COST COMPUTATION:

MATERIAL COSTING
DIRECT
STRUCTURE qty unit MATERIALS QTY UNIT PRICE COST DIRECT COST
PRICE
1.44 sq.m CHB 6" 18.00 pcs 35.00 31.25 630.00 562.50
1.44 sq.m Cement 0.83 bags 230.00 205.36 191.27 170.78
1.44 sq.m Sand 0.11 cu.m 700.00 625.00 77.62 69.30
1.44 sq.m tie.wire 0.06 kg 40.00 35.71 2.42 2.16
Exterior wall 1.44 sq.m rebar 2.96 kg 35.00 31.25 103.57 92.48
1.44 sq.m Alignmentkey 16.20 pcs 7.00 6.25 113.40 101.25
1.44 sq.m Delivery charge 18.00 pcs 10.50 9.38 189.00 168.75

1.44 sq.m CHB 4" 18.00 pcs 32.00 28.57 576.00 514.29
1.44 sq.m Cement 0.65 bags 230.00 205.36 149.04 133.07
1.44 sq.m Sand 0.09 cu.m 700.00 625.00 60.48 54.00
1.44 sq.m tie.wire 0.06 kg 40.00 35.71 2.42 2.16
Interior wall 1.44 sq.m rebar 2.96 kg 35.00 31.25 103.57 92.48
1.44 sq.m Alignmentkey 16.20 pcs 7.00 6.25 113.40 101.25
1.44 sq.m Delivery charge 18.00 pcs 8.15 7.28 146.70 130.98

1.44 sq.m Cement 0.68 bags 230.00 205.36 156.49 139.73


Plastering
1.44 sq.m Sand 0.04 cu.m 700.00 625.00 26.46 23.63
25mm thk
- -
1.44 sq.m skim coat 0.16 bags 360.00 321.43 59.25 52.90
Skim Coat
- - -
Diamond 1.44 sq.m render 0.42 bags 680.00 607.14 288.00 257.14
Render (8mm 1.44 sq.m finish coat 0.13 bags 500.00 446.43 65.45 58.44
thk) - - -

- - -
- - -
- - -
DIRECT
DIRECT COST Cost / unit
Cost / unit
562.50 437.50 390.63
170.78 132.83 118.59
69.30 53.90 48.13
2.16 1.68 1.50
92.48 71.93 64.22
101.25 78.75 70.31
168.75 131.25 117.19
907.83 810.56
514.29 400.00 357.14
133.07 103.50 92.41
54.00 42.00 37.50
2.16 1.68 1.50
92.48 71.93 64.22
101.25 78.75 70.31
130.98 101.88 90.96
799.73 714.04
139.73 108.68 97.03
23.63 18.38 16.41
- 127.05 113.44
52.90 41.14 36.73
- 41.14 36.73
257.14 200.00 178.57
58.44 45.45 40.58
- 245.45 219.16

-
-
-
GROSS AREA TO
DEDUCT NET AREA UNIT
L x H AREA
140mm CHB (Exterior) 160.59 sq.m

FRONT ELEV:
GROUND FLOOR: 5.26 x 3.55 = 18.67 - 4.77 x 1 Floor 13.90 sq.m

LEFT SIDE ELEVATION:


GROUND FLOOR: x 3.55 = - - - x 1 Floor - sq.m

RIGHT SIDE ELEVATION:


GROUND FLOOR: x 3.55 = - - - x 1 Floor - sq.m

REAR SIDE ELEVATION:


GROUND FLOOR: 5.26 x 3.55 = 18.67 - 4.74 x 1 Floor 13.93 sq.m

Fire Wall
Left - Firewall 7.00 x = 60.80 - - x 1 Item 60.80 sq.m
Right Firewall 7.00 x = 71.95 - - x 1 Item 71.95 sq.m

x = - - - x 1 Floor - sq.m

Total Length of Wall 24.52 24.52 m

GROSS AREA TO NET AREA UNIT


L x H AREA DEDUCT
110mm CHB 86.35 sq.m

FRONT ELEV:
5.26 x 3.33 = 17.52 - 4.50 x 1 Floors 13.02 sq.m

LEFT SIDE ELEVATION:


x = - - - x 1 Floors - sq.m

Rear ELEV:
5.26 x 2.50 = 13.15 - 2.79 x 1 Floors 10.36 sq.m
x = - - - x 1 Floors - sq.m

Right SIDE ELEVATION:


x = - - - x 1 Floors - sq.m

PARTITION WALL
GROUND FLOOR: 5.50 x 3.55 = 19.53 - 2.94 x 1 Floor 16.59 sq.m
2ND FLOOR: 12.60 x 3.00 = 37.80 - - x 1 Floor 37.80 sq.m

