You are on page 1of 25

FOREWORD 10 EARLY WARNING SIGNS

SPOTTING THE RISKS IN CONSTRUCTION


AND ENGINEERING PROJECTS

THERE IS A WELL-KNOWN
SAYING IN MEDICINE –
‘PREVENTION IS BETTER
THAN CURE’…
…In our experience, the same principle applies to
large-scale construction projects and the disputes
they give rise to.
Given the sheer scale and complexity of construction projects that our clients bring Beyond this introductory set of warning signs, we offer
to fruition, problems – such as managing delay and disruption, change control, practical 60-minute training ‘clinics’, where our team explain
performance disagreements and financial issues – are perhaps inevitable and they how to treat early warning signs before they deteriorate
rarely emerge out of the blue. But, if you know what to look for, many of those problems into formal proceedings – and how to prevent them from
are identifiable, or even correctable before they deteriorate into formal proceedings. happening in the first place. The content is tailored around
Construction problems spotted earlier are, on the whole, far less traumatic to cure. the warning signs that you would like to cover and your
industry sector.
In this report, our global team of specialist construction disputes lawyers take an x-ray
of large-scale construction projects, revealing the most common early warning signs If you have any questions after reading this report, please
of a likely dispute between owners and contractors, or within the supply chain. get in touch. We would be delighted to organise an ‘early
The early warning signs we examine in this report are based on our experience of warning sign clinic’ with you and your team, or have an
repetitive issues seen while resolving many construction disputes, for over 750 clients informal meeting (we promise not to bring stethoscopes).
in over 40 countries, across a multitude of sectors.

The early warning signs are by no means exhaustive – we all know there are many
niche or less predictable problems that can arise – but the intent here is to provide Richard Davies
a quick early diagnosis reminder for the most common construction ailments. Partner, Abu Dhabi
+971 (0)2 652 0330
richard.davies@bclplaw.com

2/ /3
CONTENTS 10 EARLY WARNING SIGNS

CONTENTS
06-09
LOW TENDER BIDS:
30-33
MAKE THE SIX-FIGURE FEE WORTH IT:
TOO GOOD TO BE TRUE? DUST OFF YOUR CONTRACT!

10-13
ACCELERATED PROJECT DELIVERY:
34-37
AMBIGUOUS CONTRACTS:
FAST, FASTER…TOO FAST? BEWARE THESE SIX PROVISIONS

14-17
THE SCOPE OF WORK:
38-41
PROJECT MANAGER:
HOW IT CAN MAKE OR BREAK YOUR PROJECT IT’S A DIFFICULT JOB, BUT SOMEONE’S GOT TO DO IT

18-21
DESIGN FLAWS:
42-45
TERMINATION OF CONTRACT:
WHAT GOES WRONG BETWEEN DESK AND DIGGER WHEN RELATIONSHIPS TOTALLY BREAK DOWN

22-25
CONTRACT PROGRAMMES:
46-47
OUR TEAM
UNREALISTIC, OUT-OF-DATE AND OPEN TO DEBATE

26-29
THEY WANT TO BE PAID HOW MUCH?!
© Bryan Cave Leighton Paisner. This document provides a general summary only and is not intended to be comprehensive. Specific legal
advice should always be sought in relation to the facts of a given situation.

4/ /5
LOW TENDER BIDS: TOO GOOD TO BE TRUE? 10 EARLY WARNING SIGNS

When purchasers invi Imagine three consultants are appointed to advise on the
te
tenders, isn’t it good results of a tender…
news if ...one of the bids is a lot lower than the others. How do the
one bid is significantly
lower consultants respond?
than the others? Cha
rles Lilley 1. The first is jubilant, exclaiming, “Look at the immense saving
and Alex Ottaway re
veal why a the purchaser can make!” He thinks the contract should be
bargain contract pric awarded to this tenderer.
e could
actually be a sign of
2. The second is more circumspect, warning, “You get what you
inexperience, or even pay for.” She thinks the tenderer may well cut corners and do
a litigious
contractor. a poor job.

3. The third – who we think takes the correct approach


– considers the detail of the bid, and compares it with
the others. He asks questions like, “Has the tenderer made
incorrect assumptions?”, “Has it misunderstood the
complexity of what is required?” and, “Has it legitimately
found an ingenious way to save costs?”.

When it all goes wrong: Low bids hitting the rocks


We recently encountered an example of what can go
wrong when a purchaser accepts a low bid without properly
scrutinising it and engaging in clarification meetings with the
relevant tenderer.

The project involved coastal protection works comprising a


series of offshore rock reefs. The marine site conditions meant
that there would be a lot of downtime. As the site was tidal, if
the tide was too low, crane barges and other vessels could
not access the site.

6/ 6/ /7
LOW TENDER BIDS: TOO GOOD TO BE TRUE? 10 EARLY WARNING SIGNS

Some of these difficulties could have


been avoided had the purchaser REAL-WORLD WARNING SIGNS
properly scrutinised and understood
the erroneous assumptions on which
the low bid was based.

However, severe storms, winds and very large waves were Beware: If it looks too good to be true, it probably is 1. Tenderer bids for 2. Bid based 3. Programme and 4. Contractor was 5. Purchaser received
common in this area. Therefore, even during those opportunity Problems can originate from the very beginning of the process, marine project on incorrect bid price significantly in significant works late and
windows when the tide was high, bad weather would likely which is why it is prudent to ensure that proper tender evaluation in harsh tidal assumption that shorter and cheaper delay and incurred unnecessary
cause additional downtime. procedures are in place. conditions. work could be than other bids. issued a series time, inconvenience
carried out at of unmeritorious and expense
One tenderer totally failed to appreciate the downtime The low bid in our coastal protection example was a product all times. claims. defending claims.
involved in doing the work. It was a civil engineering company of the contractor failing to appreciate the downtime that is
accustomed to working on land, and its bid was based on the required when working in water, and location-specific risks.
incorrect assumption that work could be carried out at all However, we have encountered other situations in which
times. Unsurprisingly, its programme was far more optimistic contractors deliberately underprice bids in order to win the work,
than any other tenderer, and its bid price was significantly adopting a claims-focused approach in order to recover some
cheaper. The purchaser was attracted by the low price and of their costs.
accepted the bid. The successful tenderer (the contractor)
learnt about harsh marine conditions the hard way, and When a purchaser comes across a low bid, it would be well
was in significant delay. advised to ensure its commercial team scrutinises the bid closely
and engages in clarification meetings with the relevant tenderer Alex Ottaway Charles Lilley
From the contractor’s perspective, the job went from being before deciding whether to accept it. The purchaser would then Senior Associate, London Partner, Abu Dhabi
profitable to loss-making. The contractor sought to recover be faced with a commercial decision: whether to continue +44 (0)20 3400 2614 +971 (0)2 652 0302
its losses by making claims based on adverse weather and exploring the possibility of awarding the contract to that alex.ottaway@bclplaw.com charles.lilley@bclplaw.com
physical conditions, even though it had no such entitlement tenderer, or award the contract to someone else.
contractually. Although the weather and physical conditions
were harsh, they were not unusual for that marine area.

