Installation of On/ Off

Split Air Conditioner


(R410A)

12th, Oct, 2015


By Cora Mo

Gree Electric Appliances Inc. of Zhuhai


contents

1 Preparation before Installation

2 Installation of the Air Conditioner

3 Inspection & Test Run

4 Maintenance

02
Preparation before Installation

1 Preparation before Installation

Tools

Precautions Skills
4

Preparation before Installation


Unit integrality checking

Precautions
Preparation before Installation

Basic Requirement on Installation Site

Precautions If the air conditioner is installed in the following places, it may cause
malfunction. If it is unavoidable, please contact the local service center.

Place with strong heat source, vapor,


flammable and explosive gas or volatile gas

Place with high frequency device

Coastal places

Place with machine oil in the air

Place with vulcanizing gas


Preparation before Installation

Electrical Safety Requirements


Precautions 1. The power supply shall conform to the value on the nameplate.
2.The unit can operate normally within the range of 90%~110% of rated
voltage.
3. Do not pull the power supply with excessive force.
4.The ground wire shall be connected reliably.
5. The air conditioner should be at least 1.5m away from the flammable
material.
6. For the air conditioner with a plug, the plug shall be within reach. For
the air conditioner without plug, there should be a breaker( normally, it is 2
times of the nominal current) in the circuit. The breaker shall be all open
type with a minimum contact distance of 3mm in all poles.
7

Preparation before Installation


Electrical Safety Requirements
Precautions

Circuit Breaker

Caution:
1.the outer material of the circuit breaker should be fireproof
2.normally, it is 2 times of the nominal current
Preparation before Installation

 Indoor unit checking


Precautions

3.0kgf/cm2 N2

If no gas coming out…


Preparation before Installation

Tools Spanners for fastening the


retaining bolts

Torque spanner for fastening the


retaining nut

Spanners for fastening the


retaining bolts
Preparation before Installation

Electric impact hammer, which will


Tools generate a certain stress to
improve the working efficiency of
drill a hole on the wall.

It can be equipped with two kinds


of aiguille, common aiguille and
special aiguille.

We can use the common one to


drill a hole for bolt and the latter
one to drill a bigger hole on the wall
for connection pipe.
Preparation before Installation

Tools Screwdrivers, one flat bade type and


one phillips type, for fastening the
screws of each parts

Ruler with level and suspension


weight, for horizontal and vertical
measure respectively

Pipe cutter and pipe expander for


pipe cutting and expanding
Preparation before Installation

Tools Clamp meter for AC/ DC current,


voltage, resistance, capacity
testing

Manifold gauge for pressure value


of the system

Vacuum pump for drawing out air in


system
Preparation before Installation

 pipe cutting and flaring


Caution 1: the pipe cutter should be vertical to the pipe axis .
Skills

vertical Not
vertical
Correct Wrong
Caution 2: Pay attention to the cutting speed and force to avoid deforming the pipe.

Too much
copper pipe is
force deformed

Wrong Wrong
Preparation before Installation
Caution 3: When removing the burr, the pipe orifice should be downward
to prevent the scrap from getting into the pipe.

Skills

Wrong Correct
Burr Pipe orifice downward


Double
surface Crack
1 Preparation before Installation

2 Installation of the Air Conditioner

3 Inspection & Test Run

4 Maintenance

02
Installation of the Air Conditioner

2 Installation of the Air Conditioner

 Process

2.2 2.3
2.1 select 2.4 connect wire
install mounting install outdoor
installation site of indoor unit
plate and drill holes unit support

2.7
2.8 connect wire 2.6 connect tube 2.5 install
install indoor unit
of outdoor unit of indoor unit drain hose
and outdoor unit

2.10
2.9 connect tube 2.11 vacuum
install drain block
of outdoor unit leak test
(heat pump unit)
Installation of the Air Conditioner

2.1 Selection of Installation Site

 Installation sketch

°²×°³ß´çͼ
Installation site of indoor unit
1.The air inlet and outlet should be far away from the obstructions. Ensure that the air
can be blown throughout the whole room.
2. The condensate is easy to be discharged. It is easy to connect to the outdoor unit.
3. It is out of reach of children.
4. It can bear the weight of the indoor unit and minimize the noise and vibration.
5. Ensure that there is enough space for maintenance.

