Professional Documents
Culture Documents
10 Early Warning Signs Report - October 2018 PDF
10 Early Warning Signs Report - October 2018 PDF
THERE IS A WELL-KNOWN
SAYING IN MEDICINE –
‘PREVENTION IS BETTER
THAN CURE’…
…In our experience, the same principle applies to
large-scale construction projects and the disputes
they give rise to.
Given the sheer scale and complexity of construction projects that our clients bring Beyond this introductory set of warning signs, we offer
to fruition, problems – such as managing delay and disruption, change control, practical 60-minute training ‘clinics’, where our team explain
performance disagreements and financial issues – are perhaps inevitable and they how to treat early warning signs before they deteriorate
rarely emerge out of the blue. But, if you know what to look for, many of those problems into formal proceedings – and how to prevent them from
are identifiable, or even correctable before they deteriorate into formal proceedings. happening in the first place. The content is tailored around
Construction problems spotted earlier are, on the whole, far less traumatic to cure. the warning signs that you would like to cover and your
industry sector.
In this report, our global team of specialist construction disputes lawyers take an x-ray
of large-scale construction projects, revealing the most common early warning signs If you have any questions after reading this report, please
of a likely dispute between owners and contractors, or within the supply chain. get in touch. We would be delighted to organise an ‘early
The early warning signs we examine in this report are based on our experience of warning sign clinic’ with you and your team, or have an
repetitive issues seen while resolving many construction disputes, for over 750 clients informal meeting (we promise not to bring stethoscopes).
in over 40 countries, across a multitude of sectors.
The early warning signs are by no means exhaustive – we all know there are many
niche or less predictable problems that can arise – but the intent here is to provide Richard Davies
a quick early diagnosis reminder for the most common construction ailments. Partner, Abu Dhabi
+971 (0)2 652 0330
richard.davies@bclplaw.com
2/ /3
CONTENTS 10 EARLY WARNING SIGNS
CONTENTS
06-09
LOW TENDER BIDS:
30-33
MAKE THE SIX-FIGURE FEE WORTH IT:
TOO GOOD TO BE TRUE? DUST OFF YOUR CONTRACT!
10-13
ACCELERATED PROJECT DELIVERY:
34-37
AMBIGUOUS CONTRACTS:
FAST, FASTER…TOO FAST? BEWARE THESE SIX PROVISIONS
14-17
THE SCOPE OF WORK:
38-41
PROJECT MANAGER:
HOW IT CAN MAKE OR BREAK YOUR PROJECT IT’S A DIFFICULT JOB, BUT SOMEONE’S GOT TO DO IT
18-21
DESIGN FLAWS:
42-45
TERMINATION OF CONTRACT:
WHAT GOES WRONG BETWEEN DESK AND DIGGER WHEN RELATIONSHIPS TOTALLY BREAK DOWN
22-25
CONTRACT PROGRAMMES:
46-47
OUR TEAM
UNREALISTIC, OUT-OF-DATE AND OPEN TO DEBATE
26-29
THEY WANT TO BE PAID HOW MUCH?!
© Bryan Cave Leighton Paisner. This document provides a general summary only and is not intended to be comprehensive. Specific legal
advice should always be sought in relation to the facts of a given situation.
4/ /5
LOW TENDER BIDS: TOO GOOD TO BE TRUE? 10 EARLY WARNING SIGNS
When purchasers invi Imagine three consultants are appointed to advise on the
te
tenders, isn’t it good results of a tender…
news if ...one of the bids is a lot lower than the others. How do the
one bid is significantly
lower consultants respond?
than the others? Cha
rles Lilley 1. The first is jubilant, exclaiming, “Look at the immense saving
and Alex Ottaway re
veal why a the purchaser can make!” He thinks the contract should be
bargain contract pric awarded to this tenderer.
e could
actually be a sign of
2. The second is more circumspect, warning, “You get what you
inexperience, or even pay for.” She thinks the tenderer may well cut corners and do
a litigious
contractor. a poor job.