The works were delivered late. The purchaser spent additional


time and expense dealing with the contractor’s persistent
and unmeritorious claims, even though the risks had been
successfully passed to the contractor, with a consequential Problems can originate from the
impact on the efficient delivery of the project. very beginning of the process,
Some of these difficulties could have been avoided had the which is why it is prudent to ensure
purchaser properly scrutinised and understood the erroneous
assumptions on which the low bid was based.
that proper tender evaluation
procedures are in place.
What can tenderers do?
We are seeing a promising trend for tenders – increasingly,
tenderers are resorting to independent internal
committees to review proposed bids before they are
submitted. The independent reviewers may spot issues
that those engrossed in the detail of the bid may have
missed, or assumptions that should be tested. The delivery
team should also be involved at bid stage and work closely
with the estimators, which in our experience does not happen
very often. These review procedures may minimise the risk
of the tenderer getting burnt, like the contractor in the
marine project.

8/ /9
ACCELERATED PROJECT DELIVERY: FAST, FASTER…TOO FAST? 10 EARLY WARNING SIGNS

In the construction industry, time is money


but haste makes waste. Steven Becker
and Steve Gurr look at accelerated project
delivery techniques – and how they can
lead to unexpected costs and delay.

The need for speed: Rise of accelerated project delivery


Until the mid-20th century, the design-bid-build project
delivery method or traditional contracting (also known as
‘DBB’ or ‘design-tender’) predominated. Traditional DBB
projects proceeded in a linear, methodical and relatively
slow manner, with one project phase (e.g. design) being
completed before commencement of the next phases
(e.g. bidding and construction).

Today, under pressure from shareholders, executives and other


stakeholders who crave instant gratification, project owners
face demands for ever-faster project completion. Working on
projects in over 40 countries, we have seen:

Design professionals accepting compressed times for


performance, often reluctantly, to secure employment
on project teams.

Contractors competing on the basis of schedule duration,


with hopes of distinguishing themselves from the
competition. Interestingly, in the current UK market the
pressure is the other way, with contractors unwilling to
commit to a firm price – even for design and build projects
– until the design is relatively well advanced.

Project team members asked to commit to project


durations in competitive environments, with incomplete
information, and without the benefit of candid
conversations allowing certainty as to the implications
of aggressive schedules.

Notwithstanding increased risks, the predominating


combination of market factors has led to the increased
popularity of accelerated delivery techniques.

10/ /11
ACCELERATED PROJECT DELIVERY: FAST, FASTER…TOO FAST? 10 EARLY WARNING SIGNS

Life in the fast lane: Accelerated delivery techniques “Ready, fire, aim!”: Stretching the limits of accelerated delivery
Accelerated delivery techniques include construction delivery ‘Fast-track’ is a term used to describe projects on which
methods in which the design, bidding or construction phases construction starts before project designs are complete, THREE EARLY WARNING SIGNS YOUR
overlap, as well as contract clauses aimed at expediting project
completion. For example, no-excuse incentive clauses, whereby
or nearly complete. For instance, on a fast-track project,
foundation and steel construction might start before a
PROJECT IS BREAKING SPEED LIMITS
the contractor is offered a monetary incentive for early building layout is fixed.
completion on or before a ‘drop-dead date’ that cannot be
adjusted for any reason. A risk inherent to fast-track projects is that early completion
of construction may conflict with subsequent design decisions.
The construction management (CM) method involves hiring a If the planned size of a building is changed after foundations
construction manager shortly after commencement of design have been poured, the foundations might need to be
services, thereby combining the ‘design’ and ‘bid’ phases of the demolished and rebuilt, and site utilities might need to be
DBB or traditional contracting method. Project completion is relocated, all resulting in delay and additional cost that does
further accelerated when, during the design phase, the not enhance project value. TIMELINES 'FIXED' PRICES CONSTRUCTION
construction manager provides time-saving input concerning
constructability of proposed designs, scheduling, and Risks to stakeholders increase when ‘fixed prices’ or ‘guaranteed
Project timelines that require Agreements on purportedly ‘fixed’ Proposals to substantially commence
availability of selected materials throughout the design phase. maximum prices’ are based on the incomplete designs that
commencement of construction or ‘maximum’ prices based on designs construction before an agreement on
exist when a fast-track construction commences. In the context
before key design elements are that may progress in a manner price has been reached, resulting in the
When CM was first exported from the US in the 1980s, it was of DB projects, this risk might be acceptable if the project owner
largely complete. conflicting with the owner’s original contractor becoming ‘embedded’ and
promoted as the ultimate ‘fast-track’ construction method, is prepared to relinquish control over design completion to the
design requirements. the owner losing its bargaining position
with construction on early works packages able to progress in design-builder once the price has been established. The UK
in price negotiations.
parallel with the design of services and finishes. For example, in concept of novation seeks to give the owner the best of both
the UK it was successfully used on various high-profile London worlds. It allows the owner to maintain control of design
projects. However, there is a key difference between US and UK development at an early stage, while ultimately transferring
practice in relation to CM. In the US, the construction manager design responsibility to the contractor. However, novation does
takes delivery risk in time and cost terms, whereas in the UK the slow down the process, as it contemplates the contractor
CM ‘contractor’ is generally engaged solely on a fee basis, being brought in at a later stage, once the design has been
taking minimal risk, with the employer retaining control over the developed, and not (as in the US) alongside the professional
design development process. Sophisticated UK developers team on ‘day one’.
understand and embrace this approach to risk allocation,
recognising that it both allows and forces them to retain Risks to the owner associated with prices based on incomplete
control over the design development process and to play designs are far greater on traditional DBB and, in the US, CM
an active role in risk management. In return, if all goes well projects because the project owner holds separate contracts
they pay a lower outturn cost, since they aren’t charged with the design team and the construction manager/
a premium for the transfer of risk. contractor. Each time the project owner’s design team submits
design iterations to the construction manager/contractor, there
Under the design-build method (‘DB’ or ‘D&B’) as adopted in is potential for disagreement over whether the new designs
the US, the design professionals and construction team are include ‘changes’ that warrant increases in price or time.
selected and hired simultaneously, under a single contract With respect to such projects, there is a direct relationship
with the owner, thereby streamlining the procurement process. between the certainty of a fixed price or a guaranteed
DB commonly allows the DB team to commence construction maximum price and the completeness of the designs on
while they complete final designs, producing additional which the price is based. Steven Becker Steve Gurr
time-saving opportunities. Partner, Kansas City Partner, Denver
+1 816 374 3379 +1 303 866 0520
Modular or off-site construction is on the increase, particularly
sbbecker@bclplaw.com steve.gurr@bclplaw.com
in the UK, and is seen as a means to address labour shortages
and the increasing cost of materials. Speed of construction
and reduced time on site are, among other things, often
cited as key benefits of modular construction. However,
some commentators have questioned whether it simply
moves delays from site to the factory. So, whilst it may
ultimately transform the way the industry works, it is still
too early to tell. A risk inherent to fast-track
projects is that early completion
of construction may conflict with
subsequent design decisions.