6. It should be far away from the television and stereo, at least 1m.
7. Make sure that the indoor unit is installed in accordance with installation dimension
instructions.
8. Do not use the unit in the laundry or by swimming pool etc.
Installation of the Air Conditioner
2.1 Selection of Installation Site
Installation of the Air Conditioner

2.1 Selection of Installation Site

Problem?
Installation of the Air Conditioner
 Installation site of outdoor unit
1. The noise and the air
flow will not affect the
neighbor, the animal or the
plant.
2. There should be good
ventilation.
3. The air inlet and outlet
should be far away from
obstructions.
4. It can bear the weight of
the outdoor unit and
vibration.
5. Select dry places. It
should not be exposed to
sunlight or strong wind.
Installation of the Air Conditioner
 Installation site of outdoor unit

6.Ensure the installation complies with the installation


drawing. It should be easy for maintenance and service.
7. maximum length of connecting pipe and maximum
drop should be unit: m

Model 5K 7K 9K 12K 18K 24K


H 5 5 10 10 10 10 L
L 15 15 15 20 25 25

Note: H
“H” stands for “Max Distance Height”
“L” stands for “Max Distance Length”

8. It is out of reach of children.


9. It will not block the passage.
22

4 Piping/ Pressure/ Vacuum


Oil Trap
 Piping- Oil Trap ODU
1. All the traps installed on the
Drain
gas pipe Pipe
2. Oil traps are needed when the
Oil Trap
ODU is above IDU
3. When ODU is above IDU, each
6m for 1 oil trap on the vertical Liquid
pipe. Otherwise, each 10m for Pipe

1 oil trap. Drain


Pipe
Gas Pipe

IDU
U Trap
23

4. When ODU is above IDU, a J trap is suggested


to prevent the raining water coming along with the
pipe to the indoor side.

Oil Trap

C=3~ 5 x A
Installation of the Air Conditioner
2.1 Selection of Installation Site

Problem?
Installation of the Air Conditioner

2.2 Install mounting plate and drill holes

Install mounting plate

●level (level bar);


●mark the position of the 5 holes
●capable of bearing the weight
of 60kg.
Drill holes

Capacity D(mm)
05K~12K ¢55
18K/24K ¢65

Note:
“D” stand for dimension of the hole
Install wall pipe to protect the tube and
Drill holes the wire.

Note: clean site after drilling.


Installation of the Air Conditioner
2.3 Install support of outdoor unit

outdoor unit

Expansion
screw

● level and vertical; specification of expansion screw 10 mm×100 mm;


● at least 6 expansion screws for 05/09/12K unit; at least 8 expansion screw for
18K unit and above
● The support should bear at least 4 times of the weight of the air conditioner, that
is, at least 180kg.
Installation of the Air Conditioner

2.4 Connect wire of indoor unit

Open electric box cover 2. Connect power connecting wire and signal cable according
to wiring board.

wiring
Installation of the Air Conditioner

2.5 Install drain hose

Joint the drain hose


and discharge pipe
and fix them

Exchange the position of


discharge pipe and the block on
the other side if necessary.
 Drain Pipe

 If the pressure at the connection of


the drain pipe is negative, it needs to
Indoor
unit be fixed a drainage trap.
 A plug should be designed to make
clean easy

Plug
Installation of the Air Conditioner

2.6 Connect tube of indoor unit

Align nozzle to pyramidal face of valve connector.


Tighten the nut of the connecting pipe

Attention :
1.Connect the tube to indoor unit first and then outdoor unit.
2.The nut of the connector should not be too tight, or it may lead to
leakage.
Installation of the Air Conditioner

2.6 Connect tube of indoor unit Adding Refrigerant


If long connecting pipe is applied, it is necessary to add refrigerant according to the
following requirements.

The standard pipe is 5 meters.


Every increase of 1 meter should add corresponding refrigerant per below
chart
Whenever the pipe is over 15meters, every increase of 5meters should add
5ml corresponding refrigerant oil

Dimension of Connecting Pipe mm Throttle of Indoor Unit Throttle of Outdoor Unit

Liquid Pipe Gas Pipe Cooling Only , Heat Cooling Only Heat Pump
Pump (g / m) (g / m) (g / m)
Ф6 Ф9.52 or Ф12 20 15 20
Ф6 or Ф9.52 Ф16 or Ф19 50 15 50
Installation of the Air Conditioner
Connecting pipe, discharge pipe, wrapping wires

