Professional Documents
Culture Documents
` DAR
Method Statement
METHOD STATEMENT
Issued by
Rev. # Date Description Prepared Checked Approved
Page 1
Document Type
` DAR
Method Statement
TABLE OF CONTENTS
1. TITLE
2. SCOPE OF WORK
General description.
Plant and equipment.
Materials.
Site planning & preparation
Work methodology.
Organization, Responsibilities & Supervision.
Work Force.
Risk assessments
Protective & Safety Equipment.
Contractual Requirements.
Information to personnel.
Emergency Procedures.
Permit Requirements.
4. ENVIRONMENTAL ISSUES
5. QUALITY RESPONSIBILITY
Contractual Requirements.
Critical works.
Inspection & Testing.
Follow up & Evaluation.
6. APPENDICES
Page 2
Document Type
` DAR
Method Statement
1. TITLE
2. SCOPE OF WORK
General Description
1. Crane
2. Forklift
3. Basic Mechanic Tools Box
4. Basic Electric Tools Box
5. Scaffolding
6. Painting Tools
7. Lifting Winch
Materials
1. Pipes & Fittings
2. Paint
3. Piping Supports
4. Insulation
5. Cladding
6. Cables, Wires & Wiring Accessories
1.
Page 3
Document Type
` DAR
Method Statement
All equipments and materials to be used will be delivered in the site from
storage area.
All equipments will be inspected by safety officer on site
The contractor will provide a route plan and access road prior to starting the
job.
All necessary safety measures will be provided.
If necessary, a traffic management will be included in the planning stage.
Work Methodology
Page 4
Installation
3rd compartment
Fig. 01
6 4 214 863 / 01
Installation
CAUTION
The cable must not contact any hot parts.
WARNING
! Boiler door hinges must be changed over
only by Hoval Service!
2 1 3
2
1
Fig. 02
4 214 863 / 01 7
Installation
+3
0
+3
0
collector and fix with tension springs.
Fig. 03
6. Place insulating mats (7.1/7.2/7.3/7.4) on the pins
moulded to the front wall of the boiler and secure with
the retaining discs (Fig. 03).
7. Wrap insulating mat (8) around the hinged flange and
secure with retaining discs (Fig. 03).
8 4 214 863 / 01
Installation
5.1
1.2 5.2
1.1
7.3
7.1
3
2 4
7.2 7.4
Fig. 04
4 214 863 / 01 9
Installation
2.3.2 Installing the cladding and boiler control Max-3 (420-750), Max-3 plus (420-750)
1. Hook the right side walls (9.1/9.2, Fig. 05) on the top 6. Insert 2 insulating mats (15.1/15.2) (to prevent ver-
longitudinal strutting and at the bottom in the pins at- tical circulation of air) longitudinally on the left and
tached to boiler rail (see detail A). right.
2. Hook the left side walls (10.1/10.2) on the top longitu- 7. Attach C-clips (16) to the top of the side walls (9.1/9.2/
dinal strutting and at the bottom in the pins attached to 10.1/10.2).
the boiler base rail (see detail A). 8. Mount all cladding covers (17.1/17.2/17.3).
3. Attach the bottom rear wall (11) to the special screws 9. Attach the top rear wall (18) to the bottom rear wall
in the rear side walls. (11) and attach the cladding covers (17.2/17.3) to the
4. Route the burner cable (12) with the burner connec- special screws on the top rear wall (18).
tion plug (12a) through the prepared bore hole in the 10. Fasten all cladding covers (17.1/17.2/17.3) at the
side wall, then attach the cable route with the rosette sides with self-tapping screws.
(12b) to the side wall. 11. Mount cleaning cover back onto rear of boiler (attach
- The burner must be connected to the boiler with the to the rear wall (18)).
standard plug connection. 12. Fix lead-through (19).
- The burner cable must be installed so that the plug 13. Installing door cladding:
connection has to be disconnected in order to swing - Fasten 4 threaded bolts (20) with nut and two wash-
out the burner. ers to the boiler door (see detail B).