12/ /13
THE SCOPE OF WORK: HOW IT CAN MAKE OR BREAK YOUR PROJECT 10 EARLY WARNING SIGNS

The ‘scope of work’ should keep your


project from straying too far from the
original agreement. Glenn Haley and Barry
Wong explain how a loose definition can
lead to miscommunication, additional work,
extra expense and even formal disputes.
Why the scope of work exists
No two construction projects are exactly alike – the site, design
and conditions will always be different. This uniqueness is
reflected in the scope of work, which describes the work to
be performed under a particular contract. It is the most
fundamental building block for effective project management,
defining what a contractor is going to deliver.

Although a scope of work is a useful way to agree broad


project requirements for both purchaser and contractor during
the negotiation stage, changes to the scope of work often lead
to disputes. Disagreements about delay, disruption, defects
and termination often centre on the question of whether an
item of work is within the original contract scope, or whether it
changes the scope. In our experience, many disputes could be
avoided if there was an accurate and comprehensive scope
of work in the first place. Careful negotiation on the scope of
work should ensure all parties are on the same page from the
very beginning.

14/ /15
THE SCOPE OF WORK: HOW IT CAN MAKE OR BREAK YOUR PROJECT 10 EARLY WARNING SIGNS

Early warning signs at negotiation stage Early warning signs at construction stage A LOOSE SCOPE OF WORK
During the negotiation stage of the construction contract, it is While it is best practice to have all changes to the scope of work
crucial to ask whether the scope of work is clearly defined, put in writing before any work begins on the changes, this is THE EARLY WARNING SIGNS AT A GLANCE
accurate, and whether it identifies the basic components of the rarely achieved in practice.
project, which the purchaser wants the contractor to deliver.
Construction contracts invariably provide mechanisms for
Careful consideration should be given to drafting the scope of changing the scope of work after the contract has been
work. Complex projects may warrant an extensive description, awarded. Usually, the purchaser, project manager or contract
encompassing a set timetable with significant milestones; administrator instructs reasonable change orders which may
simpler projects may only require a broad description of the give rise to additions or deductions from the contract sum.
NEGOTIATION STAGE CONSTRUCTION STAGE
work. Many projects will set out ‘exclusions’ from the scope.
These exclusions need to be drafted tightly and clearly so as not On the flipside, the contractor may submit a written notice of
to undermine detailed and carefully-considered drafting change with cost proposals for the extra work which it considers Difficulty agreeing the scope of work. Excessive requests to change scope of work.
elsewhere in the contract documents. falls outside of its scope. Construction contracts typically require
that these change orders must be authorised in writing, and the Poorly defined scope of work. Contractors requesting spurious or questionable changes.
Difficulty in agreeing the scope of work often indicates that the contractor is only entitled to additional compensation for extra
Excessively vague and ambiguous language. Contractors submitting cost proposals for abnormally
parties understand the project differently. When a change to work after this written authorisation is obtained.
high-value changes.
the scope then occurs, it often leads to a dispute about the Poorly or unclearly drafted ‘exclusions’ to scope.
interpretation of the original scope. However, in practice contractors often find themselves
Scope creep.
performing extra work to move the project forward after the Errors and omissions.
Indicators of an inadequate scope of work may include contract administrator has either refused to issue a change,
excessive use of vague language to the effect of “…including or has only given a verbal instruction, with an assurance that Impractical/impossible requirements – suggesting
but not limited to”, “…for example”, “…such as”, “…work must the written authorisation will follow. This failure to address who poor design.
be accomplished to the satisfaction of the engineer or the is responsible for the scope change often leads to disputes.
architect”, or “…work includes any other items necessary to Frequently, disputes become polarised between the employer’s
provide a complete, usable building even if not shown or team, arguing the change of scope is actually design
specified in the tender documents”. development which is the contractor’s responsibility under a
D&B contract; and the contractor, which strenuously argues it’s
A poorly defined scope of work will likely result in many claims for a change to the underlying scope of work.
change orders (or variations), and consequent claims for delay
and disruption. Project managers should be on the lookout for an excessive
number of change orders from purchasers, or requests for
changes or clarifications from contractors. The contractor must Glenn Haley Barry Wong
always be alert to changes and file written notice of them in a Partner, Hong Kong Associate, Hong Kong
timely fashion. If there are signs of an excessive number of +852 3143 8450 +852 3143 8419
changes, the change management systems and procedures glenn.haley@bclplaw.com barry.wong@bclplaw.com
must be followed to ensure that adequate and efficient cost
The contractor must always be alert and time estimates are prepared and submitted.

to changes and file written notice of Watch out for ‘scope creep’
them in a timely fashion. If changes to the scope of work are not controlled, it may lead to
‘scope creep’. For example, if there is a verbal request from the
purchaser to carry out a small piece of work with no assessment
of whether this is covered in the existing scope, it can pass
without much of an impact. However, repeat change orders will
accumulate, or ‘creep’, and eventually become significant
change orders, resulting in more work done for the same fees.
This is one of the main reasons for programme overruns and
exceeding budgets.

The only constant in construction is change


Changes can significantly impact a project’s cost and schedule.
It is imperative that these are addressed early to avoid disputes
over who’s responsible for changes to the scope of work.

16/ /17
DESIGN FLAWS: WHAT GOES WRONG BETWEEN DESK AND DIGGER 10 EARLY WARNING SIGNS

What looks great on paper can cause delay and expense on site. Glenn Haley and
Carolina Carlstedt look at how to diagnose poor design issues early – and avoid delays,
inconvenience and arguments over who’s responsible.

What causes design problems?


Issues often arise when designers are under pressure. The computer-generated model showed a minimal number
They might have to produce drawings in a tight timespan, of clashes, but in real-life, on-site conditions, the design proved
be subject to pressure or excessive instructions from the unworkable and led to substantial delays. In the design office,
client developer, or be pushed to create designs without the the model did not appear to throw up any red flags but, in
necessary field experience. Design defects often only become practice, it was simply not possible for the welders to execute
apparent on site, and disputes can arise as a result of a poor the design because of limited access, spatial constraints and
or defective design being executed in the field. Contractors an unnecessarily convoluted design. Instead, they were forced
may be faced with a design fraught with errors, omissions and to relocate equipment and reroute the pipework in order to
impractical requirements. Very often, this results in requests for rectify the errors, simplify the system and complete the work.
change orders (or variations) and a delay to completion. This resulted in more than six months of delay to the
completion of the project.
What causes poor design?
An otherwise experienced designer may lack ‘field’ experience, Poor design can also be caused by a lack of coordination
or might have been pushed into proceeding with a preliminary or between designers, which leads to disputes over interface
incomplete design by a client. For example, we have experience design. We had a case in the UK where the M&E systems
of a case where a designer with limited field experience prepared could not be spatially coordinated because the floor-to-
a complex computer-generated model for a pipework system ceiling heights were incorrect. The designers had failed to
destined for a liquefied natural gas (LNG) plant in the North Sea. communicate and coordinate with the M&E subcontractor
and instead made a series of assumptions that were flawed.

An otherwise experienced designer may lack ‘field’ experience, or might


have been pushed into proceeding with a preliminary or incomplete
design by a client.