6/ 6/ /7
LOW TENDER BIDS: TOO GOOD TO BE TRUE? 10 EARLY WARNING SIGNS
However, severe storms, winds and very large waves were Beware: If it looks too good to be true, it probably is 1. Tenderer bids for 2. Bid based 3. Programme and 4. Contractor was 5. Purchaser received
common in this area. Therefore, even during those opportunity Problems can originate from the very beginning of the process, marine project on incorrect bid price significantly in significant works late and
windows when the tide was high, bad weather would likely which is why it is prudent to ensure that proper tender evaluation in harsh tidal assumption that shorter and cheaper delay and incurred unnecessary
cause additional downtime. procedures are in place. conditions. work could be than other bids. issued a series time, inconvenience
carried out at of unmeritorious and expense
One tenderer totally failed to appreciate the downtime The low bid in our coastal protection example was a product all times. claims. defending claims.
involved in doing the work. It was a civil engineering company of the contractor failing to appreciate the downtime that is
accustomed to working on land, and its bid was based on the required when working in water, and location-specific risks.
incorrect assumption that work could be carried out at all However, we have encountered other situations in which
times. Unsurprisingly, its programme was far more optimistic contractors deliberately underprice bids in order to win the work,
than any other tenderer, and its bid price was significantly adopting a claims-focused approach in order to recover some
cheaper. The purchaser was attracted by the low price and of their costs.
accepted the bid. The successful tenderer (the contractor)
learnt about harsh marine conditions the hard way, and When a purchaser comes across a low bid, it would be well
was in significant delay. advised to ensure its commercial team scrutinises the bid closely
and engages in clarification meetings with the relevant tenderer Alex Ottaway Charles Lilley
From the contractor’s perspective, the job went from being before deciding whether to accept it. The purchaser would then Senior Associate, London Partner, Abu Dhabi
profitable to loss-making. The contractor sought to recover be faced with a commercial decision: whether to continue +44 (0)20 3400 2614 +971 (0)2 652 0302
its losses by making claims based on adverse weather and exploring the possibility of awarding the contract to that alex.ottaway@bclplaw.com charles.lilley@bclplaw.com
physical conditions, even though it had no such entitlement tenderer, or award the contract to someone else.
contractually. Although the weather and physical conditions
were harsh, they were not unusual for that marine area.
8/ /9
ACCELERATED PROJECT DELIVERY: FAST, FASTER…TOO FAST? 10 EARLY WARNING SIGNS
10/ /11
ACCELERATED PROJECT DELIVERY: FAST, FASTER…TOO FAST? 10 EARLY WARNING SIGNS
Life in the fast lane: Accelerated delivery techniques “Ready, fire, aim!”: Stretching the limits of accelerated delivery
Accelerated delivery techniques include construction delivery ‘Fast-track’ is a term used to describe projects on which
methods in which the design, bidding or construction phases construction starts before project designs are complete, THREE EARLY WARNING SIGNS YOUR
overlap, as well as contract clauses aimed at expediting project
completion. For example, no-excuse incentive clauses, whereby
or nearly complete. For instance, on a fast-track project,
foundation and steel construction might start before a
PROJECT IS BREAKING SPEED LIMITS
the contractor is offered a monetary incentive for early building layout is fixed.
completion on or before a ‘drop-dead date’ that cannot be
adjusted for any reason. A risk inherent to fast-track projects is that early completion
of construction may conflict with subsequent design decisions.
The construction management (CM) method involves hiring a If the planned size of a building is changed after foundations
construction manager shortly after commencement of design have been poured, the foundations might need to be
services, thereby combining the ‘design’ and ‘bid’ phases of the demolished and rebuilt, and site utilities might need to be
DBB or traditional contracting method. Project completion is relocated, all resulting in delay and additional cost that does
further accelerated when, during the design phase, the not enhance project value. TIMELINES 'FIXED' PRICES CONSTRUCTION
construction manager provides time-saving input concerning
constructability of proposed designs, scheduling, and Risks to stakeholders increase when ‘fixed prices’ or ‘guaranteed
Project timelines that require Agreements on purportedly ‘fixed’ Proposals to substantially commence
availability of selected materials throughout the design phase. maximum prices’ are based on the incomplete designs that
commencement of construction or ‘maximum’ prices based on designs construction before an agreement on
exist when a fast-track construction commences. In the context
before key design elements are that may progress in a manner price has been reached, resulting in the
When CM was first exported from the US in the 1980s, it was of DB projects, this risk might be acceptable if the project owner
largely complete. conflicting with the owner’s original contractor becoming ‘embedded’ and
promoted as the ultimate ‘fast-track’ construction method, is prepared to relinquish control over design completion to the
design requirements. the owner losing its bargaining position
with construction on early works packages able to progress in design-builder once the price has been established. The UK
in price negotiations.