5. Mount the boiler controller (13) and wire up the im- - Push insulating mat (21) onto the boiler door.
mersion sensor (14) and burner cable (12), see chap- - Install door cladding (22).
ter “2.3.7 Installation of boiler controller”, page 20. 14. Attach shield plate (23) to the front of the boiler (see
detail C).
WARNING 15. Affix labels and, where applicable, mount manual
! Capillaries must not be folded or kinked holder on the side.
10 4 214 863 / 01
Installation
17.2
17.3
19
17.1
10.1 18
15.2
14a 10.2
11
15.1
14
21
B
13 9.1
22
12 16
9.2
A,C
12a 12b
A B 20 C
9.2
23
20 22 21
Fig. 05
4 214 863 / 01 11
Installation
2.3.3 Installing the thermal insulation Max-3 (1000,1250), Max-3 plus (1000,1250)
Before starting installation, check the dimen- 1. Wrap the insulating mats (1.1/1.2, Fig. 07) around the
sion between the top edge of the boiler base boiler body (joint at the side, black side outwards).
rail and support rail. 2. Fit tension springs (2) to hold the ends of the insulat-
ing mats (1.1/1.2) together.
3. Fasten plastic straps (3) and strap fasteners (4).
- Do not overtighten the straps (reduced insulating
value).
4. Install insulating mat (5.1) and insulating panels
(5.2/5.3):
+3
0
- Wrap the insulating mat (5.1) around the flue gas
Fig. 06
6. Place insulating mats (7.1/7.2/7.3/7.4) on the pins
moulded to the front wall of the boiler and secure with
the retaining discs (Fig. 06).
7. Wrap insulating mat (8) around the hinged flange and
secure with retaining discs (Fig. 06).
12 4 214 863 / 01
Installation
1.1
7.3
7.1
3 4
2
7.2 7.4
Fig. 07
4 214 863 / 01 13
Installation
2.3.4 Installing the cladding and boiler control Max-3 (1000,1250), Max-3 plus (1000,1250)
1. Hook the right side walls (9.1/9.2/9.3, Fig. 08) on the 6. Insert 4 insulating mats (15.1/15.2/15.3/15.4) (to pre-
top longitudinal strutting and at the bottom in the pins vent vertical circulation of air) longitudinally on the left
attached to boiler rail (see detail A). and right.
2. Hook the left side walls (10.1/10.2/10.3) on the top 7. Attach C-clips (16) to the top of the side walls (9.1/9.3/
longitudinal strutting and at the bottom in the pins at- 10.1/10.3).
tached to the boiler base rail (see detail A). 8. Mount cladding covers (17).
3. Attach the bottom rear wall (11) to the special screws 9. Attach the top rear wall (18) to the bottom rear wall
in the rear side walls. (11) and attach the cladding cover (17) to the special
4. Route the burner cable (12) with the burner connec- screws on the top rear wall (18).
tion plug (12a) through the prepared bore hole in the 10. Mount cladding covers (19.1/19.2/19.3).
side wall, then attach the cable route with the rosette 11. Fasten all cladding covers (17/19.1/19.2/19.3) at the
(12b) to the side wall. sides with self-tapping screws.
- The burner must be connected to the boiler with the 12. Mount cleaning cover back onto rear of boiler (attach
standard plug connection. to the rear wall (18)).
- The burner cable must be installed so that the plug 13. Fix lead-through (20).
connection has to be disconnected in order to swing 14. Installing door cladding:
out the burner. - Fasten 4 threaded bolts (21) with nut and two wash-
5. Mount the boiler controller (13) and wire up the im- ers to the boiler door (see detail B).
mersion sensor (14) and burner cable (12), see chap- - Push insulating mats (22.1/22.2) onto the boiler
ter “2.3.7 Installation of boiler controller”, page 20. door.
- Install door cladding (23).
WARNING 15. Attach shield plate (24) to the front of the boiler (see
! Capillaries must not be folded or kinked detail C).