18/ /19
DESIGN FLAWS: WHAT GOES WRONG BETWEEN DESK AND DIGGER 10 EARLY WARNING SIGNS

The fast-track to conflict Make use of contractual documents


Designers are often under a great deal of pressure to complete It is important that design responsibilities are clearly set out in
a design quickly, so that bidding or construction can commence the contractual documents, and that parties adhere to these REAL-WORLD WARNING SIGNS
as soon as possible. This temptation to try to ‘fast-track’ design obligations. For example, if a contractor is faced with a design
often leads to a flawed design, as ‘fast-track’ means a design that lacks key details and is told that these will be, “resolved
has not gone through the usual quality control processes. In this through the drawing submittal process”, the contractor should
situation, there are often inconsistencies between the design follow the relevant contractual processes to ensure the designer
and the contractual documents, and an increased likelihood rectifies the omissions (rather than trying to resolve them on site).
of problems and disputes.
In such a scenario, it’s also imperative that the contractor
’Fast-track’ designs can also cause issues during the drawing satisfies the contractual notice provisions. If the final design
submittal process. Contractors are often under an obligation constitutes a change to the work, or the omissions/defects
to submit shop drawings, which have to be reviewed and cause delays to the progress of the work, the contractor should
approved by the owner before works can proceed. If designs provide the owner with a notice that complies with the contract.
are flawed, this can be an arduous task for the contractor and The contractor should also capture and document all time and
the owner, and lead to delays while parties argue over the cost impacts for future claims. 1. Pipework system 2. Designer with limited 3. Computer in design 4. Design proved 5. Project was
scope of the original design, and who is responsible for its prepared for field experience office showed a unworkable – welders delayed by
development or errors in the base design. However, in our experience, a contractor can be its own LNG plant in the created complex minimal number had to relocate more than
worst enemy. It wants to be seen as being helpful and North Sea. computer-generated of clashes. equipment and six months.
non-confrontational and, in effect, does part of the designer’s model. reroute pipework.
job for them. Correcting errors through the shop drawings or
detailed design process, rather than insisting that the designer
resolves them, leads to arguments over whether the contractor
in effect accepted responsibility for the problem and lost the
right to claim time and money for the extra work.
This temptation to try to ‘fast- Diagnosing design issues: The warning signs
track’ design often leads to a Glenn Haley Carolina Carlstedt
Contractors issuing a large number of requests for Partner, Hong Kong Senior Associate, Hong Kong
flawed design. information (RFIs) or claims notices. +852 3143 8450 +852 3143 8461
glenn.haley@bclplaw.com carolina.carlstedt@bclplaw.com
Designers correcting design deficiencies in responses
to RFIs.

Designers’ response times slowing down, both for RFIs


and revisions of drawings or specifications.

Larger than usual number of enquiries from supervising


and government bodies.

Core design issues resolved through the shop drawing


process or on site.

Arguments over whether design changes are ‘changes’ or


design development.

20/ /21
CONTRACT PROGRAMMES: UNREALISTIC, OUT-OF-DATE AND OPEN TO
O DEBATE 10 EARLY WARNING SIGNS

The contractual programme is a vital programme (for example, withholding payment), these are rarely
applied. The issue is not always the contractor’s failure to submit
management tool, and any problems a detailed contract programme, but can be the refusal of the
with it are a big red flag that trouble lies owner’s team to approve it. If shortly after project
ahead. Charles Lilley and Melissa Moriarty commencement there is no detailed programme in place
(for whatever reason), this is another warning sign that your
reveal the warning signs that should put project could be heading for trouble.
you on high alert.
Not agreeing the programme is sometimes adopted as a
Is the contractor’s tendered programme realistic? deliberate tactic by parties who think that it will improve their
We recently advised on a highly complex process plant where position. They may hope to avoid liability for prolongation costs
the EPC contractor had committed to a 24-month delivery whilst maintaining an entitlement to delay liquidated damages,
schedule. The plant was planning to deploy state-of-the-art or to secure an extension of time and entitlement to additional
technology on a scale rarely attempted before. The programme costs. Needless to say, this is not good practice. ‘Flexibility’ can
duration put forward by the next closest bidder was 36 months, quickly turn into uncertainty when trying to assess the impact of
so perhaps it should have been no surprise when delays subsequent events. In our experience, this rarely results in a
occurred. The result was a dispute over seven-figure damages. strong strategic position.
This is just one example of a problem we see time and time
again – parties putting forward programmes that are Do interface points protect against delay?
unrealistic. All projects have certain interface points which will become
important programming milestones in the execution of the
Given fierce competition amongst contractors to win contracts, project. For example, the interface between different package
and pressure on owners to achieve the earliest possible return contractors, the staged release of parts of the site by the owner,
on investment, it is highly probable that contractors will include the provision of offtake facilities, or the supply of fuel for start-up
‘ambitious’ schedules in their bids. However, significant and commissioning of a plant.
programming differences between competing bids and
unrealistic completion deadlines from owners are among Experienced contractors organise their planned sequence of
the most common telltale signs we see of future defaults works to create dependency opportunities. These can provide
and conflict. protection against delay of their own making. For example, in
scheduling and then providing update reports, a contractor
Is there an approved contract programme? might seek to show that an owner-responsible interface is on
Many contracts (e.g. FIDIC Red and Yellow Books/NEC) oblige the critical path.
the contractor to submit a detailed programme for approval
shortly after contract commencement. Programmes submitted An owner might portray a delayed interface as being
at the tender stage generally sketch out planned activities and non-critical, given other problems for which the contractor is
duration at a very high level to demonstrate some science responsible. Some legal systems have struggled to deal
behind the tendered completion date. But turning that into a consistently and coherently with what happens to the parties’
detailed programme can sometimes be problematic. Although entitlements when two delays happen at the same time – and
some contracts include sanctions for failure to submit a detailed contracts often contain ill-conceived drafting, which tries to tip
the outcome more clearly in one party’s favour.

22/ /23
CONTRACT PROGRAMMES: UNREALISTIC, OUT-OF-DATE AND OPEN TO DEBATE 10 EARLY WARNING
W SIGNS

When things get difficult, we often


find programme updates are either
skipped altogether, or become
outlandish works of fiction.

Is the programme being properly updated? REAL-WORLD


REAL-W
REAL -WORLD
ORLD WARNING SIGNS
SIGN S
Most forms of contract also require contractors to submit
regular programme updates, which are intended to act
as an active management tool. When properly done, this
should enable parties to predict the impact of events such
as change orders (or variations) on future progress and to
implement appropriate remedial action. Under some forms
of contract, such as NEC4, operation of the extension of
time mechanism depends entirely on the existence of an
accurate, up-to-date programme which can be used to
assess the impact of compensation events.

When things get difficult, we often find programme updates 1. Process plant 2. EPC contractor 3. Programme put 4. Delays and dispute 5. Unrealistic
are either skipped altogether, or become outlandish works planned to deploy committed to forward by over damages programme
of fiction. Whilst contractors can be guilty of this behaviour, state-of-the-art unrealistic closest bidder. followed. should have
owners can also be to blame by rejecting responsibility for tech. programme. been questioned.
programme impacts as a matter of policy.

