=) aj man Refineries and Petochemicals Company Document Title: QCP / Installation of Neural SQaAQ} Sohar Refinery Improversent Project arthing Resistor OMPIC Suitanste of Oman Document No: $-000-5520-186 Rev 0 comatason opNow 120476102020 QUALITY CONTROL PROCEDURE INSTALLATION OF NEUTRAL EARTHING RESISTOR, 0/0] -|5/5/2/0]-(1| 8/6] wen: [ [S]- OMAN REFINERIES AND PETROCHEMICALS COMPANY SOHAR, SULTANATE OF OMAN mony Ww aa > | wereans [issue rorcoxsmaucrion [we x A | tansan201s | 1SSUE0 FOR REVIEW ne N wo | ‘Sus.FRM. QUA er 3 W6Et6 eat DAELIM Petrofac © ‘Oman Refineries and Petochemicals Company Sohar Refinery Improvement Project Sultanate of Oran ee v PAGES ‘Document Tile: QCP / Installation of Neutral ‘Eanhing Resistor ‘Document No: $-000:5520-186 Rev 0 Job No: 1208765 / 1.02022, 'SSURD FOR REVIEW THRST ISSUE "SUED FOR CONSTRUCTION Pevieft AELIM Petrofac ‘Oman Refineries and Petiochemicals Company Document Tile: QCP / Installation of Neutral $2491 Schar Refinery improvement Project Barthing Resistor IC Suita of Oman Dace Not S-0003520-186 Rev 0 Sante SobNos 120476) 102022 conrents 4.0 runvose. . 4 20 Score. : + 30. bern 7 ABBREAONS + 4a Rerenences.. : * So Resronsiauiv@ alionrTr 3 9 DESCRIPTION oF ACTVTE oS oF Senna Regents 3 62 Eaigmentspecon 5 63° Italien epecton 3 64 Testing of Resto deme é 63 Ipecton Te ati ‘ 66 Tote @ Henin EQvpment + 67 eye + So neconos : * 74 Sitter vrij Beant * BD APPENDICES : * “wcrroinamne «Ream Petrofac @ 10 20 30 40 ‘Oman Refineries and Petochemicals Company Document Title: QCP / Installation of Netral SQA! Sohar Refinery Improvement Project arthing Resistor OFPIC Sultanate of Oman ‘Document No: $-000-5520-186 Rev 0 Ee JobNo: 120676 / 1.02022 PURPOSE 1A The purpore o! this procedwe is to define the inspection and testing method, fcceptance entra Yor the instalation of Instalatlon af Neutral Eating Resistor and the responsibilty of censtructon and Quality Control personel with regard to thi proceaure. score 24 This Quay Corral Procedure defines the Quality Control activites andthe inspections {tests pertati to the installation of Neutral Eathing Restor 12.2. This procedure covers work up to and incluing mechanical competion DEFINITIONS / ABBREVIATIONS ‘company (RPIC-Oman (0€C or contracter Dalim Petrofac Joint Venture (DPIV)-Oman Projet Sohar Refinery improvement Project-Oman ace ualty Control Procedure a Inspection & Test Plan i Inspection & Test Record « uatity Control PPE Personal Protective Equipment et Request fr inspecton v ots w 2 Hl Vets vc 5 Direct Curent Ingres Protection se Heal, Safety, Secrty and Evironment REFERENCES -000:5520-162 Itntallation of Flectrical Power & Control Cables 5-000:5520-161 IP-nsaltation of Cable Tay/Ladder and Condult sytem 5-000-5520-164 nstallation of Power Transformers ‘Sacra guc aa ace AELIM Petrofac ‘Onan Refineries and Petiochemicals Company Document Tite: QCP / Installation of Neutral SQA! Sohar Refinery Improvement Project Earhing Resistor OFPIC Suitanste of Oman ‘Document No: 8-000-5520-186 Rev 0 Goth JodNo: 120876 / 1.02022, 5-000-5520-170 Ie-nstallation of Eathing and Lightning Protection sistem s-000:5520-189 {QP nstallation &specton Requrements Fo Cevied letrcal equipment 5.0 RESPONSIBILITY & AUTHORITY 5.1 The site Electra Engneer/Supervisor shal be responsible for ensuring that Neutral Enrhing Restors are installed ta an acceptable standard of workarship and in Accordance with applicable drawings and specications as well as mang request for Itspection (RF) t2 Quality Department at each stage of work as por the applicable HP requirements, 552 The Electrical C Inspector shall be responsible for verifying that work carted out is Complete, coract nd meet the specfed requirements 5.3. The Q€ Engh or his designee shall be responsible for ensuring that al inspections {nd tests ave witnsted based on approved ITP, recorded on applicable ITRIisted in Tana saned ot. 46.0 DESCRIPTION OF ACTWITIES {6.1 General Requirements 6.41 All material received at site shall be inspected upon receipt in accardance with Construction Management Procedure Tor Mater ReceWving. 