PREPARED BY :
SUBMISSION DATE
12 MAY 2020
DEU SUBMISSION DATE
20 MAY 2020
Question 1 (i)
Info given:
break down = 1
Dump Truck [ n ] = 3 Days work = 10
Each dump truck = 150 m^3/day [excavated ]
Failure = 0.1
working = 0.9
Solution
Question 1 (ii )
check 1.00
daily output probability
(m^3/day ) output probability
328.05 0.73 0.00 0.00
72.90 0.24 150.00 0.03
4.05 0.03 300.00 0.24
0.00 0.00 450.00 0.73
Probability
0.60
0.50
0.40
0.30
0.24
0.20
0.10
0.03
0.00
0.00
328.05 72.90 4.05 0.00
Mean Daily out put
0.80
0.73
0.70
0.60
0.50
0.40
0.30
0.24
0.20
0.10
0.03
0.00
0.00
0.00 150.00 300.00 450.00
output ( meter cube )
0.03
0.00
0.00
0.00 150.00 300.00 450.00
output ( meter cube )
0.35
0.30
Probability
0.25
0.22 0.22
0.20
0.15
0.10
0.10
0.05
0.05
0.00
0.00
0.00 100.00 200.00 300.00 400.00 500.00
Output
Info givent :
The quantities for above items are calculated from longitudinal sections and cross sections
Length along cross-section area Volume (m^3 ) measured Fill needed = cumulative Length (m) Cumulative ( m^ )
road 100m from drawing fill x 100/90.9 volume (m^3 ) 0 0 3
Cut Fill
Cut Fill 200 40
0 0 0 0 400 110
200 400 +40 000 40000 600 140
400 300 +70 000 110000 800 129
600 0 0 +30 000 140000 1000 85
800 -100 -10 000 -11 000 129000 1200 30
1000 -300 -40 000 -44 000 85000 1400 8
1200 -200 -50 000 -55 000 30000 1600 28
1400 0 0 -20 000 -22 000 8000 1800 48
1600 200 20 000 28000 2000 26
1800 0 0 20 000 48000
2000 -200 -20 000 -22 000 26000
Table Quantity
Cross-section area
Fill cross-section area Cut
500
400
400
300
300
200
200
Cut and fill area
100
0 0 0 0 0 0 0 0 0 0 0
0
0 200 400 600 800 1000 1200 1400 1600 1800 2000
-100
-100
-200 -200
-200
-300
-300
-400
100
90
85
80
70 200m
300m
60
380m
50 48
40 40 37
32
30 28 30 28 26
24
20 19
300m
10 8 200m surplus 26000 m3
0 0
0 200 400 600 800 1000 1200 1400 1600 1800 2000 2200
Length along road in meter ( Figure 1 )
10 8 200m
0 0
0 200 400 600 800 1000 1200 1400 1600 1800 2000 2200
Length along road in meter ( Figure 1 )
From the table quantities, is expressed grafically in figure 1. If the cut material is use to supply the fill, then the volumes of earth moved over
haul distances 200 to 500 m can be read directelly off the graph for each haul.
Fill from borow pit = ( 132000 - 19000 ) + ( 37000 - 26000) = 124 000 X RM 9
= 124000 m^3 = RM 1116000
200 m
Cut and fill up = (140000 - 132000) + (19000 - 8000) = 30 000 X RM 6
to 200 m haule + (48 000 - 37 000) = RM 180000
m^3
200 m
Fill from borow pit = (126 000 - 24 000) + (32 000 - 26 000) = 124 000 X RM 9
= 108000 m^3 = RM 972000
300 m Cut and fill up = (140000 - 126000) + (2400 - 8000) = (30 000 X RM 6) + ((46 000-30 000) X RM 10)
to 300 m haule + (48 000 - 32 000) = RM 340000
= 46000 m^3
Total cost = RM 1072000 + RM 972000
+ RM 340000
= RM 2384000
Fill from borow pit = (119 000 - 28 000) + (28 000 - 26 000) = 93000 X RM 9
= 93000 m^3 = RM 837000
Cut and fill up = (140000 - 119000) + (2800 - 8000) = (30 000 X RM 6) + ((46 000-30 000) X RM 10)
380 m
to 380 m haule + (48 000 - 28 000) + ((61 0000 - 46 000) X RM 15 )
= 61000 m^3 = RM 565000
Fill from borow pit = (107 000 - 28 000) + (28 000 - 26 000) = 81000 X RM 9
= 81000 m^3 = RM 729000
Cut and fill up to = 117 000 - 107 000 = 10000 m^3 = 10 000 X RM 20
400 - 500 m haul = RM 200000
Summarize Result
Ploting data for economical haul diagram From graf economical haul diagram :
equation : y = -0.0039 X^3+ 7.6019 X^2- 4173.2 X + 30000000
Haule Distance Total cost
X = 390 m
200 2496000
y = -0.0039( 390^3) + 7.6019 ( 390^2) - 4173.2(390) + 30000000
= 2297356.89
300 2384000
= RM 2297356.89
380 2354000
From the economical haul diagram below the economical haul is 390 m and cost RM 2297356.89
500 2380000
COST IN RINGGIT MALA YSIA
2600000
2500000
f(x) = − 0.003935185185185 x³ + 7.60185185185196 x² − 4173.24074074078 x + 3058055.55555556
2400000
2300000
RM
2297356.89
390m
2200000
0 200 400 600
2300000
RM
2297356.89
390m
2200000
0 200 400 600
A
D
𝑡
_
1
𝑡
_
t 2
A = Dt_1
(Dt_1^2 h P)/(2 t)
Storing cost =
per week
(2t_1
= hP)/(2(t_1+t_2)) Equation 1
Now from similar trianglesQ/(t_1+ t_2 )= A/t_1 t_1=
(At_2)/(Q
−A)
Therefore, substitutingt_1 in equation (1)
storing cos per week (A^2
= hP)/2Q Equation 2
(Dt_2^2
= Z)/(2(t_1+ t_2)) Equation 3
To obtain optimum order size differentiative with respect to Q and A and maximise
Q= √(( 𝟐𝐒𝐃/𝐡𝐏 )) .
√(( (𝐙+𝐡𝐩)/𝐳) ) unit
TC = 345.2612 RM/week
√((𝟐 𝐗 𝟓𝟎 𝟏𝟐𝟎𝟎𝟎)/(𝟏/𝟐𝟎
= 𝐗 𝟐)) . √(𝟏𝟓/(𝟏𝟓+ (𝟏/𝟐𝟎) 𝐗 𝟐))