16. Affix labels and, where applicable, mount manual
holder on the side.
14 4 214 863 / 01
Installation
17
20
19.2
18
19.3
19.1
14a 15.3 10.2
15.2
11
10.1
10.3 15.1
22.2 14
22.1
B 9.2
13
23
9.3
12 16
9.1
A,C
12a 12b
A B 21 C
9.1
24
21 23 22.1
Fig. 08
4 214 863 / 01 15
Installation
2.3.5 Installing the thermal insulation Max-3 (1500-2700), Max-3 plus (1500-2700)
1. Wrap the insulating mats (1.1/1.2, Fig. 10) around the
boiler body (joint at the side, black side outwards).
2. Fit tension springs (2) to hold the ends of the insulat-
ing mats (1.1/1.2) together.
3. Fasten plastic straps (3) and strap fasteners (4).
- Do not overtighten the straps (reduced insulating
value).
4. Install insulating mat (5.1) and insulating panels
(5.2/5.3):
- Wrap the insulating mat (5.1) around the flue gas
collector and fix with tension springs.
- Remove cleaning covers from the back of the boil-
er. (The cleaning covers are reattached after fitting
the upper rear cladding walls (11.2/11.3, Fig. 11).)
- Slide insulating plates (5.2/5.3, Fig. 10) onto the
flue gas collector.
5. Place insulating mat (6) on the pins welded to the rear
wall of the boiler and secure with the retaining discs
(Fig. 09).
Fig. 09
6. Place insulating mats (7.1/7.2/7.3/7.4) on the pins
moulded to the front wall of the boiler and secure with
the retaining discs (Fig. 09).
7. Wrap insulating mat (8) around the hinged flange and
secure with retaining discs (Fig. 09).
16 4 214 863 / 01
Installation
1.1
7.3
7.1
3 4
2
7.2 7.4
Fig. 10
4 214 863 / 01 17
Installation
2.3.6 Installing the cladding and boiler control Max-3 (1500-2700), Max-3 plus (1500-2700)
1. Hook the right side walls (9.1/9.2/9.3, Fig. 11) on the 7. Attach C-clips (16) to the top of the front side walls
top longitudinal strutting and at the bottom in the pins (9.1/10.1).
attached to boiler rail (see detail A). 8. Position all cladding covers (17.1/17.2/17.3/17.4/17.5)
2. Hook the left side walls (10.1/10.2/10.3) on the top and fasten (17.1) according to detail B.
longitudinal strutting and at the bottom in the pins at- 9. Installing door cladding:
tached to boiler rail (see detail A). - Fasten 8 threaded bolts (18) with nut and two wash-
3. Attach the rear walls (11.1/11.2/11.3) to the side walls ers to the boiler door (see detail C).
and screw them in. - Push insulating mats (19.1/19.2) onto the boiler
4. Mount cleaning cover back onto rear of boiler (attach door.
to the rear walls (11.2/11.3)). - Cut a recess for the burner flange out of the insulat-
5. Route the burner cable (12) with the burner connec- ing mat (19.3).
tion plug (12a) through the prepared bore hole in the To achieve continuous thermal insulation be-
side wall, then attach the cable route with the rosette tween the boiler front and burner, the recess
(12b) to the side wall. in the insulating mat (19.3) must have the size
- The burner must be connected to the boiler with the and shape of the burner flange.
standard plug connection.
- The burner cable must be installed so that the plug - Push the insulating mat (19.3) into the recess be-
connection has to be disconnected in order to swing tween the insulating mats (19.1/19.2).
out the burner. - Install door cladding (20.1/20.2).
6. Mount the boiler controller (13) and wire up the im- 10. Affix labels and, where applicable, mount manual
mersion sensor (14) and burner cable (12), see chap- holder (21) on the side.
ter “2.3.7 Installation of boiler controller”, page 20.
