than the approved EIA and EMP themselves, are also to be executed I implemented

I followed during project execution. Consultant will devise ways and strategies for
the effective monitoring of the additional aforesaid conditions.

3 Study and review of contract agreement of the contractor

The consultant will go through the relevant section of contract agreement of the
contractor on Environmental Compliance and his environmental obligations under
the contract.

4 Environmental monitoring

Consultant will monitor on site implementation of EMP (provided with the EIA)
and the additional conditions given by Pak-EPA and/or provincial EPAs (for the
project work executed in their jurisdiction). With respect to the environmental
monitoring, the consultant will examine/monitor in detail, following points during
the project construction/execution period.

Contractor's health and safety staff

Ali, please The consultant will examine whether appropriate Health and Safety staff has been
see this hired by the contractor. Examine plans and methodology of contractor to ensure
section. compliance will all environmental measures included in his contract agreement and
Kindly mandatory under EIA report, EMP and EIA approval letter.
provide
these NEQS compliance
documents For the project under study, it will be examined that whether the contractor has
ensured compliance of National Environmental Quality Standards (NEQS) related
to sewage discharge, air emissions, ambient air and solid waste management.

Implementation of mitigation measures


It will be examined that the mitigation measures suggested in the EIA report and
Environmental Management Plan (EMP) are being executed in true spirit,
including the additional conditions set forth by each provincial EP As (for the
project work executed in their jurisdiction) and /or Pak-EPA.

Compensation for losses


It will be examined that whether compensation were provided or not where
necessary such as in case ofloss of property, shops, business etc in accordance with
the rates that are agreed upon.

Sanitation during construction and operation phases


Measures to be taken for effective sanitation will be monitored during construction
and operation phases.

Landscaping
As per the conditions laid by EPA, the proponent shall allocate 1% of the total cost
of the project for tree plantation along roadside and shall plant trees especially of