You are on page 1of 14

Republic of the Philippines

Province of Isabela
MUNICIPALITY OF QUEZON
--oOOo--
OFFICE OF THE MUNICIPAL ENGINEER

PROPOSED ROAD CONCRETING FOR BARANGAY ABUT


ESTIMATED QUANTITIES

No. of bags of cement given = 3,000.00 bags


No. of bags = 380.00 kg/m³ x Volume of Conc.
Weight of 1 cement of bag(40 kg.)
16,800.00 = 380.00 x Vc
40.00
Vc = 1768.42 m³

Vc = Length x Width x Thickness


1768.42 = L x 5.00 x 0.15
L = 2357.89 m

Vc = Length x Width x Thickness


Vc = 2357.89 x 5.00 x 0.15
Vc = 1768.42 cu.m.

Road Construction
Width per lane : 2.50 m
No. of Lanes : 2.00
Width of Shoulder : 1.50 m
Thickness of surface road : 1.50 m
Length of Road : 2357.89 m

1. Clearing and Grubbing


V = 10.00 x 0.15 x 2357.89
= 3536.84 sq.m.

2. Road Excavation
V = 5.00 x 0.15 x 2357.89 x 0.20
= 353.68 cu.m.

Prepared by: Approved by:

Engr. ERNESTO G. LOPEZ JR. Engr. PHOEBE L. NARAG


Engineer Acting Municipal Engineer
Republic of the Philippines
Province of Isabela
MUNICIPALITY OF QUEZON
--oOOo--
OFFICE OF THE MUNICIPAL ENGINEER

PROGRAM OF WORK/BUDGET COST

Project : PROPOSED ROAD CONCRETING FOR BARANGAY ABUT


Location :
Station Limits : STA. 0+000 - STA. 0+421.05
Appropriation :
Source of Fund :
16800
DESCRIPTION QUANTITY UNIT UNIT COST AMOUNT
A. EARTHWORKS 1.00 L.S. 61,989.48 61,989.48
B. ROAD CONSTRUCTION 1.00 L.S. 2,292,564.57 2,292,564.57
TOTAL DIRECT COST 2,354,554.06

BREAKDOWN OF EXPENDITURES 0
AS SUBMITTED AS SUBMITTED
1. Labor 95,494.74 A. Total Direct Cost 2,450,048.79
2. Materials 318,315.79 B. OCM & Profit
3. Rental of Equipment 2,036,238.27 C. Value Added Tax
4. Provisional Sum D. Total Construction Cost
5. OCM & Profit E. Eng'g & Admin. Overhead, %
6. Value Added Tax F. RROW Acquisition .
7. EAO, % G. Contingency 235,455.41
8. RROW Acquisition
9. Contingency 235,455.41
10. TOTAL ESTIMATED COST 2,685,504.20 H. TOTAL ESTIMATED COST 2,685,504.20

Prepared by:

Engr. ERNESTO G. LOPEZ JR.


Engineer

Noted by: Approved:

Hon. EDDIE C. SAKITING Engr. PHOEBE L. NARAG


Punong Barangay Municipal Engineer
Republic of the Philippines
Province of Isabela
MUNICIPALITY OF QUEZON
--oOOo--
OFFICE OF THE MUNICIPAL ENGINEER

PROPOSED ROAD CONCRETING FOR BARANGAY ABUT

APPROVED BUDGET FOR THE CONTRACT


DESCRIPTION QTY UNIT ESTIMATED DIRECT COST OCM & PROFIT VAT TOTAL INDIRECT COST TOTAL COST
A. 16800.00 1.00 L.S.
61,989.48 61,989.48
B. ROAD CONSTRUCTION 1.00 L.S.
2,292,564.57 2,292,564.57
TOTAL 2,354,554.06 2,354,554.06

Prepared by: Approved:

Engr. ERNESTO G. LOPEZ JR. Engr. PHOEBE L. NARAG


Engineer Municipal Engineer
Republic of the Philippines
Province of Isabela
MUNICIPALITY OF QUEZON
--oOOo--
OFFICE OF THE MUNICIPAL ENGINEER

