Professional Documents
Culture Documents
Province of Isabela
MUNICIPALITY OF QUEZON
--oOOo--
OFFICE OF THE MUNICIPAL ENGINEER
Road Construction
Width per lane : 2.50 m
No. of Lanes : 2.00
Width of Shoulder : 1.50 m
Thickness of surface road : 1.50 m
Length of Road : 2357.89 m
2. Road Excavation
V = 5.00 x 0.15 x 2357.89 x 0.20
= 353.68 cu.m.
BREAKDOWN OF EXPENDITURES 0
AS SUBMITTED AS SUBMITTED
1. Labor 95,494.74 A. Total Direct Cost 2,450,048.79
2. Materials 318,315.79 B. OCM & Profit
3. Rental of Equipment 2,036,238.27 C. Value Added Tax
4. Provisional Sum D. Total Construction Cost
5. OCM & Profit E. Eng'g & Admin. Overhead, %
6. Value Added Tax F. RROW Acquisition .
7. EAO, % G. Contingency 235,455.41
8. RROW Acquisition
9. Contingency 235,455.41
10. TOTAL ESTIMATED COST 2,685,504.20 H. TOTAL ESTIMATED COST 2,685,504.20
Prepared by:
A. EARTHWORKS
B. ROAD CONSTRUCTION
TOTAL 2,354,554.06
2,354,554.06
b. Loading
Utilized : 1.0 cu.m. Loader
Production : 55 cu. m./hr.
Rental : 734.09 /hr. (incl. Fuel & operator)
EQUIPMENT:
9.00 lit/hr x 41 /liter
Fuel = = 6.71 /cu.m.
55 cu. m./hr.
734.09 /hr.
Spare Parts = = 13.35 /cu.m.
55 cu. m./hr.
c. Hauling
c.1. Hauling from Quarry Site to Dumpsite
AHD = 42.00 kms. Speed (kph)
with Load w/o Load
Type of Road : Type I = 40.00 kms. 35.00 45.00
: Type II = - kms. 25.00 35.00
: Type III = - kms. 30.00 35.00
: Type IV = 2.00 kms. 20.00 25.00
: Type V (Manual Hauling) = - kms. 2.00 5.00
Utilized : 6x6 Cargo Truck with five (5) Laborers
truck rental = 304.23 /hr.
Labor per day = 5 - Laborers x /day = - /day
Base Cost = 120.00 /cu.m.
Capacity of Truck = 4 cu.m./trip
Capability of five (5) Laborers
Cycle Time
with load = 40.00 kms. / 35.00 km./hr. = 1.14 hrs./trip
T-I
without load = 40.00 kms. / 45.00 km./hr. = 0.89 hrs./trip
with load = - kms. / 25.00 km./hr. = - hrs./trip
T-II
without load = - kms. / 35.00 km./hr. = - hrs./trip
with load = - kms. / 30.00 km./hr. = - hrs./trip
T-III
without load = - kms. / 35.00 km./hr. = - hrs./trip
with load = 2.00 kms. / 20.00 km./hr. = 0.10 hrs./trip
T-IV
without load = 2.00 kms. / 25.00 km./hr. = 0.08 hrs./trip
Loading, Unloading, Maneuvering, delays, etc. = 0.12 hrs./trip
total time = 2.33 hrs./trip
EQUIPMENT:
15.00 lit/hr x 2.21 hrs/trip x 41 /liter
Fuel = = 340.06 /cu.m.
4 cu.m./trip
304.23 /hr. x 2.33 hrs/trip
Spare Parts = = 177.09 /cu.m.
4 cu.m./trip
SUMMARY:
SAND GRAVEL
Base Cost = 120.00 /cu.m. = 120.00 /cu.m.
Fuel Cost = 340.06 /cu.m. = 340.06 /cu.m.
Spare Parts = 177.09 /cu.m. = 177.09 /cu.m.
TOTAL = 637.15 /cu.m. = 637.15 /cu.m.
SUMMARY
c. Equipment
utilize : 1 - bagger concrete mixer
rental = 99.14 /hr.
9.50 bag/cu.m. x 10 min./bag
Time of Mixer/cu.m. = = 1.583 hr./cu.m.
60 min./hr.
Fuel = 1.26 lit./hr. x 1.5833 hr./cu.m. x 41 /liter = 81.80 /cu.m.
Spare Parts = 99.14 /hr. x 1.5833 hr./cu.m. x = 156.97 /cu.m.
SUMMARY
a. Materials = 180.00 /cu.m.
c. Depreciation = - /cu.m.
d. Spare Parts = 492.96 /cu.m.
e. Fuel = 623.43 /cu.m.
UNIT COST = 1,296.39 /cu.m.
B. STRUCTURE EXCAVATION
1. Common Materials
a. Using Dozer
utilized = 160 HP Dozer
production = 25 cu.m./hr.
rental = 1,303.34 /hr.
EQUIPMENT:
17.00 lit/hr x 41.00 /lit.
Fuel = = 27.88 /cu.m.
25 cu.m./hr.
1,303.34 /hr.
Spare Parts = = 52.13 /cu.m.
25 cu.m./hr.
SUMMARY
c. Spare Parts = 52.13 /cu.m.
d. Fuel = 27.88 /cu.m.
UNIT COST = 80.01 /cu.m.
#DIV/0!
B. MATERIALS
DESCRIPTION QTY UNIT UNIT COST ESTIMATED DIRECT COST OCM & PROFIT VAT TOTAL INDIRECT COST TOTAL COST
A. EARTHWORKS
B. ROAD CONSTRUCTION