Foreword 3
Chapter 2 Introduction
2.1 Product Features
2.2 Application Fields
2.3 Function Introduction Chapter
Chapter 5 Operation
5.1 Before You Start
5.2 Start
5.3 Changing the frequency reference
5.4 Deceleration stop
5.5 Free stop
5.6 Power Off
5.7 Operating status monitoring
5.8 Conversion of variable frequency speed control system operation to bypass
operation (if optional bypass cabinet)
5.9 Switch from bypass operation to variable frequency speed control system
operation (if optional bypass cabinet)
5.10 Maintenance of frequency conversion speed regulation system
Chapter 9 Debugging
9.1 Commissioning routine preparations
9.2 Commissioning staff cooperation
9.3 Acceptance
Chapter 10 Maintenance
10.1 Safety instructions
10.2 Standard procedures for maintenance
10.3 Victoria Maintenance project
10.4 Maintenance log
Thank you for choosing ZINVERT series high voltage variable frequency speed
control system products of Guangzhou Zhiguang Electric Co., Ltd.
Guangzhou Zhiguang Electric Co., Ltd. can provide users with a full range of
technical support from selection, field installation and commissioning,
peripheral technology support to field acceptance, and other energy-saving
solutions and a variety of mature field technical solutions. . At the same time,
the company's high-voltage high-power variable-frequency speed regulation test
laboratory can also provide test conditions for the majority of user units to
study the feasibility of applying various high-voltage variable-frequency speed
control systems, and to learn, understand, and master the operation of high-
voltage variable-frequency speed regulation systems Performance provides
training conditions, please contact. Guangzhou Zhiguang Electric Co., Ltd. will
continue to work hard to create better technology, dedicate better products,
provide more thoughtful services, and "allow users to use electricity safely,
comfortably, and comfortably"-together with you for variable frequency speed
regulation technology And energy conservation cause to make greater
contributions.
In order to enable you to use our products conveniently and effectively, you
can understand the basic principles and use methods of products in the shortest
time, please read carefully before operating this product This user manual.
Chapter 1 Safety Instructions
The series of high-voltage frequency conversion speed regulation system is a
kind of high-voltage equipment. Inside the equipment there are dangerous high
voltages. At the same time, some components heat up due to long-term operation
and the temperature rises. Direct touch will burn the human body. When you
operate, maintain, and inspect the equipment on site, strictly follow the
requirements of this manual. Any incorrect operation may cause personal injury
or equipment damage.
1.2.6 Disposal
1.2.7 other
2.1 Features
The series of high-voltage variable-frequency speed regulation systems are
suitable for standard three-phase AC (3kV, 6kV, 10kV) three-phase AC motors,
and have the following characteristics:
Can be replaced in a matter of minutes with simple tools. The complete set has
safety protection and anti-misoperation blocking functions.
The high-voltage variable frequency speed control system has automatic bypass
technology of the power unit, which enables the system to operate with faults,
which greatly increases the reliability of the system and the availability of
user equipment. It is suitable for industrial field applications such as power
plants with high reliability requirements.
Thermal power generation: induced draft fans, blowers, dust extraction fans,
compressors, feed pumps, mortar pumps, etc.
Metallurgical mining: induced draft fan, ventilation fan, dust extraction fan,
mud pump, descaling pump, centrifugal feed pump, etc.
Petrochemical industry: Induced draft fan, gas compressor, water injection pump,
submersible pump, main pipeline pump, boiler feed pump, brine pump, mixer,
extruder, etc.
Cement manufacturing: kiln induced draft fan, raw material grinding induced
draft fan, pressure blower, main suction fan, cooler suction fan, cooler exhaust
fan, preheating tower fan, separator fan, kiln air supply fan, etc.
Water supply and sewage treatment: sewage pump, clean water pump, purification
pump, biological rough processing tower pump, oxygen supply blower, etc.
The operating frequency setting methods include: optional LCD panel setting,
control cabinet potentiometer setting, external 4 ~ 20m or 0 ~ 10V analog
signal input reference, switching frequency A variety of given methods such as
lifting and giving are optional.
Closed-loop control: The detection circuit obtains the actual value of the
controlled quantity and compares it with the set value to obtain the deviation
signal. The deviation signal is controlled by PID to control the frequency
control signal, and the motor speed is adjusted to reach the control amount, so
that it is consistent with the set value.
Local control: Use the keyboard on the system controller, the buttons on the
control cabinet, the potentiometer knob, etc. to control them locally.
Remote control: The system provides digital and analog input interfaces, which
are controlled by DCS.
After a momentary power outage in the power grid and recovery within a short
time (allowable waiting time of 0.1 seconds to 30 seconds, which can be set by
the user), the ZINVERT high-voltage frequency conversion speed regulation system
can automatically search the motor speed within 0.2 to 1.0 seconds to achieve
restart without impact. To the set speed, there is no need to wait until the
motor is completely stopped before starting to ensure continuous and stable
operation of the load.
2.3.5 Bypass function
Provide power frequency bypass and unit automatic bypass function to improve
the system reliability. Power frequency bypass can be switched automatically or
manually (need to be specified when ordering).
The torque boost and U / f acceleration curve can be set to adapt to different load conditions. Up to 3
resonance frequency avoidance zones can be set. The protection parameters of the motor and the
function definition of the output interface can be set according to the site conditions .
With the function of fault alarm and fault inquiry, it can improve the efficiency
of system fault elimination and provide convenience for users' operation and
maintenance.
Control program identification: AZ and 0-9 two digits (user selection need not
be considered)
Example: Guangzhou Zhiguang Electric Co., Ltd. produces a rated voltage of 6kV
and a rated capacity of 1250kVA. It adopts a cascade topology of a 6-level H-
bridge. The adaptive motor is an asynchronous motor. It is A10 type high voltage
variable frequency speed regulation system, and its model is ZINVERT-A6H 1250
/ 06YA10.
3.2 Components and configuration
The schematic diagram of the main structure of the high-voltage variable
frequency speed control system is shown in Figure 3-1 (Take the automatic bypass
cabinet and "one" arrangement as an example. The appearance of the product may
be changed after the product is improved without notice, this figure is for
reference only).
Figure 3-1
Power cabinet - Built-in power unit with back-to-back structure for efficient heat dissipation
Control cabinet - Built-in controller, PLCA and other core control systems may be integrated with the
power cabinet structure
Bypass cabinet - Optional, with automatic or manual solutions
Technical documents - User manual and necessary drawings and materials (see technical agreement
Bypass cabinet: Select as required. This component switches the motor to the
power frequency grid in the event of a system failure and performs the bypass
function.
Interface functions of user control systems such as the letter and DCS system.
The table below gives the general technical parameters of ZINVERT series high
voltage variable frequency speed control system products.
Note: The parameters listed in the table above are general general product
parameters, which can be customized according to specific engineering
requirements. The parameters in the table above are for reference only.
The superposition improves the harmonic performance of the output voltage and
reduces the dv / dt of the output voltage. The current multiplication technology
reduces the input-side harmonics and reduces the harmonic pollution to the power
grid. The main controller uses dual digital signal processors ( DSP), VLSI
programmable devices (CPLD and FPGA) as the core, together with data
acquisition, unit control and optical fiber communication loop, and built-in
programmable logic controller (PLC) form the system control part.
4.1 System composition and principle
The overall structure of a series of intelligent high-voltage variable-frequency
speed-adjusting complete systems
It can also be equipped with manual or automatic power frequency bypass switch
cabinet according to user requirements.
The secondary windings of the rectifier transformer are isolated from each
other.
The angular connection method ensures that the system works at a load of more
than 20%. The rate factor remains above 0.96.
Control the working state of IGBT, output PWM voltage waveform. Its electrical
principle is shown in Figure-1 shown. The unit output voltage is shown in Figure
4-2.
As shown, the harmonic content is small and is very close to the standard sine
waveform.
4.2 Control system
The control of the series of high-voltage variable frequency speed control
systems adopts open loop and voltage-frequency ratio control. The structure is
simple and reliable. The main control part uses dual digital signal processors
(DSP) as the control core, supplemented by ultra-large-scale integrated circuit
programmable logic devices ( CPLD / FPGA), analog input sampling (AD) and analog
output (AO) unit, digital input output interface (DI / O). The man-machine
interface consists of a large-screen Chinese LCD (LCD), a digital tube display
(LED), and touch buttons. The control part of the unit is based on a programmable
logic device (CPLD), and is equipped with a dedicated IGBT drive and protection
module and input voltage, output current, DC voltage, and device temperature
detection loop. The control signals of the main control part and the unit
control part are transmitted through optical fibers to effectively avoid
electromagnetic interference and ensure the reliability of system control signal
transmission.
