TIMELINESS
SN ACTIVITY MIN. CD FOR
DURATION START FINISH
ACTIVITY
A. PROCUREMENT PROCESS
A.1 Bid Preparation 60 days 10 02-Feb-18 02-Apr-18
B. CONSTRUCTION/ IMPLEMENTATION
B.1 Mobilization Day 34 to 36 3 05-Sep-19 07-Sep-19
B.2 Implementation Day 37 to 112 75 06-Sep-19 19-Nov-19
B.3 Pre-Final Inspection/Punchlisting Day 105 1 12-Nov-19 12-Nov-19
B.4 Final Inspection Day 113 1 20-Nov-19 20-Nov-19
B.5 Acceptance Day 114 to 118 5 21-Nov-19 25-Nov-19