 Direction & tightness of wrapping


 Do not bend the drain hose to much;
 Drain hose should be under the gas pipe and liquid pipe.
 Insulate the indoor section of the drain hose.
 Water outlet of the drain hose should be vertical and suspending; do
not put it into water.
Installation of the Air Conditioner
2.7 Install indoor unit and outdoor unit
 Fix the indoor unit and route the pipe through the wall

 The bottom case of the indoor unit should cling to the wall.
The block of the connecting pipe should be tight to prevent dust.
Seal the hole with plaster.
Installation of the Air Conditioner

 Fix the outdoor unit

 Safety——drop prevention, vibration prevention


 Performance——avoid obstructions, noise prevention
Installation of the Air Conditioner
2.8 Connect wire of outdoor unit

Open electric box cover 2. Connect power connecting wire and signal cable according
to wiring board.

 Fix the wire with wire clamp.


 Install cushion rubber in the wire hole wiring
Installation of the Air Conditioner

2.9 Connect tube of outdoor unit

Refer to previous page for


connection
Installation of the Air Conditioner
2.10 Install water choke (heat pump unit)

 Condensate can be discharged through discharge pipe.

Install the connector of discharge pipe in Φ25 hole of the chassis. Put the water outlet of
the discharge pipe in a place easy for drainage.

Plug the other 3 drain holes.


Installation of the Air Conditioner

2.11 Vacuum & Leak Test

Vacuum Open the valve

1. Vacuum pump(R410A)
2. Connect the charge hose from manifold valve to the
service port of the gas valve and connect the
charge hose to the port of the vacuum pump.
3. Open the low pressure gauge and operate the
vacuum pump till the pressure is ≤-0.1MPa.
4. Close the pressure gauge first, then the vacuum
pump.
5. Observe the pressure gauge for 10-15mins, if it
returns to more than -0.08Mpa, there is leakage.
6. Check the possible leakage spots and repeat the
above.
7. When finish, Open the small valve a bit and close it
when the pressure reaches 0.05MPa, remove the
gauge quickly. (key process)
8. Completely open the small valve and then the big
valve, screw up the back cover screw nut of valve.
2.11 Vacuum & Leak Test
Installation of the Air Conditioner
Leak Test

 Soapy water: coat soapy water on the connector and the stop valve and keep for
3min. Bubbles indicate leak.
 In summer, test it when the unit is off. In winter, test it when the unit is heating.
 Electronic leak detector: test for 3s~5s
 Do not install the split air conditioner when it is rainy or snowy.
1 Preparation before Installation

2 Installation of the Air Conditioner

3 Inspection & Test Run

4 Maintenance

02
Inspection & Test Run

Inspection

Test Run
Others

Inspection

Items Possible results caused by improper installation

Is it installed reliably? drop of the unit, vibration or noise.

Is leak test performed? insufficient cooling (heating)


Is insulation good? Condensate , water drop
Is water discharged fluently? Condensate , water drop

Does voltage of power supply conform to Malfunction , burnout of parts


nameplate?
Are wire and pipe installed correctly? Malfunction , burnout of parts
Is the unit grounded? Electrical leakage

Does the wire model reach the requirement? Malfunction , burnout of parts

Is there obstruction near air inlet or air outlet? insufficient cooling (heating)

Are length of refrigerant pipe and refrigerant Insufficient or surplus refrigerant volume
volume recorded?
Others

Test Run

1.Preparation
Make sure you do a proper installation according to previous process.

2. Method
Test Run

1. Drainpipe test
• Open the panel and fill the water into evaporator slowly.

Note: (1) Make sure all procedure have been finished and the drainpipe is well installed.
(2) Pay attention to the speed and airflow volume when filling water, to avoid getting
wet of the electric part.
Test Run

2. Specification record(at least 15mins after operation)

① Air in/outlet temperature test


• Distance: horizontally 10cm from the air outlet.
• Temp. difference:the air in/outlet temp. difference should be more than 8℃
under cooling and be more than 15℃ under heating.

② Electric leakage test


• Test with test pencil and make sure the unit is not with electric leakage.

③ Pressure observation
• The low operation pressure value under 30℃ ambient temperature is around
0.8~1MPa(On/off),0.72-0.88Mpa(inverter)
1 Preparation before Installation

2 Installation of the Air Conditioner

3 Inspection & Test Run

4 Maintenance

02
Maintenance

4 Maintenance

Clean The air conditioner should be cleaned periodically.

cleaning