What are the early warning signs?


You would be surprised at how frequently we advise on Melissa Moriarty Charles Lilley
disputes where the root problem is unrealistic contract Principal Knowledge Development Lawyer, London Partner, Abu Dhabi
programmes, exacerbated by failures to update them. +44 (0)20 3400 4633 +971 (0)2 652 0302
Look out for the following telltale signs that future melissa.moriarty@bclplaw.com charles.lilley@bclplaw.com
disagreements are likely:

Contractor’s failure to submit a contract programme


before works commence.
Insufficient detail within the contract programme.
Lack of credibility relating to the proposed schedule
of works.
Owner’s failure to engage in agreeing programme of
works (with interface points).
Misalignment between parties on their approach
to programming issues.
Scarcity of regular programme updates.
Insufficient probing of programme updates.

24/ /25
THEY WANT TO BE PAID HOW MUCH?! 10 EARLY WARNING SIGNS

An incurable disagreement
We have recently seen a resurgence in old-fashioned large
final account claims, with significant change order (or variation)
accounts as well as loss and expense and prolongation claims
being in dispute. On one live hospital project worth over £100
million, the contractor is applying for increasingly larger
sums every month and the amounts being certified are
getting smaller.

The purchaser isn’t engaging constructively regarding


responsibility for the causes of delay, but instead is just
attacking the methodology of the delay analysis. To make
matters worse, the contractor hasn’t been very disciplined
in serving notices, despite the contract containing onerous
condition precedent provisions. And if those issues weren’t
enough, there are rumours that the purchaser’s funding is
being squeezed. As the project reaches completion, the
Decisive action parties are tens of millions apart. Relations are so strained
can prevent dis
over how much agreements and positions so entrenched that the dispute is almost
money a contr certainly heading for the courts.
owed, and how actor thinks it is
much a purcha
should pay. Ca ser thinks it It’s a familiar enough scenario, but how can it be avoided?
roline Pope an
Dupay flag the d Ric
warning signs th hard
immediate acti at require
on.

26/ /27
THEY WANT TO BE PAID HOW MUCH?! 10 EARLY WARNING SIGNS

The big red flag: Arguments over money Reasons behind under-certification
The contractual payment mechanism is perhaps the best early Issues are not always down to poor management on the
indicator that all is not well on a project. A growing disconnect contractor’s part. If there is genuine and persistent under- REAL-WORLD WARNING SIGNS
between applications for payment and sums certified is likely to certification by the purchaser’s team, it may be a sign that:
lead to one or more claims at some point, so the sooner there is
scrutiny of the underlying cause of this disparity the better. The project manager (or contract administrator) isn’t
effectively administrating the contract.
The best way to review this situation is to bring together the
commercial project-delivery teams and identify the key factors The designers are not acknowledging inadequacies or
behind the rising costs. More often than not, these professionals errors in their base design — and not issuing change orders
do not work closely enough, which makes it hard to get the full as a result.
picture. By working together to build an accurate understanding
There are inconsistencies in the contract.
of cost escalation, it may be possible to take proactive steps to
resolve or manage a problem, rather than allowing it to drift There is an unrealistic programme or tender price.
without decisive action.
1. Hospital project 2. Contractor applying 3. Contractor 4. Parties are tens 5. Positions are so
The purchaser is struggling to obtain sufficient project
Questions to ask when costs are rising worth over £100 million. for increasingly larger undisciplined in of millions apart. entrenched that
funding, has operational problems or needs refinancing.
When a contractor’s payment applications are analysed, sums, while amounts serving notices. the dispute is almost
it often becomes clear that the resourcing schedules or The importance of a proper and timely notice being certified get certainly heading
programmes have not been followed. At this point, key When considering payment, the dangers of failing to adhere smaller. for the courts.
questions to ask include: to the strict letter of the contract should never be overlooked.
Tribunals are increasingly holding that notices are a condition
Was the original bid (and particularly the planned precedent to an entitlement to time and money, so contractors
resourcing) adequate? should always give proper and timely notices.
Is the contractor slipping behind the programme? However, year after year, we experience contractors failing to
give the right notices. This provides the purchaser with an easy
Is the contractor failing to lock its supply chain into back-to-
excuse to reject the claim and to refuse to engage on its merits.
back provisions, pricing and scope, leading to escalating
In the UK, project managers still fail to issue valid pay less notices,
but invalid claims for payment?
with insufficient detail or serve outside the contractual time
Is there poor supply chain management and control? limits, thereby preventing the purchaser from withholding
payment until the next certificate. Caroline Pope Richard Dupay
Does the progress being reported reflect reality? Partner, London Senior Associate, Dubai
If not, why not? Don’t delay taking action +44 (0)20 3400 4318 +971 (0)2 652 0329
The sooner a potential problem is picked up, the greater the caroline.pope@bclplaw.com richard.dupay@bclplaw.com
Very often, one or two ‘claims-type’ issues or events become the chance of it being resolved.
dominant focus, and proliferating change orders (or variations)
are overlooked. This can be short-sighted, as large sums of As lawyers, we understand the need to ‘follow the money’ when
money are routinely tied up in disputed change items, which bringing or defending claims for clients – i.e. identifying where
are left on the back burner. If significant non-agreed sums for there are significant sums of money in dispute, and then
change orders start appearing on applications for payment, following investigation into why that is the case.
ask yourself:
The same approach should be applied to projects — as soon
Why is there a proliferation of change orders? as the payment/application delta starts to increase, decisive
action must be taken to address the causes and prevent issues
Is the validity of the change being disputed? developing into claims.

Is it a change, or is it design development? So remember, there was a reason a lot of time, effort and
money was put into negotiating the contract. Good contract
Is the purchaser’s team falling behind with issuing formal administration of the payment process by both the purchaser
change orders, resulting in uncertainty as to the validity and contractor is one which uses and acknowledges the
of changes? contract, rather than allowing it to gather dust, or prop
open the site’s office door.
Is there a difference in opinion over how to value
the change?

Is there a lack of clarity over the scope of provisional sums?

28/ /29
MAKE THE SIX-FIGURE FEE WORTH IT: DUST OFF YOUR CONTRACT! 10 EARLY WARNING SIGNS

A loose grasp of agreed contractual terms


is all too common in construction projects,
and can land contracting parties in major
disputes. Alexandra Clough and Jennifer
Varley look at the telltale signs that a party
is failing to consult the contract, and how
this can increase risk and conflict.
What are the risks?
We often see clients spend significant sums on negotiating a
contract — tens or hundreds of thousands of pounds — only to
leave it ‘gathering dust’. The parties then carry on without
reference to the agreed terms until a dispute arises, when the
contract is hauled out of a long forgotten folder and lawyers are
called back in to sort out the mess.

Using (or not using) a contract in this way is a risky approach.


If a job goes well, there may not be a problem. However, the
contract is there to set out the allocation of risk and responsibility
between the parties. It also provides a framework for how the
parties should behave in particular situations. Things can get
difficult if this framework is not followed.

