Id Nome da Tarefa Duração Início Término Predecessoras

% concluída Junho 2020 Julho 2020 Agosto 2020


2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1
1 CRONOGRAMA POLANA PLAZA 40 dias Seg 8/6/20 Sex 31/7/20 13%
2 Ceramic Floor Works 28 dias Seg 8/6/20 Qua 15/7/20 15%
3 Terrace 21st 10 dias Qui 2/7/20 Qua 15/7/20 4 0%
4 Terrace 1st 5 dias Ter 23/6/20 Seg 29/6/20 5 0%
5 Terrace GF 5 dias Ter 16/6/20 Seg 22/6/20 6 0%
6 Floor -1 Laundry 1 dia Seg 15/6/20 Seg 15/6/20 7,30 0%
7 Hall of Elevators -1 to -5 5 dias Seg 8/6/20 Sex 12/6/20 80%
8 Ceiling Works (Stucture, Boarding and 23 dias Seg 8/6/20 Qua 8/7/20 43%
Plastering)
9 Ceiling Struture Laundry -1 3 dias Sex 19/6/20 Qua 24/6/20 10,45,30 35%
10 Ceiling Struture Hall of Elevator -1 to -5 3 dias Seg 8/6/20 Qua 10/6/20 75%
11 Ceiling Gysum Board Laundry -1 3 dias Qua 24/6/20 Seg 29/6/20 9 0%
12 Ceiling Gypsum Board Hall of Elevator -1 to 3 dias Seg 29/6/20 Qui 2/7/20 11 0%
-5
13 Ceiling Gysum Plaster 1st Floor 7 dias Seg 8/6/20 Ter 16/6/20 100%
14 Ceiling Gysum Plaster GF 2 dias Qua 17/6/20 Qui 18/6/20 13 80%
15 Ceiling Gysum Plaster Laundry -1 3 dias Seg 29/6/20 Qui 2/7/20 14,11 0%
16 Ceiling Plaster Hall of Elevator -1 to -5 4 dias Qui 2/7/20 Qua 8/7/20 15,11 0%
17 Painting Works 39 dias Ter 9/6/20 Sex 31/7/20 9%
18 All the missing Apartments (2ng Hand Walls 30 dias Ter 9/6/20 Seg 20/7/20 0%
and Ceilings)
19 Hotel 1st Floor Rooms 7 dias Qua 17/6/20 Qui 25/6/20 13 50%
20 Hotel 1st Floor Corridors 5 dias Qua 17/6/20 Ter 23/6/20 50%
21 Hotel GF 3 dias Sex 26/6/20 Ter 30/6/20 19,34 0%
22 Floor -1 5 dias Qui 2/7/20 Qui 9/7/20 15 0%
23 Hall of elevator -1 to -5 5 dias Qua 8/7/20 Qua 15/7/20 16 0%
24 Signaling of the Basement 12 dias Qua 15/7/20 Sex 31/7/20 23 0%
25 Carpet Instaltions 7 dias Qua 24/6/20 Sex 3/7/20 57,78 0%
26 Skiritng Instaltions 7 dias Qui 2/7/20 Sex 10/7/20 25 0%
27 Hydraulic Works 10 dias Qua 10/6/20 Ter 23/6/20 8%
28 Hotel TermoAc. Instalation Floor 1 to 3 7 dias Qua 10/6/20 Qui 18/6/20 20%
29 Floor -5 Rainwater Pump Instalation 3 dias Sex 19/6/20 Ter 23/6/20 28 0%
30 Floor -1 Piping Laundry 1 dia Qui 11/6/20 Qui 11/6/20 25%
31 Floor -1 Piping Basement 1 dia Sex 12/6/20 Sex 12/6/20 30 0%
32 PVC Piping Floor -2 to -5 3 dias Seg 15/6/20 Qua 17/6/20 31 0%
33 GF Sanitary Equipments 2 dias Qui 18/6/20 Sex 19/6/20 32 0%
34 Sprinklers Instalations 3 dias Seg 15/6/20 Qua 17/6/20 0%
35 Floor -1 Laundry Sanitary Eqp. Instalations 1 dia Seg 22/6/20 Seg 22/6/20 33 0%
36 Stair Works 26 dias Sex 12/6/20 Sex 17/7/20 20%
37 Hotel Stair Painting 15 dias Seg 15/6/20Sex 3/7/20 10%
38 Hotel Stair Handrail 9 dias Seg 15/6/20 Qui 25/6/20 35%
39 Residence Stair Painting 20 dias Sex 12/6/20 Qui 9/7/20 30%

Tarefa Resumo do projeto Tarefa Manual Somente início Data limite

Projeto: Cronograma Polana Pla Divisão Tarefa Inativa Somente duração Somente término Andamento
Data: Sex 12/6/20 Marco Marco Inativo Acúmulo de Resumo Manual Tarefas externas Progresso manual

