Four Laning of Kamalapuram to Oddanchatram section of NH-209 ( New NH-83) From Design Km. 0.000 to Km. 35.

822 ( Total
Length -36.505 km) under Bharatmala Pariyojona Phase-I under the Category of Residual Works of NHDP on HAM in the State of
Tamil Nadu.
Item No. Description Unit Rate Remarks

BOX culverts/RCC Drain

1 (a) Excavation in all kinds of soil cum 247

(b) Excavation in ordinary rock cum ---

(c) Excavation in Hard rock cum ----

2 PCC for Foundation cum 1156

3 RCC for Raft cum 1988

4 RCC for substructure cum 1988

5 RCC for superstructure including staging cum 2850

6 Fixing of weep holes no 140

7 HYSD Reinforcement MT 8000

MNB box

1 (a) Excavation in all kinds of soil cum 247

(b) Excavation in ordinary rock cum -----

(c) Excavation in Hard rock cum -------

2 PCC for Foundation cum 1156

3 RCC for Raft cum 1988

4 RCC for substructure cum 1988

5 RCC for superstructure cum 2850 Icluding Staging

6 Fixing of weep holes no 140

7 Crash barrier excluding steel Rmt 1986

8 HYSD Reinforcement MT 7500

9 Fixing of Drainage spout no 1500

10 Fixing of expansion joints Rmt 1700


Including pedestal
11 Fixing ofbearings no 3200
concreting
12 Stageing for Deck slab cum 462