Sometimes, the team are upfront and tell you that they have
made a conscious decision “not to get contractual”. This can
be code for having no idea what the contract says!

30/ /31
MAKE THE SIX-FIGURE FEE WORTH IT: DUST OFF YOUR CONTRACT! 10 EARLY WARNING SIGNS

Who is responsible? How can you tell if your team is not referring to the
If the project faces any setbacks, proceeding without reference contract terms?
to the contract terms is ill-advised. It can mean that you There are some key warning signs that parties to a contract TOP WARNING SIGNS THAT YOUR
inadvertently take responsibility for a risk properly borne by
another, or you do something (or fail to do something) which
are failing to consult the agreed terms. Sometimes, the team are
upfront and tell you that they have made a conscious decision
CONTRACT IS ‘GATHERING DUST’
undermines your contractual rights. For example, it is not “not to get contractual”. This can be code for having no idea
uncommon for the contract to stipulate that a contractor has what the contract says!
to give notice in order to claim an extension of time or additional
monies. Failing to serve notice within that period could mean Another giveaway is when a party, if asked for a copy of the
that the contractor is not entitled to an extension of time, even contract, is unable to produce a copy in reasonable time.
where it is clear that an event causing a delay is the Very often, when we ask for a copy of the contract it takes an
responsibility of the employer. extended period for one to be tracked down – so it’s obviously
not being used by that party.
Running a project without reference to the contract terms is
certainly an early warning sign that the team is not necessarily You would expect the key stakeholders to have a pretty good
running the job appropriately. A lack of discipline in grasp of the terms of the contract and their clause numbers.
understanding and using the contract may be indicative of However, alarm bells ring when the team talks in general terms
or uses common construction terminology not used in the 1. Team says “let’s not get contractual”. 2. Contracting parties take a long time 3. Use of different terminology to
other causes for concern, such as a lack of record keeping,
particular contract. to produce a copy of the contract. that used in the contract.
a lack of an up-to-date programme or up-to-date costs
information and a general lack of control.
Contracts also set out requirements for contractual notices,
correspondence and processes. These should be followed even
if a project is running smoothly. Signs that the contract is not
being used include the project team being unable to produce
these documents, or producing lots of correspondence or
notices which do not resemble the contract’s allocation of risk
or processes.

Make the most of your legal investment


Filing your contract away in a soon to be forgotten folder 4. Not issuing contract notices 5. Correspondence and notices 6. Not following processes set out
and/or failing to follow its agreed terms is a risky practice. or correspondence. with no reference to allocation within the contract.
Using your contract as an ongoing framework for project of risk within the contract.
responsibilities and behaviours will ensure you not only make
the most of the legal investment, but crucially, take measures
to reduce the likelihood of a dispute.

Jennifer Varley Alexandra Clough


Senior Associate, London Senior Associate, London
+44 (0)20 3400 2255 +44 (0)20 3400 4341
jennifer.varley@bclplaw.com alexandra.clough@bclplaw.com

Using (or not using) a contract in this


way is a risky approach.

32/ /33
AMBIGUOUS CONTRACTS: BEWARE THESE SIX PROVISIONS 10 EARLY WARNING SIGNS

There will always be parties who


are prepared to take advantage
of ambiguities.

A great deal of disputes centre on different


interpretations of the same contract – and
ambiguities are rife when agreements
are reached under tight time constraints.
Richard Davies and Sara Paradisi explain
six key provisions that can cause problems.
The perils of imprecise drafting
Where there is doubt over the meaning of contractual provisions,
most legal systems require objective interpretation rather than
what was actually meant by the particular parties involved.
That’s why careful drafting is crucial – there will always be
parties who are prepared to take advantage of ambiguities.

Construction contracts are often based on tried-and-tested


standard forms, so look out for drafting errors in the party-drafted
amendments, or schedules and appendices, which are often not
drafted or checked by lawyers.

34/ /35
AMBIGUOUS CONTRACTS: BEWARE THESE SIX PROVISIONS 10 EARLY WARNING SIGNS

Six key drafting faux pas to look out for


We often encounter the following issues that can lead to disputes
or, at the very least, unpredictability:
REAL-WORLD WARNING SIGNS

1 2 3
Vague phrases Automatic use of boilerplate clauses Supplemental agreements
For example, “best efforts”, “reasonable Entire agreement clauses, variation It is tempting to ‘wrap things up’ when
endeavours”, “all reasonable efforts” and clauses, exclusive remedies clauses and the situation changes or there has been
1. Multi-million dollar 2. Subcontract didn’t 3. Subcontract didn’t 4. Completion of 5. Contractor lost out
“best endeavours”. If these phrases are limitation of liability clauses – these all significant time or cost overruns. Parties
frequent, there is a strong argument have their place when the parties want to ‘clear the air’ and allow the plant constructed include a clear allow the contractor construction on $1 million in delay
that the parties intended them to be deliberately intend to place parameters project to complete. However, most in the Caribbean. completion date. to extend completion was delayed for liquidated damages.
understood differently in each instance. around the contract, their obligations construction contracts already contain date as a result of its many months.
They are rarely defined. and their liabilities. However, such clauses the mechanisms for making interim own delays.
can lead to unintended results. For adjustments to scope, price and time
example, have the parties really thought without (potentially) surrendering one’s
about what losses they will incur and/or rights going forward. Formal side
what sums they can and can’t recover agreements need to be approached
from the other in case of a breach? with great caution, explicitly state what
Does the boilerplate exclusion clause is being amended and make sure the
get them there? amendments are consistent with the
contract as a whole. It can come as a
nasty shock later if a party intended to
revisit something.

Richard Davies Sara Paradisi


Partner, Abu Dhabi Senior Associate, Singapore
+971 (0)2 652 0330 +65 6571 6617

4 5 6 richard.davies@bclplaw.com sara.paradisi@bclplaw.com

Notice requirements No operable mechanism to adjust Unclear dispute resolution provisions


It is common for contracts to require a completion date, or no completion date Stepped or tiered dispute resolution
party to give timely notice of claims. Most We recently advised on a petrochemical clauses are often attractive at the
standard form contracts provide some plant in the Kingdom of Saudi Arabia, drafting stage because the parties see
mechanism to regulate the giving of such where the contract, in addition to not the benefit of having every opportunity
notices and the likely consequences specifying a clear completion date, did to resolve disagreements without formal
that will arise if notices are not given as not entitle the purchaser to extend the proceedings. However, this can backfire
stipulated in the contract. However, completion date as a result of delays as the tiers of dispute resolution forums
bespoke contracts frequently do not caused by its own acts. This proved fatal can be manipulated to cause delay.
express the consequences clearly to the purchaser’s claim for delay Often a party is not clear what, if any, the
enough (particularly when they are liquidated damages – it lost $40,000 for consequences would be of jumping a
severe), which they should for them to every day the project was delayed – step or what the appropriate final
be enforced. and the project was delayed for months. dispute resolution mechanism is.

Don’t wait until it’s too late


It can be particularly useful to have a fresh pair of eyes look at the contract once it is
executed but before the works are too advanced, in order to flush these issues out.
Finding out after the event that the project team’s assumptions about what was
agreed were unreliable, is too late.

