Chapter 6: REPORT CONTENTS


Associated Air Balance Council

6. 1 Report Contents Procedure

6. l -l This procedure applies to the following:


a. HVAC systems
b. Air systems
c. Hydronic systems
d. Direct expansion systems

6. l -2 This procedure does not apply to the following:


a. Preliminary testing and balancing
b. Partial testing and balancing

6 .l -3 Prerequisites for reports:


a. Field testing and balancing is complete.
b. Discrepancy items are either corrected before publication of the report or
the discrepancies are noted in the report.

6.1-4 Reports
a. This section sets forth an outline for the reporting of data on operating
conditions and compares this data to the design or required data.
b. The forms indicated in this procedure shall be selected for the equipment
and systems installed on the project and submitted in the final report.

6. l -5 Reporting:
a. Forms and data must be prepared logically. This section lists form titles
and data entries required by these procedures. The forms may need to be
formatted to suit each agency's office procedures or as required by the
project.