th week, the field progress report gives you the following information:
 Activities “B, C, D and E” have been completed on schedule.
0
E

0 2 6 8 8 2 10
B F J
5 11 16 18

0 0 0 0 5 6 11 11 7 18 18 2 20
START C G K N
0 0 5 11 11 18 18 20

0 3 6 9 9 3 12
D H L
9 15 15 18

3 4 7 9 2 11
I M
12 16 16 18

GE 404 (Engineering Management) 12/26/21


At the end of the 5th week, the field progress report gives you the following information:
 Activity “F” is ready to start at the beginning of the week 6.

0
E

LIVE
0 5 6 11 11 2 13
B F J
5 11 16 18

0 0 0 0 5 6 11 11 7 18 18 2 20
START C G K N
0 0 5 11 11 18 18 20

0 3 6 9 9 3 12
D H L
9 15 15 18

3 4 7 9 2 11
I M
12 16 16 18
GE 404 (Engineering Management) 12/26/21
At the end of the 5th week, the field progress report gives you the following information:
 Remaining duration of activity “H” is 4 weeks.

0
E

LIVE
0 5 6 11 11 2 13
B F J
5 11 16 18

0 0 0 0 5 6 11 11 7 18 18 2 20
START C G K N
0 0 5 11 11 18 18 20

LIVE
0 5 4 9 9 3 12
D H L
9 15 15 18

3 4 7 9 2 11
I M
12 16 16 18
GE 404 (Engineering Management) 12/26/21
At the end of the 5th week, the field progress report gives you the following information:
 Remaining duration of activity “I” is 3 weeks.

0
E

LIVE
0 5 6 11 11 2 13
B F J
5 11 16 18

0 0 0 0 5 6 11 11 7 18 18 2 20
START C G K N
0 0 5 11 11 18 18 20

LIVE
0 5 4 9 9 3 12
D H L
9 15 15 18

LIVE
5 3 8 9 2 11
I M
12 16 16 18
GE 404 (Engineering Management) 12/26/21
At the end of the 5th week, the field progress report gives you the following information:
 Activity “G” will not start until end of week 7.

0
E

LIVE
0 5 6 11 11 2 13
B F J
7 13 18 20

0 0 0 0 7 6 13 13 7 20 20 2 22
START C G K N
0 0 7 13 13 20 20 22

LIVE
0 5 4 9 9 3 12
D H L
13 17 17 20

LIVE
Remark: 5 3 8 9 2 11
As G start late, this affect times all I M
activities successors and reflect on times
15 18 18 20
GE 404 (Engineering Management) 12/26/21
At the end of the 5th week, the field progress report gives you the following information:
 Volume of work in activity “L” has been increased by 33% approximately.

0
E

LIVE
0 5 6 11 11 2 13
B F J
7 13 18 20

0 0 0 0 7 6 13 13 7 20 20 2 22
START C G K N
0 0 7 13 13 20 20 22

LIVE
0 5 4 9 9 4 13
D H L
13 17 17 20

LIVE
5 3 8 9 2 11
I M
15 18 18 20
GE 404 (Engineering Management) 12/26/21
At the end of the 5th week, the field progress report gives you the following information:
 Activity “J” has been omitted

0
E

LIVE
0 5 6 11 0
B F J
7 13

0 0 0 0 7 6 13 13 7 20 20 2 22
START C G K N
0 0 7 13 13 20 20 22

LIVE
0 5 4 9 9 4 13
D H L
13 17 17 20

LIVE
5 3 8 9 2 11
I M
15 18 18 20
GE 404 (Engineering Management) 12/26/21
At the end of the 5th week, the field progress report gives you the following information:
 It is decided to shorten activity “K” by 2 weeks.

0
E

LIVE
0 5 6 11
B F
J
7 13

0 0 0 0 7 6 13 13 5 18 18 2 20
START C G K N
0 0 7 13 13 18 18 20

LIVE
0 5 4 9 9 4 13
D H L
11 15 15 18

Remark: LIVE
As k duration is reduced, this affect 5 3 8 9 2 11
times all activities successors and reflect I M
on times 13 16 16 18
GE 404 (Engineering Management) 12/26/21
Modified AON at the end of the 5th week, after adjusting changes

5 6 11

B F
J
7 13

0 0 0 7 6 13 13 5 18 18 2 20
START G K N
C
0 0 7 13 13 18 18 20

5 4 9 9 4 13
H L
D
11 15 15 18

Critical Path: 5 3 8 9 2 11
G,K,N I M
13 16 16 18

GE 404 (Engineering Management) 12/26/21


Thank You
14

Questions Please

GE 404 (Engineering Management) 12/26/21