WARNING
! Capillaries must not be folded or kinked
18 4 214 863 / 01
Installation
B
17.4 17.2
17.5
17.3
17.1 11.3
11.2
10.3
16
10.2 11.1
14a 10.1
14
19.1
C
19.2 9.3
13
20.2
20.1 9.2
19.3 12 21
9.1
A
12b 12a
A 9.1 C 18
9.1
18 20.2 19.2
Fig. 11
4 214 863 / 01 19
Installation
13b 13
13 13b
13c
13c
Fig. 15
WARNING
! Capillaries must not be folded or kinked
WARNING
! Capillaries must not be folded or kinked
Fig. 16
2. Hook the boiler controller (13) to the special screws.
1. Mount the special screws with nuts (13a, Fig. 12) on 3. Fasten boiler controller with the self-tapping screws
the side wall. Ø 3.5 x 6.5 and serrated lock washers (13b).
4. Pull the capillaries with the immersion sensors (14,
Fig. 17) through the opening in the side wall, insert
them into the immersion sleeve (14a) as far as the
stop and fix in position with retaining spring (14b).
Fig. 13
2. Hook the boiler controller (13) into the side wall with
16a
the recesses for the special screws.
3. Fasten boiler controller with 4 self-tapping screws 16c
Ø 3.5x 6.5 and serrated lock washers (13b).
4. Pull the capillaries with the immersion sensors (14,
16
Fig. 14) through the opening in the side wall, insert Fig. 17
them into the immersion sleeve (14a) as far as the 5. Plug in the burner plug.
stop and fix in position with retaining spring (14b). 6. Attach cover plate to the boiler controller (13c, Fig.
15) with self-tapping screws ø 3.5 x 6.5 and serrated
16a lock washers.
20 4 214 863 / 01
Technical information
3. Technical information
3.1 Description of the boiler
The Max-3 or Max-3 plus boiler is constructed in 3-compartment form. The flue gases flow from the cylindrical combus-
tion chamber into the water cooled reversing elbows and through the 2nd compartment into the front reversing cham-
ber. The 3rd compartment comprises a specially formed beading pipe through which the flue gases are conducted to
the flue gas collector.
4 214 863 / 01 21
Installation
4. Installation ref. a)
Flue gas systems according to EN 13384, part 2, execu-
4.1 Boiler installation room requirements tion types I and II are appropriate for modern firing sys-
The valid building supervisory regulations for the instal-
tems (advice from the specialist is necessary). Pay at-
lation location are applicable for the construction require-
tention to the flue gas temperature at rated output; see
ments for boiler rooms and their aeration and ventilation.
chapter 4.6, page 38.
In Germany the firing regulations for the individual Bun-
desländer are to be complied with.
ref. b)
The boiler should be connected to the flue gas system with
Make sure there is an adequate supply of fresh air to
a short flue gas pipe at an ascending gradient of 30-45°.
the boiler room,
Carefully seal the flue gas pipe against the flue gas system.
to ensure that the combustion air supply necessary for
The introduction of the flue gas pipe into the vertical part
all the firing systems operated there can flow in without
of the flue gas system (a) must be executed so that no
hindrance and that no oxygen deficiency occurs for the
condensate water can flow from the chimney into the flue
operating personnel.
gas pipe and the boiler. (Fig. 18)
The binding values for the size of intake air apertures
are not usually stated in the relevant regulations, it is laid
down only that the partial vacuum in the boiler room must
not exceed 3 N/m2. To comply with this requirement, an 30-45°
30-45°
air supply cross section of 500 cm2 is to be provided up
to a rated heat output of 1000 kW. With rectangular aper- a
tures the side ratio is not to exceed 1.5 : 1 and an appro-
priate supplement is to be made with grilles to ensure that
the free cross section reaches the above values.
NOTICE
If the flue gas temperature is under 160 °C,
the chimney must be watertight and acid re-
sistant.
