TIMELINESS
SN ACTIVITY MIN. CD FOR
DURATION START FINISH
ACTIVITY

A. PROCUREMENT PROCESS
A.1 Bid Preparation 60 days 10 02-Feb-18 02-Apr-18

A.2 Pre-Procurement Conference Day 0 1 17-Jul-19 17-Jul-19

A.3 AD/Posting ITB Day 1 to 7 7 19-Jul-19 26-Jul-19

A.4 Pre-Bid Conference Day 8 1 27-Jul-19 27-Jul-19

A.5 Submission and Receipts of Bids Day 1 to 20 20 19-Jul-19 12-Aug-19

A.6 Opening of Bids Day 20 1 13-Aug-19 13-Aug-19

A.7 Bid Evaluation Day 21 to 27 7 14-Aug-19 20-Aug-19

A.8 Post Qualification Day 22 to 29 8 21-Aug-19 28-Aug-19


Approval of Resolution/Issuance of
Day 25 to 31 7 29-Aug-19 04-Sep-19
A.9 Notice of Award
A.10 Contract Preparation and Signing Day 26 to 35 10 30-Aug-19 08-Sep-19

A.11 Issuance of Notice to Proceed Day 27 to 33 7 04-Sep-19 04-Sep-19


TOTAL NUMBER OF DAYS = 69

B. CONSTRUCTION/ IMPLEMENTATION
B.1 Mobilization Day 34 to 36 3 05-Sep-19 07-Sep-19
B.2 Implementation Day 37 to 112 75 06-Sep-19 19-Nov-19
B.3 Pre-Final Inspection/Punchlisting Day 105 1 12-Nov-19 12-Nov-19
B.4 Final Inspection Day 113 1 20-Nov-19 20-Nov-19
B.5 Acceptance Day 114 to 118 5 21-Nov-19 25-Nov-19

Prepared by: Approved by:

JOSEPH A. HERALDO HON. RODEL T. ESPIRITU


Muncipal Engineer/ Local Chief Executive/
BAC Chairman Head of Procuring Entity