parallel with the design of services and finishes. For example, in concept of novation seeks to give the owner the best of both
the UK it was successfully used on various high-profile London worlds. It allows the owner to maintain control of design
projects. However, there is a key difference between US and UK development at an early stage, while ultimately transferring
practice in relation to CM. In the US, the construction manager design responsibility to the contractor. However, novation does
takes delivery risk in time and cost terms, whereas in the UK the slow down the process, as it contemplates the contractor
CM ‘contractor’ is generally engaged solely on a fee basis, being brought in at a later stage, once the design has been
taking minimal risk, with the employer retaining control over the developed, and not (as in the US) alongside the professional
design development process. Sophisticated UK developers team on ‘day one’.
understand and embrace this approach to risk allocation,
recognising that it both allows and forces them to retain Risks to the owner associated with prices based on incomplete
control over the design development process and to play designs are far greater on traditional DBB and, in the US, CM
an active role in risk management. In return, if all goes well projects because the project owner holds separate contracts
they pay a lower outturn cost, since they aren’t charged with the design team and the construction manager/
a premium for the transfer of risk. contractor. Each time the project owner’s design team submits
design iterations to the construction manager/contractor, there
Under the design-build method (‘DB’ or ‘D&B’) as adopted in is potential for disagreement over whether the new designs
the US, the design professionals and construction team are include ‘changes’ that warrant increases in price or time.
selected and hired simultaneously, under a single contract With respect to such projects, there is a direct relationship
with the owner, thereby streamlining the procurement process. between the certainty of a fixed price or a guaranteed
DB commonly allows the DB team to commence construction maximum price and the completeness of the designs on
while they complete final designs, producing additional which the price is based. Steven Becker Steve Gurr
time-saving opportunities. Partner, Kansas City Partner, Denver
+1 816 374 3379 +1 303 866 0520
Modular or off-site construction is on the increase, particularly
sbbecker@bclplaw.com steve.gurr@bclplaw.com
in the UK, and is seen as a means to address labour shortages
and the increasing cost of materials. Speed of construction
and reduced time on site are, among other things, often
cited as key benefits of modular construction. However,
some commentators have questioned whether it simply
moves delays from site to the factory. So, whilst it may
ultimately transform the way the industry works, it is still
too early to tell. A risk inherent to fast-track
projects is that early completion
of construction may conflict with
subsequent design decisions.
12/ /13
THE SCOPE OF WORK: HOW IT CAN MAKE OR BREAK YOUR PROJECT 10 EARLY WARNING SIGNS
14/ /15
THE SCOPE OF WORK: HOW IT CAN MAKE OR BREAK YOUR PROJECT 10 EARLY WARNING SIGNS
Early warning signs at negotiation stage Early warning signs at construction stage A LOOSE SCOPE OF WORK
During the negotiation stage of the construction contract, it is While it is best practice to have all changes to the scope of work
crucial to ask whether the scope of work is clearly defined, put in writing before any work begins on the changes, this is THE EARLY WARNING SIGNS AT A GLANCE
accurate, and whether it identifies the basic components of the rarely achieved in practice.
project, which the purchaser wants the contractor to deliver.
Construction contracts invariably provide mechanisms for
Careful consideration should be given to drafting the scope of changing the scope of work after the contract has been
work. Complex projects may warrant an extensive description, awarded. Usually, the purchaser, project manager or contract
encompassing a set timetable with significant milestones; administrator instructs reasonable change orders which may
simpler projects may only require a broad description of the give rise to additions or deductions from the contract sum.
NEGOTIATION STAGE CONSTRUCTION STAGE
work. Many projects will set out ‘exclusions’ from the scope.