The instantaneous voltage loss of the user's high-voltage power supply due to
bus switching, grid failure, etc. may occur. ZINVERT high-voltage frequency
conversion speed regulation system fully considers this situation, specially
designed power-off restart function, the maximum waiting time can be set to 30
seconds (function parameter code H03). After the voltage returns to normal, the
ZINVERT series high-voltage frequency conversion speed regulation system can
restart the high-speed rotating motor by itself within 0.1 to 1.0 seconds, and
the starting current is smooth and without impact to ensure the continuous and
stable operation of the user load. For different applications, users can
reasonably set the longest possible power-down recovery time according to their
own power grid conditions, or cancel this function by setting (function
parameter code H02).
4.2.3 Power frequency bypass function
When the frequency conversion speed regulation system fails or is shut down or
the frequency conversion speed regulation system is overhauled, the power
frequency bypass operation mode can be used to increase the utilization rate of
the user's load equipment and ensure the user's continuous production
requirements. According to different needs of users, it has manual power
frequency bypass and automatic work.
There are two ways of frequency bypass, which can be implemented in many ways.
They are designed and provided according to the user's process and equipment
requirements. The following two methods are used to introduce its operating
characteristics:
Manual power frequency bypass: ZINVERT series high voltage variable frequency
speed control system is designed with manual power frequency bypass wiring
principle as shown in Figure 4-6. Isolation switch is used as bypass switch
. When the frequency conversion speed control system fails or stops, or the
frequency conversion speed control system is overhauled, separate K1 and drive
K2 to the power frequency (for details, see 5.7 Conversion of frequency
conversion speed control system to bypass operation). The motor is directly
connected. The power frequency operation of the power grid, the load control
system is switched back to the traditional control methods such as dampers and
valves.
6kV, 10kV bus
Automatic power frequency bypass: ZINVERT series high voltage variable frequency
speed control system is designed with automatic power frequency bypass wiring
as shown in Figure 4-7. Vacuum contactors are used to replace isolated knife
gates. In order to ensure safety during maintenance, it can also be shown in
Figure 4
This chapter introduces the step-by-step detailed description of all the normal
operation steps after the ZINVERT series high-voltage variable frequency speed
control system is installed and commissioned. All the necessary operation steps
are numbered, and these operation steps must be strictly followed
accurately. Regarding the specific operation of the bypass cabinet, take the
common bypass schemes in Figure 4-6 and Figure 4-7 as an example. One-time
electrical wiring K1, K2 Please refer to Figure 4-7 for J1, J2, and J3.
Check that the output-side knife brake K2 is in the variable frequency position.
If a standard automatic bypass cabinet is selected, check the input and output
vacuum contactors of the frequency conversion speed regulation system:
Check that the input side vacuum contactor J1 is in the closed position,
Check that the output side vacuum contactor J2 is in the closed position.
Check that the position of each transfer switch and pressure plate in the
control cabinet is correct.
5.2 Start
According to the control mode selected by the "local / remote" switch on the
control screen, the frequency given in different control modes is as follows:
Step1: Close the high-voltage AC input line breaker.
Step2: Check whether the ZINVERT system is ready, the allowable operation
indicator on the control cabinet is on, check the controller panel for faults,
and the alarm indicator should be off. There are no warning and fault messages
on the controller LCD screen. If there is a fault and the alarm is not cleared,
please refer to Chapter 11-Fault Detection and Troubleshooting for
troubleshooting.
Step3: Enter the frequency reference and start.
For the method of inputting the frequency reference, please refer to the
following description of 5.3 Change Variable frequency reference. Then start
the system output:
"Local" control mode: press the "Start" button on the control cabinet;
"Remote" control mode: Start the variable frequency speed control system through
the remote control input contact of the "start" switch of the control system
run.
According to the setting of the function parameters of the controller F01 (for
specific settings, please refer to Chapter 6-Man-Machine Interface and Parameter
Settings), there are various setting methods
LCD Digital setting mode: The setting is controlled by the keys on the controller
panel. Enter the main interface of the LCD screen. At this time, the cursor
should stop at a certain position of the set frequency value. The "←" and "→
" keys can change the cursor position, and the "↑" and "↓" keys are used to
increase or decrease the cursor position. Value. For specific panel operations,
refer to Chapter 6, HMI and Parameter Settings.
Analog setting mode: The setting uses analog input to set the frequency, and
the target output frequency is set by adjusting the system's 4-20mA analog input
signal. The relevant setting parameters are: the output target frequency and
the function parameter F13 (maximum analog input frequency) corresponding to
the analog 20mA, and the output parameter F14 function (the minimum analog input
frequency) corresponding to 4mA.
Remote communication setting mode: The setting adopts the communication setting
with the remote, and sets the output target frequency to change the frequency
through the communication setting of the remote background monitoring system.
After setting the target frequency in the remote monitoring system, it is sent
to the controller through communication.
If it is controlled from a distance: the digital control will stop freely, and
the digital input contact will act in parallel with the control cabinet button.
If the user chooses an automatic bypass cabinet, the power frequency bypass of
the frequency conversion speed regulation system after a fault is automatically
performed in the following sequence (if manual operation, refer to the sequence
of operation of circuit breakers and contactors in this process)
After the inverter stops during a fault during frequency conversion operation,
the controller sends a node signal to control the incoming switch to open, and
then the controller sends a variable frequency to industrial frequency signal
to the PLC, opens J2, and delays 0.3 seconds to open J1. , And then delay J3
for 0.3 seconds to close. After the bypass cabinet is switched to the power
frequency state (that is, J3 is in the closed state and J2 is in the opened
state), and the incoming switch is in the opened state, the PLC sends a node
signal to control the incoming switch to close, and the motor switches to power
frequency operation. .
5.9 Power frequency bypass transition frequency operation
Step 1: Turn the manual / automatic knob on the control panel operation panel
to the automatic state. Allow power frequency conversion frequency board to
close.
Step 2: Press the power frequency change frequency button. If the bypass cabinet
is in the power frequency bypass state, the PLC output controls J3 to open,
delay 0.2 seconds, J1 to close, and delay 3 seconds, J2 to close. Switch the “
frequency / frequency conversion” switch in the control cabinet to “frequency
conversion”. Then perform the previous startup operation steps (see 5.2).
There are 15 LED light-emitting tubes on the panel of the controller, which
indicate the controller's power supply, CPU and operating status, and the
position of the output signal contact. The LED light-emitting tubes marked with
"signal" are used as system backup indicators, which has no practical
significance for the time being .
The 7-segment digital tube displays the display data during normal operation,
and the output frequency, voltage, current, and power can be selected. For
specific selection, the function number in the "parameter setting" is H16
parameter setting. This function sets the LED display content selection. The
specific settings and correspondence are shown in Table 6-1. Normally the output
frequency is displayed by default. When stopping after a serious fault, the
fault type number “EXXX” is displayed before the signal reset operation (see
Table 11-1 Alarm and fault information).
The definitions and functions of the nine buttons on the panel of the controller
are described in Table 6-2.
6.2 Basic interface display and operation
Basic interface
The LCD screen displays a variety of information, and in combination with key
functions, friendly human-machine interaction can be achieved. In order to
protect the liquid crystal, if the keyboard is not operated, the backlight of
the liquid crystal display will be displayed on the 20 LED digital tube and the
status indicator of the light emitting diode to determine the operating status
of the device.
The display contrast of the LCD screen can be set by the parameter with the
function number H17. The larger the value is set, the brighter the characters
of the LCD display, but the display contrast setting is too large to affect the
life of the LCD. Please make it clear when setting It is better to set it to
about 12 when the temperature inside the controller is about 30 ° C.
Ⅱ: When the system displays a warning message, the specific alarm content is
displayed (if there is more than one alarm message, it will be displayed in a
cycle);
Ⅲ: The current time of the system is displayed;
V: Prompts the keys and functions of the currently operable keys, and users can
perform corresponding operations according to the prompts.
The system is powered on and will stay on the normal operation interface after
initialization is completed, as shown in the figure below:
When the frequency setting key will increase the set frequency value,
When a fault occurs, the system will stop running. The LED digital tube of the
controller will display the fault type number “EXXX” (see Table 11-1 Alarm
and fault information), and the following “Fault Display” pops up on the LCD
display Interface, displaying fault information;
For detailed information, you can enter the main menu and select the "Event
Record" item to browse the fault records (see 6.3.6 Operation Guide). You can
view the status information of all faults. Users can refer to Chapter 11 Fault
Detection and Elimination according to the fault information and take
corresponding measures. If a fault occurs and the machine is stopped, the fault
must be eliminated first, and then the fault must be manually reset. The reset
operation can be performed by pressing the "function" button on the controller,
or the "silence" button on the control screen, or the remote "silence" remote
control button.