PROPOSED ROAD CONCRETING FOR BARANGAY ABUT

APPROVED BUDGET FOR THE CONTRACT


DESCRIPTION QTY UNIT UNIT COST ESTIMATED DIRECT COST OCM & PROFIT VAT TOTAL INDIRECT COST TOTAL COST

A. EARTHWORKS

A.1. Clearing and Grubbing 3,536.84 sq.m. 9.53 33,689.94 33,689.94

A.2. Common Excavation 353.68 cu.m. 80.01 28,299.55 28,299.55

TOTAL OF PART B 61,989.48 61,989.48

B. ROAD CONSTRUCTION

B.1. Class "A" Concrete 1,768.42 cu.m. 1,296.39 2,292,564.57 2,292,564.57

TOTAL OF PART E 2,292,564.57 2,292,564.57

TOTAL 2,354,554.06
2,354,554.06

Prepared by: Approved:

Engr. ERNESTO G. LOPEZ JR. Engr. PHOEBE L. NARAG


Engineer Municipal Engineer
Republic of the Philippines
Province of Isabela
MUNICIPALITY OF QUEZON
--oOOo--
OFFICE OF THE MUNICIPAL ENGINEER

Base Data of Hauling Distances of Construction Materials

Hauling Distances (km.)


Type I Type II Type III Type IV Type V
Base Cost/ Good Poorly
Item Description Source Location Quarry Fee Unit Good Poorly
Maintained Maintained Manual Total
Maintained Maintained
Concrete/ Concrete/ Hauling Distance
Gravel Road Gravel Road
Asphalt Asphalt
1 Cement Quezon, Isabela 276.00 bag 1.00 - - - 1.00
2 Sand & Gravel Pinukpok, Kalinga Quarry 120.00 cu.m. 40.00 - - 2.00 42.00

Prepared by: Approved by:

Engr. ERNESTO G. LOPEZ JR. Engr. PHOEBE L. NARAG


Engineer Acting Municipal Engineer
Republic of the Philippines
Province of Isabela
MUNICIPALITY OF QUEZON
--oOOo--
OFFICE OF THE MUNICIPAL ENGINEER

DERIVATION OF UNIT COST


(FORCE ACCOUNT WORKS)

II. Equipment Rental


"Schedule "B" of the Revised Rental Rates"
EQUIPMENT RENTAL FUEL CONSUMPTION
1 160 HP DOZER 1,303.34 /hr. 17.00 lit/hr.
2 LOADER 1.0 m3 734.09 /hr. 9.00 lit/hr.
3 6X6 CARGO TRUCK 304.23 /hr. 15.00 lit/hr.
4 1 BAGGER MIXER 99.14 /hr. 1.26 lit/hr.
note: Cost of Fuel = 41 /liter
III. Hauling of Construction Materials
1. Cement
Hauling from Source to Dumpsite
AHD = 1.00 kms. Speed (kph)
with Load w/o Load
Type of Road : Type I = 1.00 kms. 35.00 45.00
: Type II = - kms. 25.00 35.00
: Type III = - kms. 30.00 35.00
: Type IV = - kms. 20.00 25.00
: Type V (Manual Hauling) = - kms. 2.00 5.00
Utilized : 6x6 Cargo Truck with five (5) Laborers
truck rental = 304.23 /hr.
Labor per day = 5 - Laborers x /day = - /day
Base Cost = /bag
Capacity of Truck = 150 bags/trip
Capability of five (5) Laborers
Loading = 300 bags/hr
Unloading = 300 bags/hr
a. Hauling from Source To Dump Site
Cycle Time
with load = 1.00 kms. / 35.00 km./hr. = 0.03 hrs./trip
T-I
without load = 1.00 kms. / 45.00 km./hr. = 0.02 hrs./trip
with load = - kms. / 25.00 km./hr. = - hrs./trip
T-II
without load = - kms. / 35.00 km./hr. = - hrs./trip
with load = - kms. / 30.00 km./hr. = - hrs./trip
T-III
without load = - kms. / 35.00 km./hr. = - hrs./trip
with load = - kms. / 20.00 km./hr. = - hrs./trip
T-IV
without load = - kms. / 25.00 km./hr. = - hrs./trip
Loading = 150 bags/trip / 300 bags/hr = 0.50 hrs./trip
Unloading = 150 bags/trip / 300 bags/hr = 0.50 hrs./trip
total time = 1.05 hrs./trip
EQUIPMENT:
41.00 lit/hr x 0.05 hrs/trip x 41 /liter
Fuel = = 0.57 /bag
150 bags/trip
304.23 /hr. x 1.05 hrs/trip
Spare Parts = = 2.13 /bag
150 bags/trip
note: Time for Loading & Unloading and Manual Hauling were excluded from the fuel consumption.
Manual Hauling from Dump Site to Job Site
Utilize : 1 Laborer @ 149.66 /day
Capability : 1 bag/trip
Cycle Time
with load = - kms. / 2.00 km./hr. = - hrs./trip
T-V
without load = - kms. / 5.00 km./hr. = - hrs./trip
total time = - hrs./trip
SUMMARY:
Base Cost = - /bag
Fuel Cost = 0.57 /bag
Spare Parts = 2.13 /bag
TOTAL = 2.70 /bag
6. Sand and Gravel
a. Quarrying
Utilized : 160 HP Dozer
Production : 65 cu. m./hr.
Rental : 1,303.34 /hr. (incl. Fuel & operator)
EQUIPMENT:
17.00 lit/hr x 41 /liter
Fuel = = 10.72 /cu.m.
65 cu. m./hr.
1,303.34 /hr.
Spare Parts = = 20.05 /cu.m.
65 cu. m./hr.