These exclusions need to be drafted tightly and clearly so as not On the flipside, the contractor may submit a written notice of
to undermine detailed and carefully-considered drafting change with cost proposals for the extra work which it considers Difficulty agreeing the scope of work. Excessive requests to change scope of work.
elsewhere in the contract documents. falls outside of its scope. Construction contracts typically require
that these change orders must be authorised in writing, and the Poorly defined scope of work. Contractors requesting spurious or questionable changes.
Difficulty in agreeing the scope of work often indicates that the contractor is only entitled to additional compensation for extra
Excessively vague and ambiguous language. Contractors submitting cost proposals for abnormally
parties understand the project differently. When a change to work after this written authorisation is obtained.
high-value changes.
the scope then occurs, it often leads to a dispute about the Poorly or unclearly drafted ‘exclusions’ to scope.
interpretation of the original scope. However, in practice contractors often find themselves
Scope creep.
performing extra work to move the project forward after the Errors and omissions.
Indicators of an inadequate scope of work may include contract administrator has either refused to issue a change,
excessive use of vague language to the effect of “…including or has only given a verbal instruction, with an assurance that Impractical/impossible requirements – suggesting
but not limited to”, “…for example”, “…such as”, “…work must the written authorisation will follow. This failure to address who poor design.
be accomplished to the satisfaction of the engineer or the is responsible for the scope change often leads to disputes.
architect”, or “…work includes any other items necessary to Frequently, disputes become polarised between the employer’s
provide a complete, usable building even if not shown or team, arguing the change of scope is actually design
specified in the tender documents”. development which is the contractor’s responsibility under a
D&B contract; and the contractor, which strenuously argues it’s
A poorly defined scope of work will likely result in many claims for a change to the underlying scope of work.
change orders (or variations), and consequent claims for delay
and disruption. Project managers should be on the lookout for an excessive
number of change orders from purchasers, or requests for
changes or clarifications from contractors. The contractor must Glenn Haley Barry Wong
always be alert to changes and file written notice of them in a Partner, Hong Kong Associate, Hong Kong
timely fashion. If there are signs of an excessive number of +852 3143 8450 +852 3143 8419
changes, the change management systems and procedures glenn.haley@bclplaw.com barry.wong@bclplaw.com
must be followed to ensure that adequate and efficient cost
The contractor must always be alert and time estimates are prepared and submitted.
to changes and file written notice of Watch out for ‘scope creep’
them in a timely fashion. If changes to the scope of work are not controlled, it may lead to
‘scope creep’. For example, if there is a verbal request from the
purchaser to carry out a small piece of work with no assessment
of whether this is covered in the existing scope, it can pass
without much of an impact. However, repeat change orders will
accumulate, or ‘creep’, and eventually become significant
change orders, resulting in more work done for the same fees.
This is one of the main reasons for programme overruns and
exceeding budgets.
16/ /17
DESIGN FLAWS: WHAT GOES WRONG BETWEEN DESK AND DIGGER 10 EARLY WARNING SIGNS
What looks great on paper can cause delay and expense on site. Glenn Haley and
Carolina Carlstedt look at how to diagnose poor design issues early – and avoid delays,
inconvenience and arguments over who’s responsible.
18/ /19
DESIGN FLAWS: WHAT GOES WRONG BETWEEN DESK AND DIGGER 10 EARLY WARNING SIGNS
20/ /21
CONTRACT PROGRAMMES: UNREALISTIC, OUT-OF-DATE AND OPEN TO
O DEBATE 10 EARLY WARNING SIGNS
The contractual programme is a vital programme (for example, withholding payment), these are rarely
applied. The issue is not always the contractor’s failure to submit
management tool, and any problems a detailed contract programme, but can be the refusal of the
with it are a big red flag that trouble lies owner’s team to approve it. If shortly after project
ahead. Charles Lilley and Melissa Moriarty commencement there is no detailed programme in place
(for whatever reason), this is another warning sign that your
reveal the warning signs that should put project could be heading for trouble.
you on high alert.
Not agreeing the programme is sometimes adopted as a
Is the contractor’s tendered programme realistic? deliberate tactic by parties who think that it will improve their
We recently advised on a highly complex process plant where position. They may hope to avoid liability for prolongation costs
the EPC contractor had committed to a 24-month delivery whilst maintaining an entitlement to delay liquidated damages,
schedule. The plant was planning to deploy state-of-the-art or to secure an extension of time and entitlement to additional
technology on a scale rarely attempted before. The programme costs. Needless to say, this is not good practice. ‘Flexibility’ can
duration put forward by the next closest bidder was 36 months, quickly turn into uncertainty when trying to assess the impact of
so perhaps it should have been no surprise when delays subsequent events. In our experience, this rarely results in a
occurred. The result was a dispute over seven-figure damages. strong strategic position.