30 4 214 863 / 01
Installation
Basic data:
NOTICE Flue gas pipeline 5 m long, 2 90° elbows and 1 45° elbow,
Normally only one heat producer may be outside air 15 °C, height above sea level max. 800 m, flue
connected to the flue gas system! gas pipeline same ø as flue gas connector on boiler.
Flue gas pipes longer than 1 m are to be insulated. You are recommended however to use the services of the
Where a transition element is necessary from the boiler specialist right from the planning stage!
flue gas pipe to the chimney inlet, this should be executed
as a slender cone. Chimneys are to be fitted with a water drain system to
permit the draining of any condensate.
The installation of a noise damper in the flue gas pipe is
from
vom
to
zumgas recommended to dampen flue gas noise.
flue
boiler
Kessel Schornstein In the case of boiler installation locations in the domestic
system
sphere, the flue gas pipe is to be flexibly connected with
Fig. 19 compensators.
ref. c)
Dimensioning the flue gas pipe cross-section. The cross
sections are to be calculated for boilers without delivery
pressure requirement according to EN 13384. (Please
note also DIN 18160, part 1 “House chimneys”). Take into
account the local, special situation (position of the house
on a slope, position of the flue gas pipe, roof pitch, flue
gas exit shape etc.)!
In Switzerland, take note of SIA Recommendation 384/4!
In Austria the calculation is carried out according to
ÖNORM M 7515.
3000
DW 600
2800
2600 DW 550
2400
output in (kW)
2200
DW 500
Nennwärmeleistung in (kW)
2000
1800
Rated thermal
1600
1400 DW 400
1200
1000
DW 350
800
600
DW 300
400
DW 250
0 5 10 15 20 25
Effective height
Wirksameof the flue gas
Schornsteinhöhe in (m)pipe in (m)
Fig. 20
4 214 863 / 01 31
Installation
15°
60°
45°
15°
G H
Dimensions Dimensions
32 4 214 863 / 01
Installation
CAUTION
! Failure to observe the guidelines and stand-
ards for the installation of burners can result
in damage to property and personal injury.
• On installing, comply with the guidelines
and instructions for fitting the burner to the
heat producer.
• Only burners tested according to EN 267 or
EN 676 may be used.
3. Fill the cavity between burner pipe and hinged flange
with the insulating wool provided.
4. For gas and dual-fuel burners:
If the weight of the burner (including attachments)
> 90 kg and the distance of the centre of gravity of the
burner to the door > 60 cm, support the burner hous-
ing weight directly with a strut to the floor.
11.0
1000 1800 2200
750 1250 1500
10.0
9.0
620
(mbar)
2700
resistance(mbar)
8.0
530
gas-sideWiderstand
7.0
420
6.0
heizgasseitiger
5.0
Heating
4.0
3.0
2.0
1.0
0.0
100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1400 1500 1600 1700 1800 1900 2000 2100 2200 2300 2400 2500 2600 2700 2800 2900 3000
Kesselleistung
Boiler (kW)
output (kW)
4 214 863 / 01 33
Installation
11
1000 1500
10
750
Heating gas-side resistance (mbar)
9 530
8 620
420
7
0
100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1400 1500 1600 1700 1800 1900 2000 2100 2200 2300 2400 2500 2600 2700 2800 2900 3000
kW = Boiler output
mbar = Flue gas resistance λ = 1.11 (Natural gas: CO2 = 10.8 %)
500 above sea level (Tolerance: +/- 20 %)
4.4 Fuel
NOTICE
The boiler is only to be operated with the fuel
stated on the boiler rating plate.
34 4 214 863 / 01
Installation
Fig. 21
4 214 863 / 01 35
Installation
4.5.2 Safety measures relating to • Measures must be taken in the building and on electri-
EMC-compliant assembly cal equipment to protect the units against overvoltage
caused by lightning strikes.
• Cables carrying mains voltage must be routed sepa- • The mains connection for the heating system must be
rately from sensor or data bus cables. A minimum dis- designed as an independent electrical circuit. Neither
tance of 2 cm between the cables must be observed. fluorescent lamps nor any other equipment which might
Cable crossovers are permitted. cause interference may be connected, nor may it be
possible to connect such equipment.