1.5m Height Fence 5.73 x 1.50 = 8.59 - - x 1 Item 8.59 sq.m

Dry Wall
Dry Wall x = - - - x 5 Unit - sq.m
x = - - x 5 Unit - sq.m
CONCRETING WORKS
Height / Length / No. of Area Volume Surface
Description Base
Depth Height Item (sq.m) (cu.m) Area
FOUNDATION WORKS
Excavation
Footing 0 -
TB 0 -
WF-1 0.5 0.6 35.75 0.3 10.73
10.73
Fill & Complaction
Footing
WF-1 2.86
2.86
Gravel Bedding
WF-1 0.5 0.05 35.75 0.89
SOG 0.05 35.77 1.79
2.68
Concreting
Footing
F1 0 -
WF-1 0.5 0.2 35.75 0.1 3.58
3.58
BEAMS AND COLUMNS

Column
C1 0 - 0.20
0 - 0.20
- 0.40
Beam
B1 0.15 0.2 5.76 1 0.864 0.17 3.27
B1 0.15 0.2 3.7 1 0.555 0.11 2.14
0 -
0 -
0 0.28 -
SLAB: SOG & SUSPENDED SLAB
Ground floor
Close Area 0.15 35.77 5.37
ServiceArea -
Lanai -
Carport -
Porch -

2nd Floor
Close Area 0.15 34.34 5.15
Ledge -
5.15
30.26 deg. Inclination
Length Pcs
C- purlins 5.3 15 = 79.5
1.6 10 = 16
2.4 3= 7.2
102.7

Gutter 5.3 2= 10.6


11 1= 11
21.6

Rafter 10.2 1= 10.2

Sagrod 10.2 2= 20.4


4.5 2= 9
29.4 46.40026

Insulation 0.863747 58.53 = 67.7629

GI sheet 0.863747 19.35 = 22.40239


0.863747 22.92 = 26.53555

136.37 sq.m
COST COMPUTATION:

MATERIAL COSTING
DIRECT
STRUCTURE qty unit MATERIALS QTY UNIT PRICE COST DIRECT COST
PRICE
1.44 sq.m CHB 6" 18.00 pcs 35.00 31.25 630.00 562.50
1.44 sq.m Cement 0.83 bags 230.00 205.36 191.27 170.78
1.44 sq.m Sand 0.11 cu.m 700.00 625.00 77.62 69.30
1.44 sq.m tie.wire 0.06 kg 40.00 35.71 2.42 2.16
Exterior wall 1.44 sq.m rebar 2.96 kg 35.00 31.25 103.57 92.48
1.44 sq.m Alignmentkey 16.20 pcs 7.00 6.25 113.40 101.25
1.44 sq.m Delivery charge 18.00 pcs 10.50 9.38 189.00 168.75

1.44 sq.m CHB 4" 18.00 pcs 32.00 28.57 576.00 514.29
1.44 sq.m Cement 0.65 bags 230.00 205.36 149.04 133.07
1.44 sq.m Sand 0.09 cu.m 700.00 625.00 60.48 54.00
1.44 sq.m tie.wire 0.06 kg 40.00 35.71 2.42 2.16
Interior wall 1.44 sq.m rebar 2.96 kg 35.00 31.25 103.57 92.48
1.44 sq.m Alignmentkey 16.20 pcs 7.00 6.25 113.40 101.25
1.44 sq.m Delivery charge 18.00 pcs 8.15 7.28 146.70 130.98

1.44 sq.m Cement 0.52 bags 230.00 205.36 119.23 106.46


Plastering
20mm thk 1.44 sq.m Sand 0.03 cu.m 700.00 625.00 20.16 18.00
- -
1.44 sq.m skim coat 0.16 bags 360.00 321.43 59.25 52.90
Skim Coat
- - -
Diamond 1.44 sq.m render 0.42 bags 680.00 607.14 288.00 257.14
Render (8mm 1.44 sq.m finish coat 0.13 bags 500.00 446.43 65.45 58.44
thk) - - -