This is just one example of a problem we see time and time
again – parties putting forward programmes that are Do interface points protect against delay?
unrealistic. All projects have certain interface points which will become
important programming milestones in the execution of the
Given fierce competition amongst contractors to win contracts, project. For example, the interface between different package
and pressure on owners to achieve the earliest possible return contractors, the staged release of parts of the site by the owner,
on investment, it is highly probable that contractors will include the provision of offtake facilities, or the supply of fuel for start-up
‘ambitious’ schedules in their bids. However, significant and commissioning of a plant.
programming differences between competing bids and
unrealistic completion deadlines from owners are among Experienced contractors organise their planned sequence of
the most common telltale signs we see of future defaults works to create dependency opportunities. These can provide
and conflict. protection against delay of their own making. For example, in
scheduling and then providing update reports, a contractor
Is there an approved contract programme? might seek to show that an owner-responsible interface is on
Many contracts (e.g. FIDIC Red and Yellow Books/NEC) oblige the critical path.
the contractor to submit a detailed programme for approval
shortly after contract commencement. Programmes submitted An owner might portray a delayed interface as being
at the tender stage generally sketch out planned activities and non-critical, given other problems for which the contractor is
duration at a very high level to demonstrate some science responsible. Some legal systems have struggled to deal
behind the tendered completion date. But turning that into a consistently and coherently with what happens to the parties’
detailed programme can sometimes be problematic. Although entitlements when two delays happen at the same time – and
some contracts include sanctions for failure to submit a detailed contracts often contain ill-conceived drafting, which tries to tip
the outcome more clearly in one party’s favour.
22/ /23
CONTRACT PROGRAMMES: UNREALISTIC, OUT-OF-DATE AND OPEN TO DEBATE 10 EARLY WARNING
W SIGNS
When things get difficult, we often find programme updates 1. Process plant 2. EPC contractor 3. Programme put 4. Delays and dispute 5. Unrealistic
are either skipped altogether, or become outlandish works planned to deploy committed to forward by over damages programme
of fiction. Whilst contractors can be guilty of this behaviour, state-of-the-art unrealistic closest bidder. followed. should have
owners can also be to blame by rejecting responsibility for tech. programme. been questioned.
programme impacts as a matter of policy.
24/ /25
THEY WANT TO BE PAID HOW MUCH?! 10 EARLY WARNING SIGNS
An incurable disagreement
We have recently seen a resurgence in old-fashioned large
final account claims, with significant change order (or variation)
accounts as well as loss and expense and prolongation claims
being in dispute. On one live hospital project worth over £100
million, the contractor is applying for increasingly larger
sums every month and the amounts being certified are
getting smaller.
26/ /27
THEY WANT TO BE PAID HOW MUCH?! 10 EARLY WARNING SIGNS
The big red flag: Arguments over money Reasons behind under-certification
The contractual payment mechanism is perhaps the best early Issues are not always down to poor management on the
indicator that all is not well on a project. A growing disconnect contractor’s part. If there is genuine and persistent under- REAL-WORLD WARNING SIGNS
between applications for payment and sums certified is likely to certification by the purchaser’s team, it may be a sign that:
lead to one or more claims at some point, so the sooner there is
scrutiny of the underlying cause of this disparity the better. The project manager (or contract administrator) isn’t
effectively administrating the contract.
The best way to review this situation is to bring together the
commercial project-delivery teams and identify the key factors The designers are not acknowledging inadequacies or
behind the rising costs. More often than not, these professionals errors in their base design — and not issuing change orders
do not work closely enough, which makes it hard to get the full as a result.
picture. By working together to build an accurate understanding
There are inconsistencies in the contract.
of cost escalation, it may be possible to take proactive steps to
resolve or manage a problem, rather than allowing it to drift There is an unrealistic programme or tender price.
without decisive action.