Stating no unit; Then it can be changed at any time; otherwise it can only be
modified after shutdown;
After setting the parameters, press cancel. If you press to cancel the change
of the value. If the user wants to return to the normal operation interface,
press to exit step by step.
If the parameter is not allowed to be changed during operation, and the user
attempts to change it, the system will pop up a menu to warn the user that the
"parameter cannot be changed". The system will automatically exit after 5s,
indicating that the parameter must be modified in the state of shutdown.
If the "Data Protection" function parameter with function number F01 is set to
1, any parameter cannot be changed at any time. If the user changes the
parameter, the system will pop up the "Parameter Setting Protection" menu to
remind the user that the parameter cannot be modified. The parameter can only
be modified again if the "data protection" function parameter of function number
F01 is set to 0.
After all parameter settings are completed, you should check and confirm again.
The user can check the parameters by entering the "Parameter View" item described
below.
Set to query, browse, and confirm.
"Parameter View" and "Parameter Setting" are basically the same, but there is
no password required for entering, and the parameters can only be viewed and
cannot be changed. If the user does not modify the parameter content and only
queries and browses the parameter setting content, it is recommended to enter
this item to ensure that the parameters are not changed unintentionally.
Operational monitoring
This interface provides more detailed data content of the current machine
operation than the normal operation interface. Its additional content includes
the following: DC voltage, controller power and temperature, etc., which are
displayed in three pages. Page 1 displays the current operating frequency, Input
power, output power, input current, input voltage, output current, output
voltage and other information; page 2
Display DC voltage information and output zero sequence voltage of each unit;
page 3
For the “bypass unit”, when a unit is bypassed, the “*” after the letter
ABC will show the specific level of the bypassed unit. For example, when the
failure of phase 8 of phase A is bypassed, the "bypass unit" will display: A 8
A * A *, B * B * B *,
* C * C *. A total of three levels of bypass can be displayed.
Interface 5 displays the unit status resident information. It is set when the
corresponding fault occurs. The system power-on reset or keyboard (remote) fault
reset key is cleared. For specific unit information, please refer to the “Unit
Fault Information Definition” in “Event Record”. table".
6.3.4 I / 0 check
Select "I / O Check" from the main menu and press the key to enter "I / O
Check "screen. It includes four sub-menu items: input switch value, output
switch value, analog port and PLC status.
I/O check menu interface
Key to move the cursor, then press to enter the corresponding submenu. When the
cursor stays at "input switch value", press "close" to switch on and off; "off"
means switch off, as shown in the figure below.
Input switching interface
"Output switch value" shows the current state of the output switch value,
similar to the "input switch value" screen.
“Analog Port” displays the current analog value of each port. The meaning of
specific values should be displayed according to user requirements.
"PLC status" shows the current PLC input and output switching value, input
analog quantity, output analog quantity
For the switch value "0000", the first bit from the left is the status of the
PLC's first switch value, and four are used as a group;
In the input and output analog quantity, the analog value required by the
technical agreement will be displayed.
Maintenance information
Select "Maintenance Information" from the main menu to clear the information
recorded.
Select "Event Record" and "Fault Record" from the main menu to record the system
status information when a fault occurs, and "Alarm Record" records the system
status information when a warning occurs, for users to query.
The record serial number starts from 1 to 1000. A total of 1,000 fault
information can be recorded. The serial number 1 records the latest fault
information. Among the 1000 messages, the serial number 1000 is the earliest
fault.
If the frequency conversion speed regulation system has never experienced a
fault or the fault information has been cleared, when entering the "Fault
Record" screen, the following screen will appear to remind the user that there
are currently no records that can be displayed:
If there is currently a record content, the system will display the event record
when the record fails, which is divided into three pages. Users can operate by
Use the key to switch pages in the same fault log. The content of the alarm log
information is consistent with the content of the fault log information .
"Alarm type" is the name of the fault or alarm. Please refer to Table 11-1
Alarms and Fault Information to further determine the cause of the fault or
alarm in order to eliminate the fault or alarm.
Fault record content page 1
Fault record content page 3
The "Unit Information" on the "Fault Record" page 3 records the unit status at
the time of the fault or alarm. It is displayed as a 4-digit hexadecimal number.
Each bit of the corresponding 16-bit binary number represents a unit of fault
or alarm information. If this bit is 1, it indicates that the unit is faulty or
an alarm has occurred. See the table below to determine the specific fault or
alarm type.
Waveform analysis
Select "Waveform Analysis" from the main menu and press the key to enter the
"Waveform Analysis" screen.
The waveform analysis menu includes five submenus: harmonic analysis, input
voltage waveform, input current waveform, output voltage waveform, and output
current waveform.
Waveform analysis main interface
The display interface of input voltage waveform, input current waveform, output
voltage waveform and output current waveform are basically the same. On the
"Waveform Analysis" display interface, the current operating frequency, the
effective value of the current line voltage and the current waveform are
displayed;
To enlarge or reduce the waveform display. The modifiable range is 1-9. For a
6kV system, when 9 is selected: 9 * 1000 V, that is, the minimum is 1000V and
the maximum is 9000V. The scale on the ordinate is the amplitude of the currently
displayed maximum displayable waveform.
6.3.8 Clock modification
Factory commissioning
The "Manufacturer Debugging" interface is used to query and modify some internal
information made by the manufacturer during debugging.
Factory debugging main interface
“Debug parameters” are some tests performed by the manufacturer when the
system is not powered. The user must not change any parameters, otherwise, it
will cause unpredictable failure or equipment damage.
"Operation record 1" and "Operation record 2" are respectively displayed for
some internal parameters of the system.
"Sampling value calibration" The parameters of the input and output PT and CT
are set and the offset is calibrated. The parameters have been set by the
manufacturer before leaving the factory. The user must not change or enter this
menu during system operation. No changes can be made.
"Charge and Discharge Test" is used by the manufacturer to test or check the
internal status of the system.
"Clear event records" Performing this operation will clear all alarm and fault
historical event records. "Maintenance records clearing" operations will clear
the maintenance information records. After entering this interface, the system
will prompt the user whether to perform a clear operation, and the following
prompt will pop up
Display page:
If you want to clear the records, you can move the cursor to "Yes" and press OK
to clear all records.
First column is Function Code, Second Column is Parameter Function Name, Third Column is
Setting Range, Fourth Column is Factory Value, Fifth Column is Unit, Sixth Column is step
change and Seventh column is Run Change
E12 - Digital input channel 13; E13 - Mode digital input channel 14; E14 - Mode
digital input channel 15; E15 - Mode digital input channel 16; E16 - Mode
digital output channel 1; E17 - Mode digital output channel 2 ; E18 - Mode
digital output channel 3 ; E19 - Mode digital output channel 4 ; E20 - Mode
switch output channel 5 ; E21 - Mode switch output channel 6 ; E22 - Mode
switch output channel 7 ; E23 - Mode switch output channel 8 ; E24 - Mode switch
output channel 9 ; E25 - Mode switch output channel 10 ; E26 - Mode switch
output channel 11 ; E27 - Mode switch output channel 12 ; E28 - Mode switch
Digital output channel 13 ; E29 - Mode digital output channel 14 ; E30 - Mode
digital output channel 15 ; E31 - Mode digital output channel 16 ; E32 - Mode
analog output channel 1 ; E33 - Mode analog output channel 2 ; E34 - Mode
reserved ; E35 – reserved ; C00 - skip frequency 1 ; C01 - skip frequency 2;
C03 - skip frequency 3 ; P00 - skip amplitude motor ; P01 - Number of pole
pairs; P02 - Motor capacity ; P03 - Motor rated current ; P04 - Motor No-load
current motor R1 ; P05 - Motor X1 number ; H00 - Restored to the factory set
value ; H01 - Instantaneous stop ; H02 - restart ; H03 - restart time ; H04 -
DC Braking voltage
Function code H05 H06 H07 H08 H09 H10 H11 H12 H13 H14 H15 H16
Rate DC braking time Motor overload inverse time protection input Motor overload
inverse time constant Motor overload time limit protection Motor overload time
limit warning current Motor overload time limit warning time Zero sequence over
voltage protection RS232 communication address RS232 communication speed
-15.0 0-1
Monitoring selection
-4
1
NYYYYNN
Parameter P Frequency 1 Increase amplitude frequency 2 Increase amplitude Speed
ratio L type Reserved
80 100 20 0-
1 10.1 1-
Chapter 7 Control System Interface
This chapter introduces the control system interface of the ZINVERT series high-
voltage variable frequency speed control system, mainly the setting,
characteristics and application of the control I / O interface. For additional
user interface information for the two parts listed below, please refer to other
appropriate sections.
