Feasibility Studies Work Plan

Date Task Output


July 15 Groupings, Brainstorming List of Proposals
July 15-19 Consulting for Proposals, Approved proposal
Discussion of Chapter 1
July 20-25 Drafting of Chapter 1 Chapter 1
July 26 Deadline of passing chapter 1 Chapter 1
(not later than 4 pm )
July 29-31 Mock defense Defended chapter 1
Aug 5 Passing of revised chapter 1 Revised chapter 1
(not later than 4 pm)
Aug 7-8 Exam Exam
Aug 14 Discussion of chapter 2 and 3 Questionnaires/Letters
Aug 15-September 2 Data Gathering Chapter 2 and 3
Sept 4-6 Mock Defense Chapter 2 Defended
Sept 13 Submission of revised chapter 2 Revised Chapter 2 and 3
(not later than 4 pm) and 3
Sept 11-12 Exam Exam
Sept 16 Discussion of 4 and 5(Choosing Draft Chapter 4 and 5
of Consultant)
Oct 4 Passing of chapter 4 and 5 Chapter 4 and 5
(not later than 4 pm of sept
30)
October 4 and 7 Mock Defense Defended 4 and 5
Oct 9-10 Exam Exam
Oct 10-18 Passing of final paper Semi final paper
(not later than 4 pm of Oct 18) (with cp,toc,es,a,as,appen,rrl)
Oct 21-25 Final Defense Final defense
Oct 28-Nov 1 Incorporating Revision Revised paper
November 4 -12 Bookbinding Feasibility Studies

*failing to abide on the above schedule will result on deductions to your periodic grades.