1. Hospital project 2. Contractor applying 3. Contractor 4. Parties are tens 5. Positions are so
The purchaser is struggling to obtain sufficient project
Questions to ask when costs are rising worth over £100 million. for increasingly larger undisciplined in of millions apart. entrenched that
funding, has operational problems or needs refinancing.
When a contractor’s payment applications are analysed, sums, while amounts serving notices. the dispute is almost
it often becomes clear that the resourcing schedules or The importance of a proper and timely notice being certified get certainly heading
programmes have not been followed. At this point, key When considering payment, the dangers of failing to adhere smaller. for the courts.
questions to ask include: to the strict letter of the contract should never be overlooked.
Tribunals are increasingly holding that notices are a condition
Was the original bid (and particularly the planned precedent to an entitlement to time and money, so contractors
resourcing) adequate? should always give proper and timely notices.
Is the contractor slipping behind the programme? However, year after year, we experience contractors failing to
give the right notices. This provides the purchaser with an easy
Is the contractor failing to lock its supply chain into back-to-
excuse to reject the claim and to refuse to engage on its merits.
back provisions, pricing and scope, leading to escalating
In the UK, project managers still fail to issue valid pay less notices,
but invalid claims for payment?
with insufficient detail or serve outside the contractual time
Is there poor supply chain management and control? limits, thereby preventing the purchaser from withholding
payment until the next certificate. Caroline Pope Richard Dupay
Does the progress being reported reflect reality? Partner, London Senior Associate, Dubai
If not, why not? Don’t delay taking action +44 (0)20 3400 4318 +971 (0)2 652 0329
The sooner a potential problem is picked up, the greater the caroline.pope@bclplaw.com richard.dupay@bclplaw.com
Very often, one or two ‘claims-type’ issues or events become the chance of it being resolved.
dominant focus, and proliferating change orders (or variations)
are overlooked. This can be short-sighted, as large sums of As lawyers, we understand the need to ‘follow the money’ when
money are routinely tied up in disputed change items, which bringing or defending claims for clients – i.e. identifying where
are left on the back burner. If significant non-agreed sums for there are significant sums of money in dispute, and then
change orders start appearing on applications for payment, following investigation into why that is the case.
ask yourself:
The same approach should be applied to projects — as soon
Why is there a proliferation of change orders? as the payment/application delta starts to increase, decisive
action must be taken to address the causes and prevent issues
Is the validity of the change being disputed? developing into claims.
Is it a change, or is it design development? So remember, there was a reason a lot of time, effort and
money was put into negotiating the contract. Good contract
Is the purchaser’s team falling behind with issuing formal administration of the payment process by both the purchaser
change orders, resulting in uncertainty as to the validity and contractor is one which uses and acknowledges the
of changes? contract, rather than allowing it to gather dust, or prop
open the site’s office door.
Is there a difference in opinion over how to value
the change?
28/ /29
MAKE THE SIX-FIGURE FEE WORTH IT: DUST OFF YOUR CONTRACT! 10 EARLY WARNING SIGNS
Sometimes, the team are upfront and tell you that they have
made a conscious decision “not to get contractual”. This can
be code for having no idea what the contract says!
30/ /31
MAKE THE SIX-FIGURE FEE WORTH IT: DUST OFF YOUR CONTRACT! 10 EARLY WARNING SIGNS
Who is responsible? How can you tell if your team is not referring to the
If the project faces any setbacks, proceeding without reference contract terms?
to the contract terms is ill-advised. It can mean that you There are some key warning signs that parties to a contract TOP WARNING SIGNS THAT YOUR
inadvertently take responsibility for a risk properly borne by
another, or you do something (or fail to do something) which
are failing to consult the agreed terms. Sometimes, the team are
upfront and tell you that they have made a conscious decision
CONTRACT IS ‘GATHERING DUST’
undermines your contractual rights. For example, it is not “not to get contractual”. This can be code for having no idea
uncommon for the contract to stipulate that a contractor has what the contract says!
to give notice in order to claim an extension of time or additional
monies. Failing to serve notice within that period could mean Another giveaway is when a party, if asked for a copy of the
that the contractor is not entitled to an extension of time, even contract, is unable to produce a copy in reasonable time.
where it is clear that an event causing a delay is the Very often, when we ask for a copy of the contract it takes an
responsibility of the employer. extended period for one to be tracked down – so it’s obviously
not being used by that party.