Minimum distances for electrical installation
Sicherung
Fuse Heizraumbeleuchtung und
Boiler room lighting
Steckdosen and power
auf getrenntem
Heizraum-
Boiler room sockets must be in a separate
Stromkreis anschliessen
15
≥ 15cm
cm Notschalter
emergency switch circuit
Netz 230
Mains 230V
V
Datenbusleitung 1212VV
Data bus line
2
≥ 2cm
cm
Wärmeerzeuger
Heat generator
≥40
40 cm
cm
Hier Do
nicht erden!
not earth here!
Basis-/ReglerModul
Basic/controller mitmodule
module with control BedienModul
36 4 214 863 / 01
Installation
4 214 863 / 01 37
Installation
420 530 620 750 1000 1250 1500 1800 2200 2700
180.0
170.0
160.0
(°C)
150.0
gas temperature(°C)
FlueAbgastemperatur
140.0
130.0
120.0
110.0
100.0
100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1400 1500 1600 1700 1800 1900 2000 2100 2200 2300 2400 2500 2600 2700 2800 2900 3000
Kesselleistung
Boiler (kW)
output (kW)
kW = boiler output - operated with heating oil EL, - A reduction of the boiler water temperature of -10 K
°C = Flue gas temperature if surface is cleaned, natural gas effectuates a reduction of the flue gas temperature
boiler flow temperature 80 °C, return tem- λ = 1.22 with max. burner output of approx. 6-8 K.
perature 60 °C (according to DIN 4702). (CO2 heating oil EL = 12.5 %) - A change in the air index λ of ± 1 % effectuates
a change in the flue gas temperature ± 8 K.
38 4 214 863 / 01
Installation
130
2700
1250 1800 2200
420 620 1000 1500
530 750
120
Flue gas temperature (°C)
Abgastemperatur (°C)
110
100
90
80
100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1400 1500 1600 1700 1800 1900 2000 2100 2200 2300 2400 2500 2600 2700 2800 2900 3000
Boiler output(kW)
Kesselleistung (kW)
kW = boiler output - operated with heating oil EL, - A reduction of the boiler water temperature of -10 K
°C = Flue gas temperature if surface is cleaned, natural gas effectuates a reduction of the flue gas temperature
boiler flow temperature 80 °C, return tem- λ = 1.22 with max. burner output of approx. 6-8 K.
perature 60 °C (according to DIN 4702). (CO2 heating oil EL = 12.5 %) - A change in the air index λ of ± 1 % effectuates
a change in the flue gas temperature ± 8 K.
4 214 863 / 01 39
Installation
40 4 214 863 / 01
Document Type
` DAR
Method Statement
RESPONSIBLE
POSITION COMPANY CONTACT NO.
PERSON
Project Manager
Construction Manager
QA/QC Manager
.
Lead Surveyor
Safety. Manager
DAR
- CONSULTANTS
.
RESPONSIBLE
POSITION COMPANY CONTACT NO.
PERSON
Resident Engineer
Page 7
Document Type
` DAR
Method Statement
Construction Manager - will be the one to plan and coordinate all activity in the
site and he will be responsible for coordinating with other contractor working in the
area.
Safety Personnel - will be the one to establish all necessary warning signs and
barricades establish the high risk areas in coordination with the Construction
Manager and constantly monitor the activity in terms of safety to all the workers.
Furthermore, he will give advice on current and forecasted safety issues and
concern.
Field Engineer – will be the one to implement the instruction of the Construction
Manager in the site, he will also directly supervise constantly the manpower and
equipment working in the area and implement all safety regulation and precaution
set by the safety personnel.
Quality Control Inspector – will be the one to inspect and monitor the area before
recommending to DAR Field Engineer for inspection.
Foreman – will be the one to supervise and assign the works as per schedule.
Labourers/Helpers– to assist in the construction.