b. Loading
Utilized : 1.0 cu.m. Loader
Production : 55 cu. m./hr.
Rental : 734.09 /hr. (incl. Fuel & operator)
EQUIPMENT:
9.00 lit/hr x 41 /liter
Fuel = = 6.71 /cu.m.
55 cu. m./hr.
734.09 /hr.
Spare Parts = = 13.35 /cu.m.
55 cu. m./hr.

c. Hauling
c.1. Hauling from Quarry Site to Dumpsite
AHD = 42.00 kms. Speed (kph)
with Load w/o Load
Type of Road : Type I = 40.00 kms. 35.00 45.00
: Type II = - kms. 25.00 35.00
: Type III = - kms. 30.00 35.00
: Type IV = 2.00 kms. 20.00 25.00
: Type V (Manual Hauling) = - kms. 2.00 5.00
Utilized : 6x6 Cargo Truck with five (5) Laborers
truck rental = 304.23 /hr.
Labor per day = 5 - Laborers x /day = - /day
Base Cost = 120.00 /cu.m.
Capacity of Truck = 4 cu.m./trip
Capability of five (5) Laborers
Cycle Time
with load = 40.00 kms. / 35.00 km./hr. = 1.14 hrs./trip
T-I
without load = 40.00 kms. / 45.00 km./hr. = 0.89 hrs./trip
with load = - kms. / 25.00 km./hr. = - hrs./trip
T-II
without load = - kms. / 35.00 km./hr. = - hrs./trip
with load = - kms. / 30.00 km./hr. = - hrs./trip
T-III
without load = - kms. / 35.00 km./hr. = - hrs./trip
with load = 2.00 kms. / 20.00 km./hr. = 0.10 hrs./trip
T-IV
without load = 2.00 kms. / 25.00 km./hr. = 0.08 hrs./trip
Loading, Unloading, Maneuvering, delays, etc. = 0.12 hrs./trip
total time = 2.33 hrs./trip
EQUIPMENT:
15.00 lit/hr x 2.21 hrs/trip x 41 /liter
Fuel = = 340.06 /cu.m.
4 cu.m./trip
304.23 /hr. x 2.33 hrs/trip
Spare Parts = = 177.09 /cu.m.
4 cu.m./trip

SUMMARY:
SAND GRAVEL
Base Cost = 120.00 /cu.m. = 120.00 /cu.m.
Fuel Cost = 340.06 /cu.m. = 340.06 /cu.m.
Spare Parts = 177.09 /cu.m. = 177.09 /cu.m.
TOTAL = 637.15 /cu.m. = 637.15 /cu.m.

