Professional Documents
Culture Documents
Province of Quezon
MUNICIPALITY OF JOMALIG
DETAILED ESTIMATES
LGU COUNTERPART TO DOST-REHABILITATION OF LIVELIHOOD BUILDING PHASE 2
BRGY. TALISOY, JOMALIG, QUEZON
` Sub-Total 3,000.00
Profit 10% 300.00
OCM 15% 450.00
VAT 5% 187.50
TOTAL OF ITEM I = 3,937.50
UNIT COST= 3,937.50 /LOT
II.ROOF FRAMING/TINSMITHRY
Estimated Quantity : LUMPSUM= 1.00 LOT
A. MATERIAL EXPENSE
A1. Bill of Materials
Good lumber 650.00 bd.ft. 35.00 /bd.ft. 22,750.00
Pre-painted longspan 45.00 sq.m. 360.00 /sq.m. 16,200.00
ribtype roofing
Texscrew 650.00 pcs 5.00 /pc 3,250.00
A2. Material Cost 42,200.00
B. LABOR EXPENSE
B1. Manpower Composition
1 Foreman @ Php700.00/day X 6 days = 4,200.00
1 First Aider @ Php500.00/day X 6 days = 3,000.00
2 Mason-Carpenter @ Php550.00/day X 6 days = 6,600.00
2 Helper @ Php350.00/day X 6 days = 4,200.00
B2. Labor Cost 18,000.00
Sub-Total 60,200.00
Profit 10% 6,020.00
OCM 15% 9,030.00
VAT 5% 3,762.50
TOTAL OF ITEM IVI= 79,012.50
UNIT COST= 79,012.50 /LOT
III.PLUMBING/SANITARY WORKS
Estimated Quantity : LUMPSUM= 1.00 LOT
A. MATERIAL EXPENSE
A1. Bill of Materials
PVC Pipes and fittings 1.00 lot 10,000.00 /lot 10,000.00
Stainless kitchen sink 4.00 sets 1,200.00 /set 4,800.00
Toilet bowl 1.00 pcs 1,200.00 /pc 1,200.00
Strainer 3.00 pcs 120.00 /pc 360.00
Consumables 1.00 lot 1,500.00 /lot 1,500.00
A2. Material Cost 17,860.00
B. LABOR EXPENSE
B1. Manpower Composition
1 Foreman @ Php700.00/day X 4 days = 2,800.00
1 First Aider @ Php500.00/day X 4 days = 2,000.00
1 Master Plumber @ Php550.00/day X 4 days = 2,200.00
1 Helper @ Php350.00/day X 4 days = 1,400.00
B2. Labor Cost 8,400.00
Sub-Total 26,260.00
Profit 10% 2,626.00
OCM 15% 3,939.00
VAT 5% 1,641.25
TOTAL OF ITEM III = 34,466.25
UNIT COST= 34,466.25 /LOT
IV.ELECTRICAL WORKS
Estimated Quantity : LUMPSUM= 1.00 LOT
A. MATERIAL EXPENSE
A1. Bill of Materials
Electrical Pipes and 1.00 lot 10,000.00 10,000.00
fittings /lot
THHN wire 2.0 sq.mm 1.00 box 3,000.00 /box 3,000.00
THHN wire 3.5 sq.mm 1.00 box 4,000.00 /box 4,000.00
Electrical Fixtures 1.00 lot 3,200.00 /lot 3,200.00
Electrical lightings 1.00 lot 3,000.00 /lot 3,000.00
Consumables 1.00 lot 1,500.00 /lot 1,500.00
A2. Material Cost 24,700.00
B. LABOR EXPENSE
B1. Manpower Composition
1 Foreman @ Php700.00/day X 4 days = 2,800.00
1 First Aider @ Php500.00/day X 4 days = 2,000.00
1 Master Electrician @ Php550.00/day X 4 days = 2,200.00
1 Helper @ Php350.00/day X 4 days = 1,400.00
B2. Labor Cost 8,400.00
Sub-Total 33,100.00
Profit 10% 3,310.00
OCM 15% 4,965.00
VAT 5% 2,068.75
TOTAL OF ITEM IV = 43,443.75
UNIT COST= 43,443.75 /LOT
V.TILE WORKS
Estimated Quantity : LUMPSUM= 1.00 LOT
A. MATERIAL EXPENSE
A1. Bill of Materials
Ceramic/Porcelain Tile 56.00 pcs 120.00 /pc 6,720.00
60x60