Main power supply input, power output of variable frequency system: Chapter 8
Installation instructions. Bypass Cabinet and Bypass Functions and Operations:
Chapter 5 Operation
In order to ensure the normal operation of the system equipment and personal
safety, it is recommended to use a 50mm cross-section cable to connect the
ground copper bar at the bottom of the equipment cabinet to the field ground
copper bar.
In order to ensure the normal operation of the control system, all signal cables
should be shielded at the single end of the system and the analog signal or
communication cable should be shielded twisted pair. 7.1.3 Controller signal
interface
VDC, electromagnetic lock, etc. use 12VDC generated inside the system. Control
power supply voltage: 220VDC 35% ~ -20%
Digital input generally adopts optically isolated digital interface, and the
control power source uses 24VDC generated in the system. The type of digital
output can be customized according to technical requirements. Generally, there
are relay contacts or solid-state MOSFET interfaces.
The definition of each of the other digital inputs IN0 ~ IN15 can be selected
according to the design requirements of the electrical circuit in Table 7-1
Controller Digital Input Type Definition.
According to the factory setting design of the system, the existing input signal
definitions are shown in Table 7-2 Controller digital input factory settings.
The definition of other digital inputs can be configured by the commissioning
personnel according to the site conditions (function parameters E00 ~ E15).
There are 6 types of digital output hardware. Manufacturers need to set the
factory settings according to the actual functions and interfaces of the user's
engineering site (inconvenient to change on site):
Type: Normally closed direct output contact, the maximum number of which is 3
(OUT0, OUT2, OUT4). The output contact can be opened after the controller
applies an excitation, and the excitation cancel contact is closed.
Type: Normally open direct output type contacts, the number of which is 3 to 9,
OUT1, OUT3, OUT5 are normally open direct output type contacts. Type A output
contacts OUT0, OUT2, OUT4 and c type output contacts OUT6, OUT7, OUT8 are
required It can be changed to b type according to technical requirements.) After
the controller applies the stimulus, the output contact is closed and the
stimulus cancel contact is opened.
Type: Normally open output contacts that need to be started, the maximum number
is . There are 3 (OUT6, OUT7, OUT8). When this contact is closed, a start signal
must be output first to stimulate a power control. The relay turns on the power
of the output relay, and then controls the output contact to close after the
excitation is applied. There is no start signal to excite or the output relay
excites the canceled contact to open.
Type: Self-retaining direct output contact, there are 5 (OUT9 ~ OUT13), which
can be directly output by the controller. After the controller applies the
excitation, the output contact is closed, and the state of the canceled contact
is unchanged. Only when a common reset is applied After the stimulus signal,
all are disconnected.
Type: Self-retaining direct output contact, there is one (OUT14), the controller
closes the output contact after the start stimulus signal is applied, and the
contact state remains unchanged after the start stimulus is canceled. Only when
a reset stimulus signal is applied can the output contact break open.
Type: The device has a self-test fault signal contact. The number is one (OUT15),
which is directly output by the controller. When a power failure or a CPU fault
is detected, the output contact is closed, and the contact is open during normal
operation.
The parameter setting of the controller is shown in Table 7-3. There are several
types of digital output volume definition types, which can be set and selected
in the output with the same output hardware type.
According to the system's factory setting design, the existing output signal
definitions are shown in Table 7-4. Controller digital input factory settings.
The definition of other digital inputs can be configured by the commissioning
personnel according to the site conditions, or based on the as-built drawing
port definition. (Function parameters E16 ~ E31).
Analog input includes high-voltage input and output measurement, weak current
monitoring and control signals.
The power loop detection analog input is used for monitoring and protection of
the input and output voltage and current loops in the system. Both are installed
and wired inside the system, and no external wiring is required. See Table 7-
6.
The analog output is the internal output of the controller. The signal can be
selected to generate a weak current signal of 0-20mA / 4-20mA or 0-10V according
to technical requirements. It can be selected through jumpers and software
settings.
The options of analog output settings (function parameters E32 ~ E33) are shown
in Table 7-8 below.
Note: In the table, Fmax indicates the setting value of the maximum frequency
(function parameter F03), and Un indicates the setting value of the output rated
voltage (function parameter F05).
It indicates the set value of rated current (function parameter P02), and Pn
indicates the set value of output rated power (function parameter P03).
Chapter 8 Installation Instructions
This chapter introduces the electrical installation and mechanical installation
steps and precautions of ZINVERT series high voltage variable frequency speed
control system. Including the installation of the cabinet and the connection of
the ground, main circuit, motor and control part.
◆ Basic dimensions and spacing: For the cabinet size, external dimensions and
floor installation drawings of the frequency conversion speed regulation system,
please refer to the relevant drawings in the engineering technical data. All
cabinets should be installed as shown in the figure, and sufficient space should
be left on the periphery to ensure air flow and maximum door swing, as well as
the space required for maintenance. Provide access to the installation base
(aisle spacing, etc.) and ensure that space is provided to provide auxiliary
equipment for variable frequency speed control systems.
◆ Basic level and cable trench: ZINVERT's cabinet must be installed vertically,
and the foundation must be non-combustible material, smooth and wear-free
surface, moisture-proof and able to bear the weight of the variable frequency
speed control system (usually a channel steel base). Cable ducts must be non-
combustible materials (generally concrete, steel, etc.), non-abrasive surfaces,
moisture-proof, dust-proof, and measures to prevent animal entry.
◆ All incoming and outgoing wires must meet the requirements of electrical
insulation, and connection wires that do not meet technical requirements must
not be used to avoid potential risks to human life and user equipment.
◆ The electrical insulation distance of the high voltage part must meet the
requirements of the electrical safety distance, so as not to cause a short
circuit due to discharge.
◆ After all connections are completed, the electrical input of the system
should be tested for electrical insulation performance. The reference values
for the test voltage are as follows: 6kV system is 25kV, 10kV system is 35kV.
The actual insulation test voltage should be 75% of the above value during the
field handover test . If the air humidity at the site is obviously too high, or
there is a long period of high humidity in the long-term storage environment
before the system is installed, commissioned, and operated, you should pay
attention to
◆ The signs of high voltage parts must be clearly visible to avoid mistakes.
◆ Since the motor rotation is related to the phase sequence, the phase sequence
of the input and output lines must be completely correct during installation.
◆ Protection equipment
The high-voltage switch on the power side of the high-voltage variable-frequency
speed regulation system must be reasonably protected. The setting of the
protection setting should be performed with reference to the following
principles:
The switch must trip immediately when a short circuit in the transformer's
primary winding or primary incoming cable fails. The setting value of the
protection operating current should be guaranteed to avoid the no-load closing
inrush current of the rectifier transformer without tripping (it can be set to
8 to 10 times the rated current of the rectifier transformer).
Transformer secondary side fault protection adopts delayed trip mode. When the
transformer secondary side winding, the cable connecting the transformer
secondary side to the system unit and the unit input rectifier bridge are short-
circuited, the incoming switch can be tripped. The protection delay is short,
and the time setting can be adjusted to be set long enough to ensure that the
transformer does not trip during the inrush current. The setting value of the
operating current can be set to twice the rated current of the rectifier
transformer to ensure that the secondary side fault of the rectifier transformer
can trip within 500ms.
There are no special requirements for the cable from the circuit breaker to the
primary side of the phase-shifting transformer of the Zinvert series high-
voltage variable frequency speed control system. Its rated voltage value should
be consistent with the primary circuit voltage value. The rated current of the
cable should meet the transformer and protection settings. Design the cable
derating value according to the maximum expected ambient temperature, cooling
factors and other factors required by local electrical regulations, and install
according to the standard of medium voltage devices.
Since the output voltage and current waveforms of the ZINVERT variable frequency
speed control system are close to the standard sine wave, the cable does not
require special shielding. Therefore, no special measures need to be taken for
common mode current.
The user needs to ensure that the system's ground network is good, and provide
a good ground wire with a grounding resistance of less than 4 ohms. The cross-
section of the copper core cable used for the connection between the ground
point of the ZINVERT high-voltage variable frequency speed control system set
to the ground point of the power grid must not be less than 50mm. If the base
of the cabinet is welded and fixed to the base channel when the system is
installed, a separate copper bar or cable must be used to reliably connect the
ground points of each cabinet of the Zinvert series high-voltage variable
frequency speed control system complete set and ground it. The method is shown
in the following figure:
8.5. Auxiliary power and cables
The user should provide three-phase AC power without interruption. The auxiliary
three-phase power capacity required by ZINVERT high-voltage variable frequency
speed control system is not less than 10kVA (refer to the design drawing
requirements for the control power capacity of large-capacity systems above
2000kVA). If this power supply cannot be provided or the quality of the power
supply cannot be guaranteed, it must be specified when ordering.