SUMMARY

Base Hauling Cost


Materials
Cost Labor Depreciation Spare Part Fuel Total
1 Cement - - - 2.13 0.57 2.70
2 Sand 120.00 - - 177.09 340.06 637.15
3 Gravel 120.00 - - 177.09 340.06 637.15
IV. Items of Works
A. CONCRETING WORKS
1. Class "A" Reinforced Concrete (Road concreting, Brgy Road)
a. Materials
Materials
Description Base Cost Labor Depreciation Spare Parts Fuel
per cubic meter
Cement 9.50 - - 20.25 5.41
Sand 0.50 60.00 - - 105.25 178.74
Gravel 1.00 120.00 - - 210.49 357.49
TOTAL 180.00 - - 335.98 541.64

c. Equipment
utilize : 1 - bagger concrete mixer
rental = 99.14 /hr.
9.50 bag/cu.m. x 10 min./bag
Time of Mixer/cu.m. = = 1.583 hr./cu.m.
60 min./hr.
Fuel = 1.26 lit./hr. x 1.5833 hr./cu.m. x 41 /liter = 81.80 /cu.m.
Spare Parts = 99.14 /hr. x 1.5833 hr./cu.m. x = 156.97 /cu.m.

SUMMARY
a. Materials = 180.00 /cu.m.
c. Depreciation = - /cu.m.
d. Spare Parts = 492.96 /cu.m.
e. Fuel = 623.43 /cu.m.
UNIT COST = 1,296.39 /cu.m.

Prepared by: Approved:

Engr. ERNESTO G. LOPEZ JR. Engr. PHOEBE L. NARAG


Engineer Municipal Engineer
Republic of the Philippines
Province of Isabela
MUNICIPALITY OF QUEZON
--oOOo--
OFFICE OF THE MUNICIPAL ENGINEER

DERIVATION OF UNIT COST


(FORCE ACCOUNT WORKS)

II. Equipment Rental


"Schedule "B" of the Revised Rental Rates"
EQUIPMENT RENTAL FUEL CONSUMPTION
1 160 HP DOZER 1,303.34 /hr. 17.00 lit/hr.
note: Cost of Fuel = 41 /liter

IV. Items of Works


A. CLEARING & GRUBBING
utilized = 160 HP Dozer
production = 210 sq.m./hr.
rental = 1,303.34 /hr.
EQUIPMENT:
17.00 lit/hr x 41.00 /lit.
Fuel = = 3.32 /sq.m.
210 sq.m./hr.
1,303.34 /hr.
Spare Parts = = 6.21 /sq.m.
210 sq.m./hr.
SUMMARY
b. Spare Parts = 6.21 /sq.m.
c. Fuel = 3.32 /sq.m.
UNIT COST = 9.53 /sq.m.

B. STRUCTURE EXCAVATION
1. Common Materials
a. Using Dozer
utilized = 160 HP Dozer
production = 25 cu.m./hr.
rental = 1,303.34 /hr.
EQUIPMENT:
17.00 lit/hr x 41.00 /lit.
Fuel = = 27.88 /cu.m.
25 cu.m./hr.
1,303.34 /hr.
Spare Parts = = 52.13 /cu.m.
25 cu.m./hr.
SUMMARY
c. Spare Parts = 52.13 /cu.m.
d. Fuel = 27.88 /cu.m.
UNIT COST = 80.01 /cu.m.

Prepared by: Approved:

Engr. ERNESTO G. LOPEZ JR. Engr. PHOEBE L. NARAG


Engineer Acting Municipal Engineer
Republic of the Philippines
Province of Isabela
MUNICIPALITY OF QUEZON
--oOOo--
OFFICE OF THE MUNICIPAL ENGINEER

PROPOSED ROAD CONCRETING FOR BARANGAY ABUT

MINIMUM EQUIPMENT REQUIREMENT


Equipment Description Capacity No. of Equipments
1. Bulldozer (D6H SERIES II PSDS/DD) 1.00

2. 16800.00 4-6 ft³/min. 1.00

3. Cargo/Service Truck(All Models) 9-10mt 1.00

4. Payloader (LX80-2C) 1.50 m³ 1.00

#DIV/0!

Prepared by: Approved:

Engr. ERNESTO G. LOPEZ JR. - Engr. PHOEBE L. NARAG


Engineer Acting Municipal Engineer
Republic of the Philippines
Province of Isabela
MUNICIPALITY OF QUEZON
--oOOo--
OFFICE OF THE MUNICIPAL ENGINEER

PROPOSED ROAD CONCRETING FOR BARANGAY ABUT

DETAILED UNIT PRICE ANALYSIS


Clearing and Grubbing
Name and Capacity No. of units No. of Hours Hourly Rate Amount
A. EQUIPMENT

A.1. Bulldozer (D6H SERIES II PSDS/DD) 1.00 16.84 1,303.34 21,950.99

A.1. Fuel Consumption 1.00 16.84 697.00 11,738.95

Total Unit Cost 33,689.94


#DIV/0!