Tile Adhesive 6.00 bags 450.00 /bag 2,700.00
Portland Cement 10.00 bags 360.00 /bag 3,600.00
Sand 3.00 cu.m. 800.00 /cu.m. 2,400.00
A2. Material Cost 15,420.00
B. LABOR EXPENSE
B1. Manpower Composition
1 Foreman @ Php700.00/day X 3 days = 2,100.00
1 First Aider @ Php500.00/day X 3 days = 1,500.00
1 Mason @ Php550.00/day X 3 days = 1,650.00
1 Helper @ Php350.00/day X 3 days = 1,050.00
B2. Labor Cost 6,300.00
Sub-Total 21,720.00
Profit 10% 2,172.00
OCM 15% 3,258.00
VAT 5% 1,357.50
TOTAL OF ITEM V = 28,507.50
UNIT COST= 28,507.50 /LOT
VI.CEILING WORKS
Estimated Quantity : LUMPSUM= 1.00 LOT
A. MATERIAL EXPENSE
A1. Bill of Materials
Hardiflex board 5.5mm 15.00 pcs 550.00 /pc 8,250.00
thk.
Metal Furring 70.00 pcs 120.00 /pc 8,400.00
Carrying Channel 70.00 pcs 120.00 /pc 8,400.00
W-clip 350.00 pcs 8.00 /pc 2,800.00
Sand 3.00 cu.m. 800.00 /cu.m. 2,400.00
A2. Material Cost 30,250.00
B. LABOR EXPENSE
B1. Manpower Composition
1 Foreman @ Php700.00/day X 3 days = 2,100.00
1 First Aider @ Php500.00/day X 3 days = 3,000.00
2 Carpenter @ Php550.00/day X 3 days = 3,300.00
B2. Labor Cost 8,400.00
C. EQUIPMENT EXPENSE
C1. List of Equipments:
2 Electric Drill @ Php250.00/day X 3 days = 2,100.00
C2. Equipment Cost 2,100.00
Sub-Total 40,750.00
Profit 10% 4,075.00
OCM 15% 6,112.50
VAT 5% 2,546.88
TOTAL OF ITEM VI = 53,484.38
UNIT COST= 53,484.38 /LOT
VII.PAINTING WORKS
Estimated Quantity : LUMPSUM= 1.00 LOT
A. MATERIAL EXPENSE
A1. Bill of Materials
Flatwall Enamel 1.00 tins 2,800.00 /tin 2,800.00
QDE ver. Color 1.00 tins 3,400.00 /tin 3,400.00
Flat latex paint 1.00 tins 2,800.00 /tin 2,800.00
Semi-gloss latex paint 1.00 tins 3,400.00 /tin 3,400.00
Consumables 1.00 lot 1,500.00 /pc 1,500.00
A2. Material Cost 13,900.00
B. LABOR EXPENSE
B1. Manpower Composition
1 Foreman @ Php700.00/day X 4 days = 2,800.00
1 First Aider @ Php500.00/day X 4 days = 4,000.00
2 Painter @ Php550.00/day X 4 days = 4,400.00
B2. Labor Cost 11,200.00
Sub-Total 25,100.00
Profit 10% 2,510.00
OCM 15% 3,765.00
VAT 5% 1,568.75
TOTAL OF ITEM VII = 32,943.75
UNIT COST= 32,943.75 /LOT
Sub-Total 20,956.17
Profit 10% 2,095.62
OCM 0% -
VAT 5% 1,152.59
TOTAL OF ITEM VIII = 24,204.38
UNIT COST= 24,204.38 /LOT
A. TOTAL APPROVED BUDGET FOR THE CONTRACT : 300,000.00
B. TOTAL ESTIMATED GOVERNMENT EXPENDITURES : -
Engineering and Administrative Overhead and CO -
RROW/Site Acquisition (MOC) -
C. TOTAL PROJECT COST : 300,000.00
BILL OF QUANTITIES
LGU COUNTERPART TO DOST-REHABILITATION OF LIVELIHOOD BUILDING
PHASE 2
BRGY. TALISOY, JOMALIG, QUEZON
7.92
75.5 X190
8 120 X 120
2 60 X 120
1 60 X 240
54
36
9
0
16.5
IMPLEMENTING OFFICE:_______________________________________________________
NAME OF PROJECT:___________________________________________________________