Since the load includes a three-phase cooling fan, care must be taken to ensure
that the phase sequence of A, B, and C of the three-phase control power supply
is correct. The auxiliary power supply requires the use of a 380V three-phase
four-wire cable with a neutral line, and the incoming and outgoing lines.
Regulations should meet industry standards for power installations.
8.6 Control signal cable
Select the control cable according to Table 8-1. The shield of the cable is
grounded only on the single end of the ZINVERT high-voltage variable frequency
speed control system. One or more twisted pairs can be used. Whether to use
armored cables depends on the site conditions of the user. To prevent rodent
infestation, it is recommended to use armored cables or other corresponding
protection.
The wiring of the main power and motor cables must conform to national standards,
and please refer to according to the instructions and recommendations of the
cable manufacturer.
◆ If the cross-sectional area of the cable shielding layer is less than 50% of
the cross-sectional area of one phase, an additional ground wire must be added
along the cable to avoid cable shielding.
◆ Cable end According to the requirements of the cable manufacturer, the cable
must be installed with a cable connector at the end.
◆ Because the output voltage and current waveforms of the frequency conversion
speed regulation system are close to sinusoidal, the maximum length of the cable
connected to the motor only needs to consider its voltage drop, but it is
generally recommended not to exceed 1km. When the field cable length exceeds
1km, it should be proposed when ordering.
◆ The ground connection of the corresponding cable must comply with national
electrical installation standards.
In order to ensure the normal operation of the variable frequency speed control
system, it is necessary to ensure that various signal lines work normally
without being subject to various electromagnetic interference. Therefore,
external signal lines such as signal lines connected to DCS systems, remote
control signal lines, etc. When installing the output lines and various
measurement signal lines, you must pay attention to the correct installation of
these signal lines in the following aspects.
◆ Digital signal lines and analog signal lines should be routed as far as
possible to avoid mutual interference.
◆ If the signal line and power line must be routed in the same place, shield
the signal line to minimize the interference caused by the power line to the
signal line.
◆ Avoid parallel wiring of signal lines and power lines to avoid interference.
◆ The signal ground must be reliably connected to the shielded wire, and the
shielding layer must also be reliably grounded at one end.
◆ When necessary, the signal line can be connected with the external after the
metal conductive sleeve is threaded, so that various interference signals can
be reliably isolated to ensure the normal operation of the variable frequency
speed control system.
Figure 8-1 is a schematic diagram of the cabinet layout of the "1" layout of
the ZINVERT high-voltage variable frequency speed control system.
◆ Open all the cabinet doors and carefully inspect the variable frequency speed
control system and its accompanying equipment for possible transportation
damage. If any parts are damaged or lost, please contact the technical service
department and transportation company of Guangzhou Zhiguang Electric Co., Ltd.
immediately. Please pay attention to how to open the cabinet door.
◆ Check that the cabinet doors of the ZINVERT system are tightly closed. ◆
Carefully move the cabinet to its installation position.
◆ Check whether the door can be fully opened and closed. If not, you need to
adjust the level of the cabinet and its foundation. Check the mechanical and
electromagnetic lock on the door: the front door cannot be opened except the
door of the control part before and during operation. The electromagnetic lock
can only be opened after a high voltage power outage or forced release of the
pressure plate. If the cabinet door is open during operation, the system will
alarm.
Note: Please pay attention to the method of opening the cabinet door. Do not
open the cabinet door forcibly, or the equipment will be damaged.
8.8.3 Unit installation
The removal and installation of all unit packages must be carried out under the
guidance of engineering service technicians of Guangzhou Zhiguang Electric Co.,
Ltd. ◆ Unpack the unit module of the frequency conversion speed regulation
system, to inspect the unit module for possible transportation damage. If there
is any abnormality or damage, please contact the technical service department
of Guangzhou Zhiguang Electric Co., Ltd. immediately.
◆ Place the power unit on the unit guide rail and push it in place. Use the
attached bolts to secure it. Check that the contact resistance between the unit
housing and the guide rail is less than 1 ohm.
◆ During the installation of the power unit body, pay attention to the
protection of the optical fiber and the power supply line to avoid damage to
the optical fiber and the control power supply.
Warning: The cable connection of the power unit should be completed under the
guidance of service or commissioning technicians of Guangzhou Zhiguang Electric
Co., Ltd.
◆ For the output of the connection unit, connect the output wiring of each
unit in series with the in-phase unit according to the wire label. One end of
the highest unit of each phase is used as the neutral point, and the voltage of
one end of the lowest unit of each phase is used as the output. End U, V, W.
◆ Connect the control fiber. Note that the installation of the dust-proof
sponge cannot block the fiber head. Tighten the fiber head screw.
Other equipment):
◆ Ensure that ZINVERT is disconnected from the main and auxiliary grids during
installation:
The main circuit breaker of the high-voltage incoming line is open and under
maintenance, and the grounding switch is closed. The motor is disconnected from
the mains and grounded. The auxiliary power supply fuse has been removed.
◆ Open the cabinet door of the power inverter cabinet and the cabinet cabinet
door to perform all power wiring and secondary electrical terminal operations.
◆ Connect the input main power cable to the rectifier transformer once. If you
choose to choose the accessories of the bypass cabinet, the primary input cable
of the transformer is already installed in the box. The user only needs to
connect the external high-voltage input cable to the high-voltage AC input lines
A, B, and C of the ZINVERT device.
Auxiliary power cable should be routed from the bottom of the control cabinet.
Follow these steps:
◆ Open the front door of the control cabinet and connect the auxiliary power
cable to the corresponding terminal according to the drawing. If using a
shielded cable, strip the cable insulation at the cable entry and connect the
stranded conductor of the cable shield to the protective ground at one end.
Even if ZINVERT's main power and auxiliary power are cut off, dangerous voltages
from external circuits may exist in the control cables. The connection of
control cables must refer to the corresponding engineering drawings.
Chapter 9 Debugging
The series of high-voltage frequency conversion speed regulation system can
only be debugged by the technical engineers of Guangzhou Zhiguang Electric Co.,
Ltd. The function test, debugging and initial parameter calibration are
completed by the technical service engineer of Guangzhou Zhiguang Electric Co.,
Ltd. The final test, parameter calibration and performance test are completed
by the technical engineers of Guangzhou Zhiguang Optoelectronics Co., Ltd. Gas
Co., Ltd. with the cooperation of users. What the user must know is described
below.
◆ The wiring cables of the transformer, variable frequency speed control system
and motor have been connected.
◆ The shields of all cables are connected.
◆ The insulation of transformers, power cables and motors must be tested and
a test report submitted.
◆ Provide main power voltage.
During commissioning, the user must provide at least two professional electrical
technicians as necessary operating members for commissioning, which must meet
the following conditions:
Familiar with medium and low voltage electrical equipment and corresponding
safety regulations. Familiar with the user's load transmission process.
9.3 acceptance
When the commissioning is completed, the first draft of the commissioning data
should be accepted and signed by the user and the technical engineer of Guangzhou
Zhiguang Electric Co., Ltd. The commissioning report should be written by the
technical engineer of Guangzhou Zhiguang Electric Co., Ltd. The other was filed
with Guangzhou Zhiguang Electric Co., Ltd. for the record.
Chapter 10 Maintenance
This chapter introduces the overall maintenance plan of ZINVERT series high-
voltage variable frequency speed control system. Lists all preventive
maintenance and spare parts replacement work performed by users and service
technicians of Guangzhou Zhiguang Electric Co., Ltd. In addition, user
preventive maintenance work is described in detail.
◆ Before starting work on ZINVERT, you must carefully read and understand the
contents of Chapter 1 Safety Instructions. Guangzhou Zhiguang Electric Co.,
Ltd. is not responsible for all possible damages caused by you ignoring the
above.
◆ All maintenance work that requires power failure must be performed 30 minutes
after the main power and auxiliary power are disconnected. The input and output
isolation switches must be open and in a safe position and take reliable
grounding measures. The input high-voltage power supply terminal must be
grounded. Do not touch the high-voltage input circuit and the motor without
grounding the system. When the input high-voltage power supply is turned off,
the operation of the variable frequency speed control system, the motor and the
motor cable should wait for the DC capacitors of each unit box to be discharged
and the discharge indicator to light up.
◆ Some loads may provide a mechanical torque to the motor shaft. If this load
can drive the motor to rotate, the motor should be separated from the load,
short-circuited, or mechanically blocked before starting work.
◆ After the repair is completed, the power cannot be turned on until the
following checks have been made. The main power and motor are connected.