- - -
- - -
- - -
DIRECT No. of Total Labor
DIRECT COST Cost / unit Man Hour Rate
Cost / unit Workers Cost
562.50 437.50 390.63
170.78 132.83 118.59
69.30 53.90 48.13
2.16 1.68 1.50
92.48 71.93 64.22
101.25 78.75 70.31
168.75 131.25 117.19
907.83 810.56
514.29 400.00 357.14
133.07 103.50 92.41
54.00 42.00 37.50
2.16 1.68 1.50
92.48 71.93 64.22
101.25 78.75 70.31
130.98 101.88 90.96
799.73 714.04
106.46 82.80 73.93
18.00 14.00 12.50
- 96.80 86.43
52.90 41.14 36.73
- 41.14 36.73
257.14 200.00 178.57
58.44 45.45 40.58
- 245.45 219.16

-
-
-
Description
Labor Skilled Coverage Rate / Unit
Work Descriptiom Unit Rate / Unit
450 500 / day (LESS 12%)

Earth Works
a.)Lay-Out and Staking 3.00 1.00 100.00 sq.m 19.00 16.96
b.)Excavation Work 1 1 cu.m 450.00 401.79
c Fill & Compaction 1 9.76 cu.m 47.00 41.96
d Gravel Bedding 1 6 cu.m 75.00 66.96
-
Concrete Works - -
Slab on Grade 1 1 1.6 cu.m 594.00 530.36
Column 1 1 6.8 cu.m 140.00 125.00
Beams 1 1 5.2 cu.m 183.00 163.39
Suspended Slab 1 1 4.8 cu.m 198.00 176.79
- -
Formworks - -
Fabrication 1 1 14.88 sq.m 64.00 57.14
Stripping:
Beams 2 15.6 sq.m 58.00 51.79
Column 2 18.8 sq.m 48.00 42.86
Slab 2 14.8 sq.m 61.00 54.46

Reinforcement
Fabrication 2 150 kg 7.00 6.25
Installation 1 1 111 kg 9.00 8.04
Steel Deck 1 2 15 sq.m 97.00 86.61

Metal Works
Structural Steel 1 1 160 kg 6.00 5.36
Fabrication of anchor bolts 1 1 80 kg 12.00 10.71
Installation of anchor bolts 1 1 24 kg 40.00 35.71
Fabrication of embbeded Items 1 1 56 kg 17.00 15.18

Painting Works
Any Pain 1 1 27.84 sq.m 35.00 31.25
Varnish 1 1 18.56 sq.m 52.00 46.43
Structural Steel frame 1 1 160 lm 6.00 5.36

Tinsmithing
Corr. G.I. Sheet (Lifting) 4 40 sq.m 45.00 40.18
Corr. G.I. Sheet (Installation) 1 2 40 sq.m 37.00 33.04
Gutter (Cut & Shape) 1 52.16 lm 10.00 8.93
Downspout (out & Shape) 1 52.16 lm 10.00 8.93
Downspout (Installation) 1 1 52.16 lm 19.00 16.96
Installation of Inulation Material 1 1 40 sq.m 24.00 21.43

Block Laying
4" CHB ordinary 1 1 12 sq.m 80.00 71.43
6" CHB ordinary 1 1 10 sq.m 95.00 84.82
8" CHB ordinary 1 1 8 sq.m 119.00 106.25

4" CHB smart 1 1 18 sq.m 53.00 47.32


6" CHB smart 1 1 15 sq.m 64.00 57.14
8" CHB smart 1 1 12 sq.m 80.00 71.43

Dry Wall 2 2 23 sq.m 83.00 74.11

PVC Groove Guide 2 35 sq.m 26.00 23.21

Grout 1 1 10 sq.m 95.00 84.82

Plaster Works 1 1 5 sq.m 190.00 169.64


Skimcoat 1 1 7.5 sq.m 127.00 113.39
Diamond Render 1 1 10 sq.m 95.00 84.82
Render Finish Coat 1 1 50 sq.m 19.00 16.96

Tile Works
Glaze Tile 1 1.52 sq.m 329.00 293.75
Unglaze Tile 1 1.84 sq.m 272.00 242.86
Vinyl floor tiles 1 2 sq.m 250.00 223.21

Ceiling Works
Frame Work 1 2 20 sq.m 73.00 65.18
Facia 1 1 20 sq.m 48.00 42.86
Ceiling Works 1 2 15 sq.m 97.00 86.61

Sealant
Sealant application 1 90 lm 6.00 5.36
block laying 53
rebar 30.6
grouting 95
Catch Basin Cost Computation

Unit Cost Total Cost Labor Cost Total Labor


Smart Block 8 pcs 34.00 272.00 53 33.92
plaster 1.35 sq.m 366.60 130.00 190 256.50
rebar 5.92 kg 27.00 159.84 9 53.28
slab 0.016 cu.m 3,650.00 58.40 594 9.50
620.24 353.20

Stair Railings