36/ /37
PROJECT MANAGER: IT’S A DIFFICULT JOB, BUT SOMEONE’S GOT TO DO IT 10 EARLY WARNING SIGNS

Project managers, or contract administrators, have to walk


a fine line between being an agent of the employer and
acting as impartial arbiter of contractor claims. James
Clarke and Marcus Birch explain why it’s a tricky position,
and which two personality types you should be wary of.
The top complaints about project managers
1. Not coordinating with the contractor and the design team.

2. Poor management of the programme and failing to report progress and


delay accurately.

3. Not effectively operating the contractual mechanisms for the assessment


of the contractor’s claims for time and/or money.

It would be naive to think that a dispute couldn’t possibly arise if a contract was
administered perfectly. However, most would agree that fewer disputes would reach
a formal resolution process if contracts were better managed.

Problems of contract administration are often symptomatic of deeper-rooted tensions


in the underlying role of the project manager, the individuals who perform that role, and
the parties’ relationship with them.

So, what are the early warning signs that a contract is not being administered correctly,
and how should they be dealt with?

There is an inherent conflict of interest in the role


of the project manager.

38/ /39
PROJECT MANAGER: IT’S A DIFFICULT JOB, BUT SOMEONE’S GOT TO DO IT 10 EARLY WARNING SIGNS

The invidious position of the project manager Or a pushover?


There is an inherent conflict of interest in the role of the project On the other hand, a project manager who is overly generous
manager. They are an agent of the employer on the one hand, will give the impression of being a mere ‘post-box’ between TWO EXTREME TYPES
and the impartial arbiter of contractor claims on the other. the contractor and the design team. They will disengage from
project correspondence and meeting minutes, accepting
OF PROJECT MANAGER
In practice, these competing duties can lead to project
managers becoming an antagonising factor in a dispute. change and delay-related claims without challenge.
‘On-account’ assessments are made, deferring proper scrutiny.
Two polarised characterisations of project managers are
as follows: A pushover project manager will often, in the early stage of
works, certify applications for payment which are front-loaded
The first is the stubborn defender of the purchaser’s relative to reported progress. By the time final account
interests. This type of project manager might zealously negotiations begin, they are left with little room for manoeuvre
defend all contractor claims irrespective of merit, or commit given the overly generous starting point and inflated contractor THE STUBBORN DEFENDER THE PUSHOVER
to maintain their employer’s expectations of delivering the claims. In addition, the project manager may not follow Defends the contractor’s claims Agrees to everything the
project for the original price and duration no matter what. contractual mechanisms, fearing that issuing notices might
This attracts complaints from the contractor that the project irrespective of merit. contractor asks for, leading
prompt a dispute. The contractor is therefore not held to
manager is in the employer’s pocket and lacks impartiality. account for failing to issue notices in respect of events for to increased cost and delay.
which it claims additional entitlements. Progress reports lack
At the other extreme, albeit rarer, is the project manager who
the detail required to enable the employer to defend the
always follows the path of least resistance, saying “yes” to
contractor’s claims. Always stripping back contractor claims to static sum. Disengaging from project correspondence and minutes.
everything. Disputes with the contractor are avoided at all
costs. This tends to lead the contractor into viewing the project Such a project manager may be pressurised into certifying early Routinely rejecting or valuing at nil claims for Accepting change orders and delay-related claims
manager as a pushover, leading to an alarmed employer completion of works, despite outstanding or defective works. change orders. without challenge.
as the final bill increases, and delays mount. Alternatively, they may resist calls to properly assess the
contractor’s liability for delay and enforce the employer’s Increase in delay notices by contractor. Front-loaded payment claims leading to difficulties
These are admittedly the extremes. However, a project
entitlement to liquidated damages. agreeing final account.
manager has to tread a fine line in order to guide the parties Contractor withdrawing resources or deploying B teams.
away from disputes. Prevention is better than cure Not following contractual mechanisms to challenge
In either of the above scenarios, disputes are more likely to arise Arguments over mitigation/acceleration. the contractor.
A stubborn defender?
and escalate. Both approaches encourage contractors to
If the project manager is a stubborn defender, it is likely that Argumentative correspondence over work quality. Issuing early completion certificates despite
advance more aggressive claims – either in response to an
sums certified as due to the contractor will remain static, and outstanding issues.
overly-hard line by the project manager, or opportunistically Disputes over whether work is complete.
the discrepancy between the amount claimed and the amount
when seemingly faced with an open door to push against. It is
certified will increase as the project manager routinely strips Resisting enforcing purchaser’s right to
not suggested that such behaviours on their own cause
claims bare. The variation account in particular may be liquidated damages.
disputes, but they certainly can fuel them. Active engagement
disputed as the contractor’s claims for change, arising perhaps
by both the employer and the contractor is key to preventing
from a poorly coordinated design team, are routinely rejected
this behaviour.
or valued at nil. There may be an increase in contractor delay
notices, which the project manager dismisses as disputed risk The project manager’s role, with the conflicting duties that come
events, or events with no practical impact on the programme. with it, remains a valuable tool for managing the contractual
and commercial relationship between the employer and
Faced with this hardening position, the contractor may James Clarke Marcus Birch
contractor. Criticism is often levelled against the “administration
disengage from a project, reducing resources or deploying its Partner, Singapore Associate Director, London
of the contract”, but it is all too easy to direct it solely at the
‘B’ or ‘C’ teams. Correspondence may replace face-to-face +65 6571 6624 +44 (0)20 3400 4605
project manager. In fact, it is for all parties to administer, and
engagement and become more assertive and emotive in tone, james.clarke@bclplaw.com marcus.birch@bclplaw.com
ensure good administration of the contract, in order that issues
with challenges over workmanship and non-conforming work
that inevitably arise are dealt with efficiently and
meeting the contractor’s requests for a certificate of
contemporaneously under the contract.
completion. Positions become entrenched, making
resolution harder.

40/ /41
TERMINATION OF CONTRACT: WHEN RELATIONSHIPS TOTALLY BREAK DOWN 10 EARLY WARNING SIGNS

Some projects are so beset with problems Do you have grounds to terminate?
Most engineering and construction contracts allow parties
that despite heeding early warning signs, to terminate the contract if one party is in default, if it becomes
the relationship between purchasers and insolvent, or after a period of non-payment/suspension.
contractors totally breaks down. Caroline Many also allow the purchaser to terminate for any reason
(known as ‘termination for convenience’).
Pope and Bob Maynard outline the key
considerations and risks for purchasers Unless the contractor abandons or suspends the works, the
most common grounds for termination by a purchaser are for
if they decide to terminate. ‘default’ or ‘convenience’.