6.4.2 Prior to removal ost, the equipment shall be Mentified and checked against the fata sha. (6.4.3 Allstallatin and testing wars shall be casi ut in compliance with the applicable project spectiatos. (6414 Tests shal 3e condicted by the Electrician under the supervision of Electra Sipervigrs and witnessed by Ue Quality Control inspector (Electrical) 6.45 The test shall be recorded as defined herein and witnessed by Subcontractor, Petrofac and Company 35 Indicated inthe applicable ITP. Prior to Ising the ‘epot forms, the iepecton items sal be signed by the Electrical GC Inspector. 6.2 equipment inspection 6 1 Prior to removal ost, the equipment stall be checked agains the data shoot to ‘eure confamity 6.2.2. The equipment shal be inspected for mechanical damage and where damage Is Served sal be reported according to Material ReceWing procedure. 6.3 fstallation Inspection “cpg Rd HE Trees DAELIM petrofac © ‘Oman Refineries and Petrochemicals Company Document Tile: QCP / Installation of Neutral = SQA! Shar Refinery Improverent Project arthing Resistor OFPIC Sultanate of Oman ‘Document No: $-000-$520-186 Rev 0 Cano | JobNo: 120876 / 31-0202 1634 ‘The nameplate shall be checked against the neutral earth resistor datasheet to stabi eonormity 6.32. Where netrl earth esstorauniiares are shipped loge, these shall be identified land checked against the equipment MRK Patel Receiving Report) 6.2.3 The resistor fstallation shall be carried ou by the electrical construction with the sistance of the sgging group (required. 1634 Prior to instalation, the resistor foundation shall be checked for cleanliness and love 6.2.5 The location and alignment of cables shal be checked to ensure sufficient Clearance for cable entry and glancing. 6.3.6 The resistor shall be inspected to ensure correct location, orientation and ligament for cabling, 62.7 The resistor shall be inspected for correct assembling as per manufacturer's dri 6.3.8. The resistor sal be propery insulated and ventilated. 639 Installation of CT (Curent Transformer) shall be verified against data shest/ rawr. {62:40 he resistor sall be propery coated for protection aganstcorosve and hut crvtonment by thanufacturer only and cing site Inspection verity that codon ot tis coating (62:11 All enclosure and resistor elements sal be clean and fre of dust (63:12 1 rating of resistor box and able box shal be mantained as per the requirement specified eata sheet name plat. 16.313 Inspection res sal be ecorded on SHR-FRALQUA.E-1101, {6.4 Testing of Resistor Element 164.1 Prioe to testi, resistor elements shall be clean and ensure that surface i free of dist. 6.42 Element redstance shall be messed and compared against nameplate (etaia/data sheet, Eosre to record ambient temporatre and hurity during the test 6.43 The Insulate resistance of the resistor elements shall be conducted between {enstoreloment and eat. Test values shal De 35 per ManuTactrers pulse data 6.44 Test rests all be recorded on SHR:FRI-QUAE-T1ODA, (6.5 nspoction & Tost Status {65:1 Inspection and Testing shall be carried out based on this document and applicable approved TP. 165.2. tnepection and Test results shall be recorded on rlovantITR indicated on the ‘Sgn cue acto AELIM Petrofac & > .q) Ont Refnries and Petocenicals Company Document Tile: QCP /Istalaton of Netra sQ4QI Sonar Refinery Improvement Project Eurthing Resistor OFAC stant of Oman Document No 0045520186 Rev Suse? BopNostanere/ anon applicable IPs an shall be signed off by al parties involved without any delay. 165.8 nspoction and Test status of each tagged items sfall be mabntained by QC Oman Refineries and Petochemicals Company Dactent Tie: QCP Installation of Neutral S210! Sohae Refinery improvement Project, arthing Resistor OMPIC Sultanate of Oman Document No: S-000-552 JabNos 120876, 1.02022 6.7.9 When required, necessary work permit shall be obtained from HSSE Department 25 per elevant ocedure 7.9 RECORDS 74 List of Verifying Documents (TRS) No. RN. Description + | shreeaquee-11014 | instalation of Neural Eathing Resistor 2. | sterrw-quice-st02a | Test Record for Neutral Eathing Restor 8.0 APPENDICES Ni ‘Scrat oe heehee DAELIM Petrofac

You might also like