Running a project without reference to the contract terms is
certainly an early warning sign that the team is not necessarily You would expect the key stakeholders to have a pretty good
running the job appropriately. A lack of discipline in grasp of the terms of the contract and their clause numbers.
understanding and using the contract may be indicative of However, alarm bells ring when the team talks in general terms
or uses common construction terminology not used in the 1. Team says “let’s not get contractual”. 2. Contracting parties take a long time 3. Use of different terminology to
other causes for concern, such as a lack of record keeping,
particular contract. to produce a copy of the contract. that used in the contract.
a lack of an up-to-date programme or up-to-date costs
information and a general lack of control.
Contracts also set out requirements for contractual notices,
correspondence and processes. These should be followed even
if a project is running smoothly. Signs that the contract is not
being used include the project team being unable to produce
these documents, or producing lots of correspondence or
notices which do not resemble the contract’s allocation of risk
or processes.
32/ /33
AMBIGUOUS CONTRACTS: BEWARE THESE SIX PROVISIONS 10 EARLY WARNING SIGNS
34/ /35
AMBIGUOUS CONTRACTS: BEWARE THESE SIX PROVISIONS 10 EARLY WARNING SIGNS
1 2 3
Vague phrases Automatic use of boilerplate clauses Supplemental agreements
For example, “best efforts”, “reasonable Entire agreement clauses, variation It is tempting to ‘wrap things up’ when
endeavours”, “all reasonable efforts” and clauses, exclusive remedies clauses and the situation changes or there has been
1. Multi-million dollar 2. Subcontract didn’t 3. Subcontract didn’t 4. Completion of 5. Contractor lost out
“best endeavours”. If these phrases are limitation of liability clauses – these all significant time or cost overruns. Parties
frequent, there is a strong argument have their place when the parties want to ‘clear the air’ and allow the plant constructed include a clear allow the contractor construction on $1 million in delay
that the parties intended them to be deliberately intend to place parameters project to complete. However, most in the Caribbean. completion date. to extend completion was delayed for liquidated damages.
understood differently in each instance. around the contract, their obligations construction contracts already contain date as a result of its many months.
They are rarely defined. and their liabilities. However, such clauses the mechanisms for making interim own delays.
can lead to unintended results. For adjustments to scope, price and time
example, have the parties really thought without (potentially) surrendering one’s
about what losses they will incur and/or rights going forward. Formal side
what sums they can and can’t recover agreements need to be approached
from the other in case of a breach? with great caution, explicitly state what
Does the boilerplate exclusion clause is being amended and make sure the
get them there? amendments are consistent with the
contract as a whole. It can come as a
nasty shock later if a party intended to
revisit something.
4 5 6 richard.davies@bclplaw.com sara.paradisi@bclplaw.com
36/ /37
PROJECT MANAGER: IT’S A DIFFICULT JOB, BUT SOMEONE’S GOT TO DO IT 10 EARLY WARNING SIGNS
It would be naive to think that a dispute couldn’t possibly arise if a contract was
administered perfectly. However, most would agree that fewer disputes would reach
a formal resolution process if contracts were better managed.
So, what are the early warning signs that a contract is not being administered correctly,
and how should they be dealt with?
38/ /39
PROJECT MANAGER: IT’S A DIFFICULT JOB, BUT SOMEONE’S GOT TO DO IT 10 EARLY WARNING SIGNS
40/ /41
TERMINATION OF CONTRACT: WHEN RELATIONSHIPS TOTALLY BREAK DOWN 10 EARLY WARNING SIGNS
Some projects are so beset with problems Do you have grounds to terminate?
Most engineering and construction contracts allow parties
that despite heeding early warning signs, to terminate the contract if one party is in default, if it becomes
the relationship between purchasers and insolvent, or after a period of non-payment/suspension.
contractors totally breaks down. Caroline Many also allow the purchaser to terminate for any reason
(known as ‘termination for convenience’).
Pope and Bob Maynard outline the key
considerations and risks for purchasers Unless the contractor abandons or suspends the works, the
most common grounds for termination by a purchaser are for
if they decide to terminate. ‘default’ or ‘convenience’.
