Professional Documents
Culture Documents
2
Outline
Project
01 Definition – Characteristics – Project vs Routine – Constraints
Project Management
02 Project Life Cycle – PM Process Group – Knowledge Areas
Project Cost
03 Cost Categories & Classification – Factors Affecting – Method/Time vs
Cost
OWNER
CONSULTANT CONTRACTOR
Need Project Management Need Project Management
Interrelationship of
PMBOK® Guide
Key Components in Projects
Project Management
The PMBOK® Guide groups processes into five categories called Process
Groups.
Project Management Process Group
5. Closing
4. Monitoring
2. Planning & Controlling
3. Executing
1. Initiating
Project Management Process Group
Initiating Process Group à to define a new project or a new phase of an
existing project by obtaining authorization to start the project or phase.
Planning Process Group à to establish the scope of the project, refine the
objectives, and define the course of action required to attain the objectives
that the project was undertaken to achieve.
01
People – Usually classified by the skills they bring to the project, for example, programmer,
mechanical engineer, welder, inspector, marketing director, supervisor
Equipment – Costs include rental/depreciation, maintenance/repair costs, operating costs (fuel,
02
oil, grease)
04 Subcontracts – The cost of specialty work performed by subcontractors to the prime contractor.
05 Other – All other costs that do not fit into one of the other cost categories
Cost Classification
l Direct Material
Indirect Cost Variable Cost
l Direct Labor Cost
l Equipment / Tools
01 Size of Project
02 Location
COST
C1 Inappropiate
Method
C2
Inappropiate
Method
Ci
Appropiate
Method
METHOD
M1 Mi M2
Asianto
Time vs Cost
COST
C1 Shorter Duration
C2
Longer Duration
Ci
Ideal Duration
TIME
T1 Ti T2
Asianto
Estimating Guidelines #1
Unknown Known
Known
Unknown Unknown
o Close-out Report
o Feasibility Study
o Enter New Market o Project Succesfully
o Identifies Unknown Issues
Completed
PROJECT COST MANAGEMENT
In practise, The Project Cost Management processes are overlap and interact in ways that cannot be completely detailed.
These processes interact with each other and with processes in other Knowledge Areas.
#01 Plan Cost Management
Planning
Process
Group
35
#01 Plan Cost Management
Planning
Process
Group
Outputs :
⌕ Cost Management Plan
⎋ Units of measure
⎋ Level of precision
⎋ Level of accuracy
⎋ Organizational procedures links
⎋ Control thresholds
⎋ Rules of performance measurement
⎋ Reporting formats
⎋ Additional details
#02 Estimate Cost
Planning
Process
Group
40
#02 Estimate Cost
Planning
Process
Group
74
#03 Determine Budget
Planning
Process
Group
A project budget includes all the funds authorized to execute the project.
83
#04 Control Cost Monitoring & Controling
Process Group
T&T : Charts
#04 Control Cost Monitoring & Controling
Process Group
T&T : Forecasting
⌕ As the project progresses, the project team may develop a forecast for
the estimate at completion (EAC) that may differ from the budget at
completion (BAC) based on the project performance.
⎋ EAC = AC + Bottom-up ETC
⌕ Three of the more common methods
⎋ EAC forecast for ETC work performed at the budgeted rate.
EAC = AC + (BAC – EV)
⎋ EAC forecast for ETC work performed at the present CPI.
EAC = BAC / CPI
⎋ EAC forecast for ETC work considering both SPI and CPI factors.
EAC = AC + [(BAC – EV) / (CPI × SPI)]
#04 Control Cost Monitoring & Controling
Process Group