Job No.

20-503 Project : Route 3, Route 46

Summary (NW & RW Submittals)


Date
Submittal (NW & Date Received Outstanding
S.No. Date of Submission submitted to Status Remarks
RW) GC/UP from Engineer Submittals

03/21/2020 R0 4/06/2020 R&R


1 NW # 1A 6/2/2020 R1 6/2/2020 R1 6/8/2020 R1 Certified
2 NW # 1B - - - - 6/20/2020
5/21/2020
3 NW # 2 6/02/2020 R1 6/1/2020 R&R
-
3/20/2020 R0
4 NW # 3A Panels - - -

3/3/2020 R0
5 NW # 3A Posts 4/09/2020 R1 4/8/2020 R&R

5/13/2020 R0
6 NW # 3B Bott. 5/29/2020 R1 6/18/2020 R2 6/9/2020 R1 R&&
Panels 06/18/20 R2
NW # 3B Panels 4/8/2020 R0
(Grid 1 to 18) 5/11/2020 R1 5/11/2020 R1 - -
2/18/2020 R0 3/31/2020 R&R
7 NW # 3B Posts 6/2/20220 R1
NW # 3C Bott. 5/23/2020 R0 6/9/2020 R&R
8 Panels 6/18/2020 R1 6/18/2020 R1
2/18/2020 R0 3/31/2020 R&R
9 NW # 3C Posts 6/2/20220 R1

5/29/2020 R0 6/9/2020 R&R


10 NW # 4 Panels 06/18/2020 R1 6/18/2020 R1
3/18/2020 R0 4/7/2020 R&R
11 NW # 4 Posts 6/3/2020 R1 6/17/2020 R1 R&R
06/18/2020 R2 6/18/2020 R2
12 RW # 1 6/19/2020
-
NW # 1 (RW#1)
13 Panels - - 6/24/2020

NW # 1 (RW#1)
14 Posts - - 6/24/2020

15 NW # 7 - - 7/17/2020 Original Date


16 NW # 10 - - 7/8/2020
2/26/2020 R&R
2/14/2020 R0 Recommended
17 RW # 12 3/2/2020 R1 - 4/10/2020 R1 for approval as
4/14/2020 R2 noted

5/4/2020
18 NW # 12 (RW#12) 5/13/2020 6/9/2020 R1 R&R
6/12/2020 6/15/2020 R2
19 RW # 14 - - 6/27/2020
3/16/2020
03/06/2020
20 RW # 15 03/25/2020 4/10/2020R1 R&R
5/12/2020 R2 6/02/2020 R2 Certified
21 NW # 15 Panels 4/25/2020 R0 - -
(RW#15)

22 NW # 15 Posts 4/25/2020 R0 5/21/2020 R&R