Warning signs that a contract is heading for termination However, when a contract goes wrong, purchasers rarely want
The issue of termination usually arises well into projects, usually to terminate for convenience. This is because they blame the
in the fourth quartile. Typical warning signs include: contractor for not delivering the project and expect it to pick up
the bill for an alternative contractor to finish the job.
Very significant delays.
That leaves only one palatable option for the purchaser –
Doubts about whether the contractor is putting in termination for default. The purchaser commonly argues that
enough effort. the contractor has failed in its contractual obligations (there are
various contractual grounds of failure), serves a default notice or
Disagreements over responsibility for key matters, notice to correct, and terminates if the contractor does not
such as testing and takeover criteria. rectify that failing. Examples include the contractor failing to
proceed in accordance with clause 8 without reasonable cause
Reductions in workforce. (FIDIC 2017 Silver Book), substantially failing to comply with its
Entrenching of positions on contract interpretation. obligations (NEC3) or failing to proceed regularly or diligently
with the works (IChemE).
External developments that reduce the purchaser’s
motivation to proceed.
42/ /43
TERMINATION OF CONTRACT: WHEN RELATIONSHIPS TOTALLY BREAK DOWN 10 EARLY WARNING SIGNS
Is the contractor obliged to proceed? Practical steps to take before issuing a termination notice
Delay in itself does not mean that the contractor is failing to fulfil
its contractual obligations. Arrange to secure the site before the contractor
Ask whether your team has the skills and experience to To terminate or not to terminate? Morton’s fork
optimise the plant while you find an alternative contractor Purchasers consider terminating a project for a variety of
(this could involve a lengthy tender process). Take commercial reasons – from having reached the cap on
independent advice (engineering/architectural/ liquidated damages, to a relationship breakdown at site and
programming) on why the scheme proved hard to deliver. executive levels; combined with regulatory pressure to complete
This will help to satisfy you, your legal advisers and the scheme on time to avoid fines or prosecutions. For a
ultimately a tribunal (if the termination is contested), contractor, the reputational impact of having a major contract
that the contractor was in default. terminated can be significant, particularly as it must disclose
any terminations at pre-qualification for future projects.
The grounds to terminate are rarely black and white, so the risk is
substantial. Decision makers are rarely prepared to take the risk
of serving ‘termination for default’, fearing that their termination
will be held to be wrongful by a tribunal, but don’t want to let the
contractor off the hook by ‘terminating for convenience’.
44/ /45
OUR TEAM 10 EARLY WARNING SIGNS
OUR TEAM
HELPING YOU KEEP
CONTROL OF YOUR
CONSTRUCTION PROJECT
When your project is worth millions, we know how important GLOBAL REACH
it is to stay in control. That’s why our team of over 90 expert Our team has helped clients manage risk in over 40 countries.
construction lawyers focuses on helping you avoid nasty
ALGERIA CANADA GUERNSEY KUWAIT PORTUGAL TURKS & CAICOS
surprises in the first place.
AUSTRALIA CHINA HONG KONG LAOS QATAR TRINIDAD
To find out how we can help you keep control of BAHAMAS EGYPT IRAN LEBANON RUSSIA UNITED ARAB
EMIRATES
your project, simply call or email. BAHRAIN FRANCE IRAQ MACAU SAUDI ARABIA
UNITED KINGDOM
BANGLADESH GERMANY INDIA MALAYSIA SINGAPORE
Richard Davies UNITED STATES
BULGARIA GIBRALTAR JORDAN MOROCCO SPAIN
Partner, Abu Dhabi OF AMERICA
+971 (0)2 652 0330 CAMBODIA GREECE KAZAKHSTAN OMAN TURKEY
VIETNAM
richard.davies@bclplaw.com
YEMEN
> 1,030
> 90
Over 90 specialist
construction lawyers...
...with over 1,030 years of
combined experience...
13
...working from 13 offices
around the world.
Responsiveness: ten out of ten (and
I don’t give ‘tens’ away)…excellent.
Joint Managing Director,
mechanical and electrical
services contractor
46/ /47
Getting in touch
When you need a practical legal solution for
your next business opportunity or challenge,
please get in touch.
15195
bclplaw.com