The auxiliary power supply and the control circuit are connected, and all
control platens and transfer switches are restored. No tools or foreign objects
remain in the cabinet.
All cabinet doors, including protective isolation nets and cabinet doors, are
installed and closed.
The following steps are standard operations when outage maintenance is required.
The contents in Table 10-1 that need to be shut down and maintained need to be
performed in accordance with the following steps to ensure maximum security:
◆ Safety measures: Make sure you are familiar with and fully comply with the
Safety Instructions in Chapter 1 and the safety instructions at the beginning
of this chapter.
◆ Turn off the auxiliary power and disconnect all external equipment that will
generate dangerous voltage to the frequency conversion speed regulation system.
The main power and motor are connected.
Auxiliary power and control circuit are connected. No tools or foreign objects
remain in the cabinet.
All cabinet doors including protective isolation nets and cabinet doors are all
closed at
◆ Restart the variable frequency speed regulation system, please follow the
instructions in Chapter 5.
◆ Check and clean the connection parts of various parts of the variable
frequency speed control system, the high voltage connection input / output
connection of the transformer cabinet, and all power input / output connections
of the power cabinet.
◆ The ground wire is an important part that must be inspected and must not be
forgotten.
◆ Regularly check the heat dissipation and ventilation of the equipment and
clean the ventilation channels.
10.3.2 Daily inspection
◆ Check the ambient temperature, humidity, vibration, etc. for dust, gas, and
condensation. ◆ Check whether the LED and LCD display on the controller panel
is normal. ◆ Check the system for abnormal vibration or noise and odor.
◆ Check the LCD for alarm information and recent event records to be processed.
◆ Check the dust filter of the air inlet on the cabinet door. If there is
obvious dust, remove it and clean it. When disassembling, pay attention that
the tools must not penetrate into the cabinet door to prevent electric shock. The
air filter should be cleaned and aired after drying.
◆ Check the operation of the cooling system: Put a standard A4 printing paper
at the air inlet of the dust filter of each electrical cabinet, and the paper
should be adsorbed on the dust filter.
◆ Use a vacuum cleaner with plastic nozzles to thoroughly clean the inside and
outside of the cabinet to ensure that the equipment is dust-free and ensure
heat dissipation. Care should be taken not to be near high voltage live parts
during maintenance.
Check the air inlet filter of the cabinet door, and clean it with a dry cloth
or vacuum cleaner after removing it. If necessary, it can be rinsed with tap
water after removal, but it should be thoroughly dried before reinstallation,
so as not to rust or affect the insulation performance in the cabinet.
◆ Remove the air filter on the cabinet door and remove the frame from the door
panel. ◆ Remove the filter mesh pad of the air filter and insert a new mesh
pad. ◆ Install the air filter frame of the filter and put it back in the
cabinet door. ◆ Record replacement date
◆ Rinse the replaced filter net, dry it and pack it for the next replacement.
10.4.5 Replace the fan
◆ Power off the system in accordance with the standard procedures for
maintenance described above. ◆ After taking grounding measures, open the power
cabinet.
◆ If an air duct is installed, remove the air duct interface and the fan fixing
plate. ◆ Remove the fan's power and control cable connectors.
◆ Use a wrench to loosen and remove the locking screws located on the left and
right sides, and remove the fan bracket.
◆ Replace with a new fan, and then fix the fan. If there is an air duct,
restore and fix the air duct interface.
A maintenance log must keep all records of maintenance work. Each record should
include: Date and time
According to the severity of the impact on the operation of the ZINVERT system,
there are two levels of fault information:
In order to restart the system after a shutdown due to a fault, the fault must
be manually reset after the fault is eliminated. You can press the "function"
button on the controller or the "silence" button on the control screen, or you
can operate the "silence" button if you set it in a remote place.
For specific fault types, see Table 11-1 Alarm and fault messages, their possible
causes, and solutions.
After the system is shut down or the alarm is maintained, if the power supply
of the controller is normal, the controller's LCD should have an alarm or fault
display, and the audible and visual alarm will start to alarm until the signal
is "silenced". If it is the fault that caused the shutdown, the fault code
"EXXX" will be displayed on the seven-segment LED digital tube. If the required
output contact is set in the parameter setting, then the corresponding digital
output relay contact will be closed (for specific setting and content, please
refer to Chapter 6 and Chapter 7 above) Relevant sections).
After a fault has caused a shutdown, if the function parameter H02 "Instantaneous
restart restart setting mode" is set to allow, then when the fault disappears
within the time set by the function parameter H03 "Instantaneous restart restart
waiting time" and the system automatically restarts successfully , The fault
signal will automatically return, and the acousto-optic alarm will automatically
stop alarming; otherwise, the LCD screen and the digital tube will keep
displaying the fault information, and the acousto-optic alarm will continue to
alarm until the signal is "silenced".
◆ Safety measures: Familiarize yourself with the contents of this chapter and
the safety instructions in Chapter 1.
◆ Check the fault records on the controller, and record the actual faults and
fault records in the controller in detail. And please do not clear the fault
record.
Refer to Table 11-1 for explanations of error messages. The table also gives
solutions to faults. Any fault and alarm information records include:
Parameters for system real-time operation (input and output current, voltage,
unit DC voltage, unit information, etc.) Controller control parameters (factory
reference);
◆ Detection:
Auxiliary power and control circuit are connected. No tools or foreign objects
remain in the cabinet.
All cabinet doors, including protective isolation doors and control section
doors, are closed.
Table 11-1 lists all error messages and all possible causes. Users should note
that many alarms and faults are related to specific equipment (such as the type
of transformer, cooling system) and external protection equipment provided by
the user. For specific solutions, refer to troubleshooting and troubleshooting
measures.
After the unit bypass function takes effect, the unit in the system is in the
bypass working state. At this time, the user should closely monitor the working
status of the system and run according to the derated load allowed by the
system. If conditions permit, it should be arranged as early as possible for
processing and replacement failures
The unit. The system will send an alarm signal when the unit is bypassed.
◆ When a unit has a bypass fault, the frequency conversion speed regulation
system uses a contactor to bypass this unit and the other two units of the same
level. (Neutral offset control algorithms can be used for special requirements,
and only the faulty unit is bypassed.)
◆ After bypassing, the system needs to be derated under large loads, and the
system operation remains unchanged under small and medium loads. Corresponding
to different series systems, the derating range that allows first-stage bypass
operation is different from . After the system of level 7 or higher is bypassed,
the control algorithm changes to ensure that the system can still run at full
load.
◆ Bypass operation signal is given to alert the user during bypass operation,
and the fault information on the LCD interface can be consulted to display and
locate the faulty unit.
When the ZINVERT series high-voltage variable frequency speed control system
needs to be checked and repaired after the system fails, if a power frequency
bypass is required, the standard manual bypass cabinet is separated from K1 and
K2 is switched to the “power frequency” position. The frequency bypass wiring
principle is shown in Figure 4-6), and the automatic bypass cabinet is separated
by J1, J2, and closed J3 (refer to the power frequency bypass wiring principle
shown in Figure 4-7). For specific operations, please refer to 5.7 Conversion
of Variable Frequency Speed Control System Operation to Bypass Operation. The
motor is directly connected to the power frequency operation of the power grid,
and the load regulation control system is switched back to the traditional
control methods such as damper and valve. Through the power frequency bypass
function, the adaptability of the entire system is improved to ensure the
continuous operation requirements of user loads.
When the load drive is switched from the industrial frequency to the ZINVERT
variable frequency speed control system after the maintenance is completed,
please refer to 5.8 Bypass Operation for Conversion to the Variable Frequency
Speed Control System Operation for specific operation instructions.
Table 11-1 Alarm and fault messages, their possible causes, and solutions
Code 005
Action alarm
Output current imbalance
Remedy-Check the cable connection-Check that the motor's contact switches and
safety switches are in the proper position. -
Sense current Hall measurement signal circuit-If the fault cannot be corrected,
contact Zhiguang. -Check the main input voltage circuit.-If the fault cannot be
eliminated, contact Zhiguang.
Check if the alarm is caused by an external event (such as: mains voltage under-
voltage, short-term interruption voltage), and make a record-if the power is
off, power off, check the unit input fuse-check the event alarm record, check
the relevant information display -If the problem cannot be solved, please
contact Zhiguang. -Check the fault records and related information display-
Check the motor and drive system selection and inverter ratings-If it only
occurs during acceleration, check the startup parameter settings and increase
the acceleration time-If the fault cannot be eliminated, contact Zhiguang
Company Contact. -The acceleration / deceleration time setting may be too short.
