MANNAR WIND POWER PROJECT

DAY AHEAD REQUEST FOR INSPECTIONS LIST - Rev -2


Inspection Request List for 9/6/2020 Submitted to : Vestas Wind Sri Lanka Submitted On: 9/6/2020

Involved Field Location Scheduled Date/Time


Contractor/ Responsible
Ref/ no Sub Field Inspection description officer's name (contact)

06.00-
Civil/Elec/Mech Zone Element Date
18.00 Hrs

LABORATORY ACTIVITIES

ACC/MWPP/PC/WALL/24(28 days)
AACC/MWPP/MA/CON/144(7 days),
1 MWPP-ACC-CN-8871 Civil CN Project Laboratary Concrete cube crushing test 6/9/2020 09.00 onwards Access Eng/Anjana(ME)

2 MWPP-ACC-CN-8872 Civil CN WTG 9, WTG18 Bird radar system DCP testing 6/9/2020 9.00 Access Eng/Anjana(ME)

HARDSTAND ACTIVITIES