LOCATION:__________________________________________________________________
APPROVED BUDGET FOR THE CONTRACT
Stations: ________________________________
Length: ________________________________ Contract Duration: ____________________________
ITEM NO. DESCRIPTION QUANTITY UNIT ESTIMATED MARK-UPS IN PERCENT TOTAL MARK-UP VAT TOTAL INDIRECT TOTAL COST UNIT COST
DIRECT COST OCM PROFIT % VALUE COST
1 2 3 4 5 6 7 8 9 10 11 12 13
(5) X (8) 5%((5)+(9)) (9) + (10) (5) + (11) (12)/(3)
Part A Facilities for the Engineer
Total of Part A
Part B Other General Requirements
Total of Part B
Part C Earthworks
Total of Part C
Part D Sub-Base and Base Course
Total of Part D
Part E Surface Courses
Total of Part E
Part F Bridge Construction
Total of Part F
Part G Drainange and Slope Protection Structures
Total of Part G
Part H Miscellaneous Structures
Total of Part H
TOTAL
_____
Republic of the Philippines
MUNICIPALITY OF JOMALIG
Province of Quezon
SCOPE OF WORK
CONSTRUCTION OF LOCAL CORE ROAD FROM POBLACION TO SITIO MOROS
BRGY. TALISOY, JOMALIG, QUEZON
I. Mobilization/Demobilzation - this refer to the mobilization and demobilization of all heavy and/or mi-
nor equipments to be used in the above mentioned project
II. Signs and Identification - this refer to the signage printed in a tarpaulin with wooden frame to be
placed or posted in the project site for project identifications.
III. Subgrade Preparation - works undertaken herein were the clearing and grubbing,earthworks inclu-
ding compactions and other related works pertaining to preparation of subgrade
IV. Aggrregate Subbase Course - works undertaken herein were the laying,spreading, and
compacting of aggregate subbase course
V. Portland Cement Concrete Pavement- this refer to pouring of concrete,including rebarworks and
asphalt filling of the groove in the pavement.
VI.Safety Health Program- this refer to as the provision of comprehensive safety health program
of the contractor as mandated by law (see IRR of R.A. 9184), provisions of PPE's to all
workers, and other related occupational safety and health activities in the project.
VII.Temporary Facilities- this item of work refer to as the provision of the contractor of its field
office including warehouse/storage area and living quarters for their workers.
TOTAL = 192.5
sand gravel
80.5266 107.3688
PPE
PROJECT
QUANTITY RATE PER DAY DURATION Hard Hat Safety Shoes Safety Vest
Safety Officer 1.00 540.00 90.00 450.00 1,200.00 200.00
Nurse/First
Aider 1.00 500.00 90.00 450.00 1,200.00 200.00
Foreman 1.00 700.00 90.00 450.00 1,200.00 200.00
Laborer 15.00 330.00 90.00 450.00 1,200.00 200.00
Mason-
Carpenter 4.00 450.00 90.00 450.00 1,200.00 200.00
Equipment
Operator 2.00 600.00 90.00 450.00 1,200.00 200.00
PPE
First Aid
Safety Globes Goggles Kit TOTAL
50.00 200.00 50,700.00