Check the startup parameter settings to increase the acceleration / deceleration
time.-This alarm is normal when overcurrent or quick-break protection occurs.-
Check the unit power and display conditions.-Check the communication fiber.-If
the fault cannot be ruled out, contact Zhiguang Company Contact. -Check each
setting parameter and reset it-Check each setting parameter and reset it-Check
the motor load
Check if the warning is caused by an external event and view the fault log. -
If the problem cannot be solved, please contact Zhiguang. -Check the status of
the high-voltage incoming circuit. -Check whether the high voltage live
indication device and its output contacts and wiring are normal. -If the problem
cannot be solved, please contact Zhiguang.
Code 014
Action alarm
Causes-The cabinet door is not closed properly-The cabinet door travel switch
is faulty-The control cable shield is not properly grounded-The input and the
bypass switch are closed at the same time-The disconnect switch travel switch
contact is faulty-The control cable shield is not properly grounded
Remedy-Check the closed state of the cabinet door-Check the door switch of the
cabinet door and its contacts-If the fault cannot be eliminated, please contact
Zhiguang Company. -Check the input and bypass switch status-Check the input and
bypass switch travel switches and their contacts-Check the isolation switch
contact leads and their shielding-If the fault cannot be ruled out, please
contact Zhiguang. -Check the 380VAC, 220VDC auxiliary power-Check the 24VDC
power output and generate the loop-Check the circuit monitoring relays and their
wiring-If the fault cannot be ruled out, please contact Zhiguang Company. -
Check whether the fan and its power circuit are normal-Check whether the fan
power circuit thermal relay is normal-Check that the shield of the external
signal circuit and its cable are not properly grounded-Check that the
transformer load and ambient temperature are compared with the rated value (make
a record) -Check whether the installation conditions meet the requirements
(whether it is exposed to the sun, whether the air circulation is good, etc.)-
Check whether the shield of the control cable is properly grounded-Check the
wiring of the temperature controller and its circuit-If the fault cannot be
ruled out, please contact Zhiguang Company . -Check
Check whether the air filter is normal-Check whether the wind pressure detection
sensor and its wiring are normal-Check the motor, fault records and load
conditions-Check all protection settings-Check ZINVERT and the external
protective input line and its cable shield and ground-Check The shields of the
external signal loop lines and their cables are not properly grounded-check the
fault records on the controller according to the corresponding alarm messages-
check the status of the external signals-check the screens of the external
signal loop lines and their cables
Includes: Input 380VAC control power abnormal Input 220VDC control power
abnormal 24VDC control power abnormal Control power detection relay failure
019 Air duct differential pressure alarm External motor protection alarm
Air filter, air filter problem-The wind pressure detector or signal shield is
not properly grounded-The motor's external protective device is actuated due to
a motor failure-The circuit of the protection circuit is disturbed-The alarm
signal connected to the external circuit-The shield of the control cable Not
properly grounded
The shield of the external lift control input signal cable is not properly
grounded
Single phase of external output cable or motor-Check whether the external cable
and motor are grounded-Check that the shield of the signal cable is not properly
grounded-The output voltage bus is unloaded, and the PT wiring problem is not
properly grounded. Cause-The main power supply voltage is too high, which leads
to overvoltage.-The detection circuit in the unit is faulty.-Output and load
changes (such as excessively rapid speed reduction) cause the motor to be in a
power generation state, resulting in overvoltage-the unit input fuse is blown-
the fuse is blown. Detect contact failure-Excessive ambient temperature-
Ventilation and heat dissipation system failure-Long-term over-rated current
output-Unit internal temperature detection circuit failure-Failure signal
keeping solution Check the DC voltage record value in the record Check whether
the main power voltage is within the allowable range If the detected DC voltage
appears during the deceleration process, please check whether the deceleration
time setting is reasonable-if the fault cannot be eliminated, please contact
Zhiguang Company. -Shut down, replace unit fuses and detect fuse signals.-If
the fault cannot be eliminated, please contact Zhiguang. Take measures to ensure
that the ambient temperature is within the required range. Check the ventilation
and cooling system. Check the system load and operating conditions. If the fault
cannot be ruled out, please contact Zhiguang.
Code 024
Action alarm
Perform signal reset as described in 11.2 Fault Display Section-Check the fault
information record and operation of the event record
Status monitoring, check the cause of the fault and remove it, and then reset
the signal according to the instructions in 11.2 Fault Display-If the fault
cannot be eliminated, please contact Zhiguang Company. -Check the cable
connection and input switch.-Check the input current CT wiring and signal
circuit.-If the fault cannot be eliminated, contact Zhiguang. -This alarm will
disappear automatically soon. If it cannot disappear, please contact Zhiguang
Company. -Check the fiber connection.-Check the unit indication, reset the
system, and restart the operation.-If the fault cannot be eliminated, contact
Zhiguang. -Check the fiber connection. -Check the unit indication display, reset
the system, and run again.-If the fault cannot be eliminated, please contact
Zhiguang. -Check whether the unit input fuse is normal. -Please contact Zhiguang
Company. -Check if the input voltage is abnormal. -Check whether the input
secondary voltage is normal. -If the fault cannot be eliminated, please contact
Zhiguang Company.
032 033
Alarm
Input The output voltage is lower or higher than the theoretical output
voltage. -Output voltage detection PT circuit failure-Input voltage exceeds
user set value (105% -115% of rated voltage). -Output current exceeds 1.2 times
of rated current
Whether the input voltage reaches-check whether the output PT secondary voltage
is normal-please contact Zhiguang Company-check the input power. -Check if there
is any abnormality on the motor side. -If it only occurs during acceleration,
check the startup parameter settings and increase the acceleration time.-Please
contact Zhiguang Company. Solution-Check if the fan control power is abnormal. -
Check if the fan is abnormal. -Please contact Zhiguang Company. -Check if ups
is on. -Check if the ups output is abnormal. -Check whether the power supply of
the thermostat is abnormal. -Check whether the cable connector of the
temperature probe of the temperature controller is tight. -Please contact
Zhiguang Company. -Check if the connection between the PLC and the controller
is loose. -Please contact Zhiguang Company. -Check whether the indicator lights
"Main CPU" and "Auxiliary Control CPU" on the panel are blinking (if they are
blinking evenly, the CPU is working normally). -Reset the frequency converter. -
Contact Zhiguang. -Check the fault records, and check the reason for the bypass
of the unit after the shutdown.-If the fault cannot be eliminated, please
contact Zhiguang Company. -Check whether the input voltage is normal. -Please
contact Zhiguang Company.
035 036
Alarm
Code 037
Action alarm
Type fan failure warning ups failure temperature controller failure PLC
communication failure internal error
Cause-Fan Failure
038 039
Alarm
040 041
Alarm
The communication between the controller and the PLC is faulty. -Internal
controller error.
042 043
Alarm
Units in the system are bypassed. -When the input voltage does not reach the
output voltage, in order to avoid output overcurrent due to output undervoltage,
the inverter automatically reduces the output frequency. -The controller power
board is abnormal.-The auxiliary CPU analog sampling circuit is abnormal.-The
controller temperature exceeds 50 & # 186; C.-The PLC analog input is
disconnected.
Whether auxiliary AC380V, DC220V and other power supplies are normally
provided. -Check if the ambient temperature is too high and the ventilation is
good. -Check if the net is blocked. -When using the PLC analog input channel,
please check whether the connection cable is correct or loose. -Please contact
Zhiguang Company. -Check the PLC battery. -Stop and replace the PLC battery. -
Please contact Zhiguang Company. -Check whether the high-voltage contactor
control operation circuit is normal. -Check the control of the high voltage
contactor
047
048
System control high voltage contactor failed.
049 050 051 052 053 Alarm Alarm Alarm Alarm Alarm
Code E001
Action stop
Solution-Check the output high-voltage wiring after the power failure, the
wiring between the units-stop the high-voltage, control the power to check the
Hall circuit wiring. -Please contact Zhiguang Company. -Check whether the actual
load condition matches the rated value of the motor drive equipment-Check
whether the motor and the variable frequency speed control system match within
the entire speed regulation range-Check the motor protection parameter setting
settings-Check the motor connection cable-Check the load and frequency Is the
speed control system working properly-Check the current Hall measurement signal
circuit-If the fault occurs during acceleration, the acceleration time may be
too short- If the fault cannot be ruled out, please contact Zhiguang Company
Contact. -Check the motor load and the rated parameters of the inverter speed
control system-Check the motor connection cable-If the fault only occurs during
acceleration, the acceleration time may be too short, increase the set time-
Check the current Hall measurement signal circuit-If the fault cannot be
eliminated, Contact Zhiguang Company. -Check the external cables and the motor
for grounding-Check that the shield of the signal cable is not properly grounded
E-002
Downtime
E-003
Downtime
The load condition does not match the rating of the motor and the variable
frequency speed control system-the motor stalls, continuously
E004
Downtime
E005
Downtime
E006
Downtime
Code E007
Action stop
Remedy-Check if the warning was caused by an external event and view the fault
log. -If the problem cannot be solved, please contact Zhiguang. -Check all the
setting parameters and reset them corresponding to the setting parameter record
table. -If the problem cannot be solved, please contact Zhiguang. -Check that
the input wiring is intact. -Check the CT circuit, secondary output and wiring.-
Check the cause of the bypass and the number of abnormalities in the multi-
level unit. -Contact Zhiguang.