Resumo Resumo Inativo Resumo Manual Marco externo

Página 1
Id Nome da Tarefa Duração Início Término Predecessoras
% concluída Junho 2020 Julho 2020 Agosto 2020
2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1
40 Residence Stair Handrail 16 dias Sex 26/6/20 Sex 17/7/20 38 10%
41 Electrical Works 39 dias Seg 8/6/20 Qui 30/7/20 11%
42 Cabling and Wiring 25 dias Qua 10/6/20 Ter 14/7/20 10%
43 Floor 3 2 1 2 dias Qua 10/6/20 Qui 11/6/20 100%
44 Ground Floor 3 dias Qui 11/6/20 Ter 16/6/20 43 0%
45 Floor -1 (Laundry) 5 dias Ter 16/6/20 Ter 23/6/20 44 0%
46 Baement -1 7 dias Sex 3/7/20 Seg 13/7/20 61 0%
47 Basement -2 to -5 3 dias Ter 23/6/20 Sex 26/6/20 45 0%
48 Lights and Instalations 17 dias Seg 8/6/20 Ter 30/6/20 31%
49 Floor 21st to 4th 7 dias Seg 8/6/20 Ter 16/6/20 0%
50 Floor 3 2 1 7 dias Qui 11/6/20 Seg 22/6/20 43 80%
51 Ground Floor 2 dias Seg 22/6/20 Qua 24/6/20 50,44 0%
52 Basements -1 to -5 2 dias Sex 26/6/20 Ter 30/6/20 51,47 0%
53 Board Instalations 39 dias Seg 8/6/20 Qui 30/7/20 7%
54 Floor 21st to 4th 30 dias Sex 19/6/20 Qui 30/7/20 0%
55 Floor 3 2 1 10 dias Seg 8/6/20 Sex 19/6/20 29%
56 Main boards Instalation/Connections 7 dias Seg 8/6/20 Ter 16/6/20 50%
57 Hotel rooms Boards 5 dias Seg 15/6/20 Sex 19/6/20 0%
58 Ground Floor 5 dias Qua 17/6/20 Ter 23/6/20 56 0%
59 Floor -1 (Laundry) 1 dia Ter 23/6/20 Qua 24/6/20 45 0%
60 Floor -1 to -5 5 dias Qua 24/6/20 Ter 30/6/20 58 0%
61 Tranformer and MV SwitchGear Instalations 7 dias Qua 24/6/20 Qui 2/7/20 58 0%

62 HVAC Works 18 dias Seg 6/7/20 Qua 29/7/20 0%


63 Grids Instalations 15 dias Seg 6/7/20 Sex 24/7/20 0%
64 Floor 21st to 4th 2 dias Seg 6/7/20 Ter 7/7/20 0%
65 Floor 3 2 1 9 dias Qua 8/7/20 Seg 20/7/20 0%
66 Corridors and Common areas 2 dias Qua 8/7/20 Qui 9/7/20 64 0%
67 Hotel rooms Grids 7 dias Sex 10/7/20 Seg 20/7/20 66 0%
68 Ground Floor 2 dias Ter 21/7/20 Qua 22/7/20 67 0%
69 Floor -1 to -5 2 dias Qui 23/7/20 Sex 24/7/20 68 0%
70 Exterior Units of the Hotel 2 dias Qui 23/7/20 Sex 24/7/20 68 0%
71 Ventilators Intalation 17 dias Ter 7/7/20 Qua 29/7/20 0%
72 Floor 1 5 dias Ter 7/7/20 Seg 13/7/20 4 0%
73 Ground Floor 5 dias Ter 14/7/20 Seg 20/7/20 72,5 0%
74 Basements -1 to -5 7 dias Ter 21/7/20 Qua 29/7/20 73 0%
75 Fire Detection Project (Extin) 34 dias Ter 9/6/20 Sex 24/7/20 17%
76 Firedetectors Intalation 31 dias Ter 9/6/20 Ter 21/7/20 20%
77 Floor 21st to 4th 2 dias Sex 17/7/20 Ter 21/7/20 79 0%
78 Floor 3 2 1 10 dias Qua 10/6/20 Qua 24/6/20 60%
79 Ground Floor 2 dias Qua 15/7/20 Sex 17/7/20 81 0%

Tarefa Resumo do projeto Tarefa Manual Somente início Data limite

Projeto: Cronograma Polana Pla Divisão Tarefa Inativa Somente duração Somente término Andamento
Data: Sex 12/6/20 Marco Marco Inativo Acúmulo de Resumo Manual Tarefas externas Progresso manual

Resumo Resumo Inativo Resumo Manual Marco externo

Página 2
Id Nome da Tarefa Duração Início Término Predecessoras
% concluída Junho 2020 Julho 2020 Agosto 2020
2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1
80 Control Panels 1 dia Sex 17/7/20 Seg 20/7/20 79 0%
81 Basements -1 to -5 15 dias Qua 24/6/20 Qua 15/7/20 78 0%
82 CO detector Instalation (Extin) 5 dias Sex 17/7/20 Sex 24/7/20 79,81 0%
83 Other Speciality Works 10 dias Qua 8/7/20 Ter 21/7/20 0%
84 Screen of the Apartments (21st to 4th) 10 dias Qua 8/7/20 Ter 21/7/20 0%
85 Access Controls 19 dias Seg 22/6/20 Qui 16/7/20 0%
86 Floors 3 2 1 (Locks) 7 dias Seg 22/6/20 Ter 30/6/20 57 0%
87 Basements (Barriers) 3 dias Qua 1/7/20 Sex 3/7/20 86 0%
88 Control Panels 2 dias Seg 6/7/20 Ter 7/7/20 87 0%
89 CCTV (Floor 3 to Basement -5) 7 dias Qua 8/7/20 Qui 16/7/20 88 0%

Tarefa Resumo do projeto Tarefa Manual Somente início Data limite

Projeto: Cronograma Polana Pla Divisão Tarefa Inativa Somente duração Somente término Andamento
Data: Sex 12/6/20 Marco Marco Inativo Acúmulo de Resumo Manual Tarefas externas Progresso manual

Resumo Resumo Inativo Resumo Manual Marco externo

Página 3