Prepared by: Approved:

Engr. ERNESTO G. LOPEZ JR. - Engr. PHOEBE L. NARAG


Engineer Acting Municipal Engineer
Republic of the Philippines
Province of Isabela
MUNICIPALITY OF QUEZON
--oOOo--
OFFICE OF THE MUNICIPAL ENGINEER

PROPOSED ROAD CONCRETING FOR BARANGAY ABUT

DETAILED UNIT PRICE ANALYSIS


Structure Excavation
Name and Capacity No. of units No. of Hours Hourly Rate Amount
A. EQUIPMENT

A.1. Bulldozer (D6H SERIES II PSDS/DD) 1.00 14.15 1,303.34 18,438.83

A.1.1 Fuel Consumption 1.00 14.15 697.00 9,860.72

Total Unit Cost 28,299.55


#DIV/0!

Prepared by: Approved:

Engr. ERNESTO G. LOPEZ JR. - Engr. PHOEBE L. NARAG


Engineer Acting Municipal Engineer
Republic of the Philippines
Province of Isabela
MUNICIPALITY OF QUEZON
--oOOo--
OFFICE OF THE MUNICIPAL ENGINEER

PROPOSED ROAD CONCRETING FOR BARANGAY ABUT

DETAILED UNIT PRICE ANALYSIS


Class "A" Concrete
Name and Capacity No. of units No. of Hours Hourly Rate Amount
A. EQUIPMENT

A.1. 16800.00 1.00 1,768.42 158.56 280,392.00

A.1. Fuel Consumption 1.00 1,768.42 81.80 144,648.00

A.2. Bulldozer (D6H SERIES II PSDS/DD) 1.00 2,387.37 20.05 47,870.04

A.2. Fuel Consumption 1.00 2,387.37 10.72 25,599.94

A.3. Payloader (LX80-2C) 1.00 2,387.37 13.35 31,864.42

A.3. Fuel Consumption 1.00 2,387.37 6.71 16,017.07

A.4. Cargo/Service Truck(All Models) 1.00 3,000.00 2.13 6,393.66

A.4. Fuel Consumption 1.00 3,000.00 0.57 1,707.68

A.4. Cargo/Service Truck(All Models) 1.00 2,387.37 177.09 422,786.83

A.4. Fuel Consumption 1.00 2,387.37 340.06 811,838.84

B. MATERIALS

A.1. Cement 16,800.00 -

A.2. Sand 884.21 120.00 106,105.26

A.3. Gravel 1,768.42 120.00 212,210.53

Total Unit Cost 2,107,434.28

Prepared by: Approved:

Engr. ERNESTO G. LOPEZ JR. Engr. PHOEBE L. NARAG


Engineer Municipal Engineer
Republic of the Philippines
Province of Isabela
MUNICIPALITY OF QUEZON
--oOOo--
OFFICE OF THE MUNICIPAL ENGINEER

PROPOSED ROAD CONCRETING FOR BARANGAY ABUT


STA. 0+000 - STA. 0+421.05
SUMMARY OF QUANTITES

DESCRIPTION QTY UNIT UNIT COST ESTIMATED DIRECT COST OCM & PROFIT VAT TOTAL INDIRECT COST TOTAL COST
A. EARTHWORKS

A.1. Clearing and Grubbing 3536.84 sq.m. 9.53 33,689.94 33,689.94

A.2. Common Excavation 353.68 cu.m. 80.01 28,299.55 28,299.55

TOTAL OF PART A 61,989.48 61,989.48

B. ROAD CONSTRUCTION

B.1. Class "A" Concrete 1768.42 cu.m. 1296.39 2,292,564.57 2,292,564.57

TOTAL OF PART B 2,292,564.57 2,292,564.57

TOTAL 2,354,554.06 2,354,554.06

Prepared by: Approved:

Engr. ERNESTO G. LOPEZ JR. Engr. PHOEBE L. NARAG


Engineer Municipal Engineer

You might also like