Finalization of design and materials to be used for the project 1/27/2020 1/28/2020 1
Canvassing of materials 2/3/2020 2/5/2020 2
Purchasing of materials 2/10/2020 2/12/2020 2
Fabrication of the frame and hopper 2/21/2020 2/28/2020 7
Fabrication of the blades, counter blades and sieve 2/29/2020 3/7/2020 7
Purchasing of other materials needed 3/9/2020 3/10/2020 1
Final arrangement of the machine 3/11/2020 3/14/2020 3
Initial testing and evaluation of the machine 3/17/2020 3/18/2020 1
Conducting different trials for further improvement 3/23/2020 3/24/2020 1
Collection and analysis of gathered data 3/23/2020 3/24/2020 1
Calculation and organization of data 3/25/2020 3/26/2020 1
Preparation for oral defense 4/23/2020 4/24/2020 1
Finalizing of the papers needed 4/29/2020 4/30/2020 1
12/1/2019 1/20/2020 3/10/2020 4/29/2020 6/18/2020