Work Force
Page 8
Document Type
` DAR
Method Statement
Contractual Requirements
Shall adopt and promote the Zero accident policy for our performance of the
work under this contract.
Will appoint sufficient ES &H personnel to manage the work.
Managers and supervisors shall be familiar with an end force site rules,
regulations and all actions taken to ensure compliance with the ZHBG and
DAR ES &H Programme.
Shall ensure that all our equipment and operator are competent, experienced
and qualified.
Site management shall attend the weekly toll box meeting.
Safety Representative shall complete file and make available to the DAR
weekly tool Box Meeting Record.
Information to Personnel
All the manual workers that will be working in the site will be informed and
reminded by conducting morning tool box meeting in order to continuously
remind them of the existing safety risk and it will be handled by the designated
safety officer and sometimes with the presence of the safety personnel.
The STARRT card will be used before any work will proceed.
The third party certificate will be submitted to DAR Consultants for approval.
Emergency Procedures
The following are the safety procedure that will implemented in case of
accident:
Page 9
Document Type
` DAR
Method Statement
Permit Requirements
The following are the required permit before implementing the activity:
1. Encroachment Permit
2. Work Permit
3. Transport Permit
4. ENVIRONMENTAL ISSUES
Contractual Requirements:
Emergency Procedures:
5. QUALITY RESPONSIBILITY
Contractual Requirements
1. Shall implement and maintain an effective quality system in compliance with the
contractual obligations and conforms to the requirements stipulated on the
Project Specifications in construction of boundary wall
2. Will organized a QA/QC group headed by a qualified QA/QC Supervisor, in aid
of equally reliable QA/QC Inspectors.
3. Ensure that the procedures and instructions are issued for the performance of
all activities that bear an effect on quality.
4. Ensure by qualified inspection, that the work is carried out to the required
quality level.
5. Demonstrate by means of documented quality records that the construction
have been carried out and inspected to the required quality level.
Page 10
Document Type
` DAR
Method Statement
Critical Works
The possible
Inspection critical work for this activity is the wrong or improper way of using
and Testing
equipments and careless approach towards construction of boundary wall. The
wrong way of construction of boundary wall may cause injuries or fatalities.
Once the preparation is not properly done redoing the job will entail more time,
more labor and material cost.
Page 11
50-CL0014 / 2 / Page 1/1
Front plate
WELDLING
Rear plate
Pipes
Others
Welder identification plate (if
asked)
Flanges, pipes position
Raw material damages
Flue gas box - sealing
Refractory concrete
Seal - rope
DOORS
Door assembly
Door and hinge posi-
tion
Casing frame
Check welding pins for fixation
of insulation and "heavy roll
pins" at boiler base frame
Painting
Labels
Accessories, peep hole parts
Others
Inspected by + date:
Signature:
- OK
X - Fault Date of fault repair if any, operator signature
Application range:
Working pressure: bar < 6,0
Test pressure: bar 9,6
.,'
Operating temperature: oc < 120
Design temperature: oc 120
The product has passed all required quality control checks and pressure test (made
on xx.xx.xxxx) to the expectations of the quality controller.
1 Fuel LPG
2 Burner operation ✓
3 Modulation operation ✓
4 Boiler set point temperature ( oC ) 80
4 Flue Gas CO % 26
` DAR
Method Statement
Work evaluation will be based on facts, on the reports/results that has been
conveyed to the DAR, we see to it that it was truly done on the basis of its
requirements and integrity.
The QA/QC will be always open for suggestions, comments pertaining of their
performance besides, of its obligation to perform on highest quality level.
6. APPENDICES
Appendix A
CONFIRMATION OF INSTRUCTIONS TO OPERATIVES
Those names listed below confirm receipt of the method statement and have had the contents
explained to them/understand it and are aware of the site ES&H requirements.
Name Employer Date Signature
Note to contractor supervisor – Any significant change from this method statement requires it to be
revised and resubmitted to OBI before work can commence.
Page 12