Warning signs that a contract is heading for termination However, when a contract goes wrong, purchasers rarely want
The issue of termination usually arises well into projects, usually to terminate for convenience. This is because they blame the
in the fourth quartile. Typical warning signs include: contractor for not delivering the project and expect it to pick up
the bill for an alternative contractor to finish the job.
Very significant delays.
That leaves only one palatable option for the purchaser –
Doubts about whether the contractor is putting in termination for default. The purchaser commonly argues that
enough effort. the contractor has failed in its contractual obligations (there are
various contractual grounds of failure), serves a default notice or
Disagreements over responsibility for key matters, notice to correct, and terminates if the contractor does not
such as testing and takeover criteria. rectify that failing. Examples include the contractor failing to
proceed in accordance with clause 8 without reasonable cause
Reductions in workforce. (FIDIC 2017 Silver Book), substantially failing to comply with its
Entrenching of positions on contract interpretation. obligations (NEC3) or failing to proceed regularly or diligently
with the works (IChemE).
External developments that reduce the purchaser’s
motivation to proceed.

Delay in itself does not mean that


the contractor is failing to fulfil its
contractual obligations.

42/ /43
TERMINATION OF CONTRACT: WHEN RELATIONSHIPS TOTALLY BREAK DOWN 10 EARLY WARNING SIGNS

Is the contractor obliged to proceed? Practical steps to take before issuing a termination notice
Delay in itself does not mean that the contractor is failing to fulfil
its contractual obligations. Arrange to secure the site before the contractor

The contractor is obliged to proceed continuously, industriously


demobilises to ensure materials and plant are not removed
during the rectification period.
WARNING SIGNS A CONTRACT
and efficiently with appropriate physical resources (labour,
Ensure your operations team is ready and able to take
IS HEADING FOR TERMINATION
materials and plant) in progressing the works steadily towards
completion [Faulkner v London Borough of Newham (1994)]. over operations on termination, without causing any
service interruption.
But an impasse between purchaser and contractor often
comes down to a dispute over risk allocation, or the cause Be ready to secure and insure the site and works !!??
of delayed progress. on termination. !?!?
?!?
Whether the breach is serious enough to justify termination will What if you get it wrong?
usually be judged objectively depending on the terms and Wrongful termination brings the risk of reputational damage
duration of the contract, the nature of the breach and, to a and potential financial consequences.
1. Slow progress. 2. Significant delays. 3. Doubts about the 4. Disagreement
lesser extent, the consequences (both legal and commercial) contractor working about responsibility
If a tribunal finds that the purchaser has terminated incorrectly,
of the breach. hard enough. for key matters.
the contractor becomes entitled to be paid the proper value
Therefore, the purchaser will need to be satisfied that the for its work up to the date of the termination (which it is due
contractor’s performance meets the criteria to justify irrespective of the termination) and its loss of profit on the
termination, and that contractual termination mechanisms are incomplete element of the project, (which it would need to
carefully and precisely followed. prove). This is far from straightforward, as the projects that
contractors struggle to deliver are often the very ones where the
While terminations are project-specific, in our experience, contractor has made major cost or technical miscalculations. It
certain points can be drawn out. also assumes there is no effective exclusion of claims for loss of
profit in the contract.
Key questions to ask yourself before issuing a default notice 5. Reductions in workforce. 6. Entrenched positions on 7. Reduced motivation
The contractor could also have claims for additional contract interpretation. for project to proceed.
How will the contractor respond to the notice? demobilisation costs, as well as any costs it was already
committed to paying, for example to its supply chain.
Is the default notice correct?
Wrongful termination would also prevent the purchaser from
Are those implementing the process aware of the
recovering the extra over cost of engaging an alternative
contractual termination timeline?
contractor, and its loss of income for any extended period of
Do they understand that it takes time to implement the delay to completion. It would also give rise to a risk of the project Bob Maynard Caroline Pope
contractual termination mechanisms? being delayed even longer than if the defaulting contractor had Partner, London Partner, London
been kept on, whilst the purchaser tenders for, selects and +44 (0)20 3400 4009 +44 (0)20 3400 4318
Practical steps you can take when issuing a default notice appoints an alternative contractor. And can a new contractor bob.maynard@bclplaw.com caroline.pope@bclplaw.com
be found who is willing to underwrite the existing design and
Monitor and carefully record what the contractor does and workmanship?
does not do to rectify the notified default. Record progress
before and during the rectification period, to ensure there is These risks must be weighed against the project’s delayed
a baseline against which to measure any performance income stream, and against the contractor’s entitlement if the
improvements after the default notice has been served. purchaser had exercised its right to terminate at will.

Ask whether your team has the skills and experience to To terminate or not to terminate? Morton’s fork
optimise the plant while you find an alternative contractor Purchasers consider terminating a project for a variety of
(this could involve a lengthy tender process). Take commercial reasons – from having reached the cap on
independent advice (engineering/architectural/ liquidated damages, to a relationship breakdown at site and
programming) on why the scheme proved hard to deliver. executive levels; combined with regulatory pressure to complete
This will help to satisfy you, your legal advisers and the scheme on time to avoid fines or prosecutions. For a
ultimately a tribunal (if the termination is contested), contractor, the reputational impact of having a major contract
that the contractor was in default. terminated can be significant, particularly as it must disclose
any terminations at pre-qualification for future projects.

The grounds to terminate are rarely black and white, so the risk is
substantial. Decision makers are rarely prepared to take the risk
of serving ‘termination for default’, fearing that their termination
will be held to be wrongful by a tribunal, but don’t want to let the
contractor off the hook by ‘terminating for convenience’.

The party seeking to terminate has to balance the commercial


reasons for terminating against that risk; a cost-benefit analysis
is essential.

44/ /45
OUR TEAM 10 EARLY WARNING SIGNS

OUR TEAM
HELPING YOU KEEP
CONTROL OF YOUR
CONSTRUCTION PROJECT
When your project is worth millions, we know how important GLOBAL REACH
it is to stay in control. That’s why our team of over 90 expert Our team has helped clients manage risk in over 40 countries.
construction lawyers focuses on helping you avoid nasty
ALGERIA CANADA GUERNSEY KUWAIT PORTUGAL TURKS & CAICOS
surprises in the first place.
AUSTRALIA CHINA HONG KONG LAOS QATAR TRINIDAD

To find out how we can help you keep control of BAHAMAS EGYPT IRAN LEBANON RUSSIA UNITED ARAB
EMIRATES
your project, simply call or email. BAHRAIN FRANCE IRAQ MACAU SAUDI ARABIA
UNITED KINGDOM
BANGLADESH GERMANY INDIA MALAYSIA SINGAPORE
Richard Davies UNITED STATES
BULGARIA GIBRALTAR JORDAN MOROCCO SPAIN
Partner, Abu Dhabi OF AMERICA
+971 (0)2 652 0330 CAMBODIA GREECE KAZAKHSTAN OMAN TURKEY
VIETNAM
richard.davies@bclplaw.com
YEMEN

> 1,030
> 90
Over 90 specialist
construction lawyers...
...with over 1,030 years of
combined experience...
13
...working from 13 offices
around the world.
Responsiveness: ten out of ten (and
I don’t give ‘tens’ away)…excellent.
Joint Managing Director,
mechanical and electrical
services contractor

46/ /47
Getting in touch
When you need a practical legal solution for
your next business opportunity or challenge,
please get in touch.
15195

bclplaw.com

You might also like