E008
Downtime
E009 E010 E011
Shut down
E012
Downtime
Input current abnormal Input over-voltage unit bypass power-down output over-
current flow protection
When the inverter is not running,-check whether the input and output wiring of
the transformer is normal. Transformer input current is abnormal. -Check whether
the transformer is normal. -The input current is outside the allowable range. -
The input voltage exceeds the allowable voltage range. -Check if the input
voltage is abnormal. -After the unit is bypassed, the unit input loses power.-
Check whether the input voltage is abnormal.
E013 E014
Downtime
E100
Downtime
Detect the motor and its load Detect the motor connection cable Detect the
current Hall measurement signal circuit If the fault cannot be ruled out, please
contact Zhiguang
Company Contact. Test transformer wiring and input test motors, output
connection cables, and load test current Hall measurement signal circuits. Check
the transformer's insulation withstand voltage. If the fault cannot be ruled
out, contact Zhiguang.
E101
Downtime
Shut down
Unit input phase loss protection bypass voltage is too high single
Unit input is out of phase. -The voltage of the bypassed unit exceeds the
allowable value of the unit. -The power unit power module is faulty. -Poor
connection between controller and power unit fiber-Power unit control board
failure
Code E106
Action stop
DC voltage protection
Remedy-Check the recorded DC voltage value in the record, determine whether the
voltage is over or under voltage-Check whether the mains voltage is within the
allowable range-Verify the detected DC voltage-If it appears during the
deceleration process, please check whether the deceleration time is set
Reasonable-If the problem cannot be corrected, contact Zhiguang.
E107
Downtime
Take measures to ensure that the ambient temperature is within the required
range. Check the ventilation and cooling system. Check the system load and
operating conditions. If the fault cannot be eliminated, please contact
Zhiguang.
E108
Downtime
Check the output cable for faults-Check the motor windings for faults-if the
fault cannot be ruled out, please contact Zhiguang. -Check the fiber connection
of the corresponding power unit-Check Check the fiber communication circuit of
the controller-Please contact Zhiguang Company. -Check the signal ground of the
control system-Check the fault or alarm event records, check the corresponding
part-Check the controller's optical fiber communication loop-After an unknown
fault occurs, press the "Reset" key when the system is stopped. -Please contact
Zhiguang Company. -Please contact Zhiguang Company. -Please contact Zhiguang
Company.
E109
Downtime
Downstream communication failure unknown failure
E110
Downtime
Fault alarm
SCPU fault signal
When loading and unloading the ZINVERT series high-voltage variable frequency
speed regulation system, a lifting device is required. Pay attention to the
following: ◆ Keep the inverter in vertical position during transportation.
◆ The compressor cabinet must not use the lifting ring on the top of the
frequency conversion speed regulation system. It must be hoisted with a cloth
strap. When unpacking the variable frequency speed control system, the following
steps should be followed:
◆ Carefully remove the packaging materials. Do not use sharp or pointed tools
to remove the packaging box to prevent damage to the system unit cabinet
shell. ◆ Check the status of the ZINVERT series high-voltage variable frequency
speed control system when it arrives, and pay attention to the following:
Doors and side panels deformed Control cables are loose Unassembled spare parts
Are there any damaged parts Intact condition of the dust layer Water or humidity
effects Damage caused by flying insects
◆ Open the door of the inverter and check the internal conditions.
◆ Compare with order list and manufacturer's shipping packing list to prevent
missing parts. If any spare parts are missing, please contact the local
Guangzhou Zhiguang Electric Co., Ltd. sales service company or transportation
company immediately.
124 Storage and its conditions
The following are the minimum requirements for storage. During storage, the
following conditions must be met: Ambient temperature: -5 ° C to 55 ° C
Note: The ZINVERT series high-voltage variable frequency speed control system
needs to be stored for one year, and the following measures must be taken. If
you want to save the inverter speed control system for a longer time, please
contact the technical service department of Guangzhou Zhiguang Electric Co.,
Ltd.
◆ Seal cable inlets and ventilation slots with wooden boards. Add a layer of
impervious plastic or aluminum metal film between the wooden board and the
ventilation slot. ◆ Increase the amount of desiccant: Each unit of desiccant
(30g) absorbs 6g of moisture. Depending on the packaging material you use, you
need the following amount of desiccant:
Polyethylene metal film: 10 units per square meter Aluminum metal film: 8 units
per square meter ◆ Close and lock the system cabinet door.
Polyethylene metal film: 0.3 g / m2 for 24 hours Aluminum metal film: 0.01 g /
m2 for 24 hours
In order to keep the spare parts of the equipment from being damaged during the
warranty period, the following should be noted:
The storage location must be free of vibrations and shocks and protected from
moisture, frost, temperature, dust and grit.
The circuit board must be stored in an antistatic packaging bag with a moisture-
proof agent that will not leak. It must be kept away from corrosive gases that
can cause damage to the circuit board and gases containing saline, alkali or
other impurities. If you find that the maximum allowable humidity of the air
has been exceeded, environmental protection measures such as cooling, heating,
and dehumidification should be used to ensure the environmental conditions of
the spare parts storage.
When removing spare parts from the original packaging, take care to prevent
electrostatic discharge. Improper operation may cause damage to sensitive
components. The following instructions must be followed:
◆ The faulty board should be transported and transferred like the new board to
prevent electrostatic discharge.
When the ZINVERT operation is temporarily stopped, power off, cut off the power
of the variable frequency speed control system and ground it according to the
operation instructions in the previous chapter. Pay attention to safety
instructions and perform safety precautions. When storing the variable frequency
speed control system, please follow the instructions of the previous storage
requirements.
When processing and recycling the equipment in the ZINVERT series of high-
voltage variable frequency speed control systems, the electrolytic capacitors,
printed circuit boards, electronic components and other parts need to be treated
properly so that no part will cause harm to the surrounding environment. The
state's legislation and regulations on environmental protection are implemented.
Chapter 13 Miscellaneous
Quality assurance
The products of Guangzhou Zhiguang Electric Co., Ltd. are in strict accordance
with the GB / T19001-2000 idt ISO9001 2000 quality management system standards
for the entire process quality management of the products. Consistent.
Guangzhou Zhiguang Electric Co., Ltd. will appropriately shorten the free
maintenance period for users who have installed and commissioned the equipment
after half a year of shipment (see the order agreement for details).
Guangzhou Zhiguang Electric Co., Ltd. will provide users with timely and
thoughtful quality and reliable technical support and services for equipment
failures or faults and defects that occur due to users' inability to install
and use equipment in a timely manner.
This Three Guarantees service does not include equipment manufactured by non-
sellers such as power transformers, motors, etc., and equipment and devices
that have not been repaired or modified by Guangzhou Zhiguang Electric Co.,
Ltd., and parts that have been damaged by seals.
◆ The user should provide a stable power supply voltage. The fluctuation range
of the 3kV / 6kV / 10kV power supply voltage should meet the requirements of
the technical conditions. In addition, the user should also provide a three-
phase uninterrupted 380V power supply and an optional 220V DC control power
supply.
◆ Please select the rated capacity of the variable frequency speed control
system according to the nameplate value of the driven motor and the method
introduced in this manual. The selected capacity should be slightly larger than
the required capacity.
◆ Excluding the variable frequency speed control system itself, if the user
has unconventional configuration or special requirements for spare parts options
such as bypass cabinets, it must be reflected in the contract.
◆ If the user needs Guangzhou Zhiguang Electric Co., Ltd. to complete system
integration and related control projects, a separate contract is required.
◆ The user should provide the objects of use of ZINVERT series high-voltage
variable frequency speed control system, such as the technical parameters of
the load of the motor, fan or pump, and the environmental conditions of the
installation site, to Guangzhou Zhiguang Electric Co., Ltd.
◆ Before signing a formal economic contract, the two parties should conduct
careful technical negotiations and sign a technical agreement based on the
characteristics of the use and the environment and the characteristics of the
variable frequency speed control system to ensure that you can complete the
system with the best configuration and price Required technical performance.