You are on page 1of 3

Project Precedence Diagramming Method (PDM) costs. (e.g. Adding more resources.

) Schedule Performance Index (SPI) = EV/PV


Temporary with a beginning & end. Or Activity on Node:
Creates unique product, service or result. 1) Finish-to-Start (Most common) Schedule Baseline: Final schedule Choosing Projects
Progressively elaborated. 2) Start-to-Start Net Present Value (NPV): Choose higher
Program 3) Finish-to-Finish What-If Scenario Analysis Internal Rate of Return (IRR): Choose higher
Group of projects that feed into each other. Monte Carlo Analysis: Computer to simulate Payback Period: Choose lower
Project Management Office (PMO) Arrow Diagramming Method (ADM) or the outcome of a project. Making use of three Benefit Cost Ratio: Choose higher
Provides policies, methodologies & templates. Activity on Arrow: point estimates (Optimistic, Pessimistic, Most
Provides support and guidance. Likely). Opportunity Cost: Cost given up by selecting
Provides project managers. GERT: Diagrams with loops. one project over another.
Milestones: For management. Resource Leveling: Resource limited Sunk Costs: Costs that cannot be recovered to
Triple Constraint (6 constraints) schedule. Move resources around when any significant degree.
Cost, Time, Scope, Risk , Quality & Customer Leads: Activity starts before the end of needed. Law of Diminishing Returns: More you put into
Satisfaction. another. something the less you get out of it.
Lags: Time needed between activities. Milestone Charts Working Capital: Amount of money the
Product Life Cycle Bar Charts company has available to invest.
Conception > Growth > Maturity > Decline > Activity Resource Estimating: Time and Depreciation: Assets that lose value over time.
Withdrawal quantity of resources are determined. Progress Reporting
1) 50/50: 50% if started, 100% if completed. Project Quality Management
5 Project Management Process Groups Activity Duration Estimating: Amount of time 2) 20/80: 20% if started, 100% if completed. Quality Planning (P)
Initiating (I) each activity is to take. 3) 0/100: 0% if started, 100% if completed. Perform Quality Assurance (E)
Planning (P) Perform Quality Control (M)
Executing (E) One time estimate: Based on expert Project Cost Management
Monitoring & Controlling (M) judgment or historical information. Cost Estimation (P) Quality: Degree at which the project fulfills
Closing (C) Cost Budgeting (P) requirements.
Analogous Estimating: Top-down or expert Cost Control (M) Gold Plating: Giving extras.
9 Project Management Knowledge Areas judgment. Prevention over inspection
Project Integration Management Life Cycle Costing: Looking at the life of a Marginal Analysis: Optimal quality is when
Project Scope Management Parametric Estimating: Math model based product, not just the cost of the project. incremental revenue from improvement equals
Project Time Management on historical records. incremental cost to secure it.
Project Cost Management Value Analysis: Finding less costly ways of the Just in Time: Inventory close to zero. Must
Project Quality Management Heuristics: Rule of thumb. doing the same work. have high quality.
Project Human Resource Management Poor Quality: Causes increased costs, low
Project Communications Management Three-Point Estimates: Optimistic (O), Variable Costs: Costs that change with the morale, low customer satisfaction, increased
Project Risk Management Pessimistic (P) and Most Likely (M). amount of production or work. (e.g. materials, risk, rework and delays.
Project Procurement Management supplies, wages.)
PERT Formula = (P + 4M + 0)/6 Cost Benefit Analysis
Project Integration Management Standard Deviation of Activity = (P - O)/6 Fixed Costs: Costs that do not change as the Benchmarking
Develop Project Charter (I) Variance of Activity = [(P – O)/6]2 product changes. (e.g. set up, rental.) Design of Experiments
Develop Preliminary Project Scope Statement (I) Cost of Quality (COQ): Looking at costs of
Develop Project Management Plan (P) Schedules are calendar based while time Indirect Costs: Overhad. (e.g. taxes, benefits) conformance & non-conformance.
Direct/Manage Project Execution (E) estimates are not.
Monitor & Control Project Work (M) Bottom-Up Estimating: Done at the activity Quality Audits
Integrated Change Control (M) Project Estimate: All critical path activities level then rolled up. Process Analysis: Activities/work packages
Close Project (C) added. repeated and checked for better improvement.
Rough Order of Magnitude (ROM): At initiation
Project Scope Management Standard Deviation: All critical path -50 to +100%. Definitive: -5% to +10% (later in Quality Control: Focuses on correctness of
Scope Planning (P) variances added then the square root is the project). work.
Scope Definition (P) taken. Population/Sample: Inspection of 100% of
Create Work Breakdown Structure (P) Cost Budget population will take long, cost too much, be
Scope Verification (M) Total Variance: All critical path variances too destructive.
Scope Control (M) added. Management Reserve Mutual Exclusivity: If two events cannot both
Unforeseen Risks occur in a single trial.
Scope Verification: Check work against PM Plan. Float = Late Start – Early Start Probability: Likelihood that something will
Primary focus is customer acceptance. = Late Finish – Early Finish Cost Baseline occur.
Statistical Independence: The probability of
Work Breakdown Structure (WBS) Duration = Early Finish – Early Start Contingency Reserve one event occurring does not affect the
= Late Finish – Late Start Foreseen Risks probability of another event occurring.
Standard Deviation: Measure of a range
Project 1 Sigma: 68.26%
3 Sigma: 99.73%
Control Account 6 Sigma: 99.99985%

Work Package 7 Basic Tools of Quality


Activities in the Critical Path have a Float = 1. Cause & Effect Diagram (Fishbone,
0. Therefore, ES = LS and EF = LF. Activity Ishikawa): Fix problem & root cause of
WBS Dictionary: Description of work to be done problems.
For each work package. Total Float: Time an activity can be delayed Earned Value Technique 2. Flowchart: Analyze quality problems and
without delaying the project or milestone. Planned Value (PV): Planned cost to date. how they occur.
Project Time Management Earned Value (EV): Cost of work performed to 3. Histogram: Data displayed in bars or
Activity Definition (P) Free Float: Time an activity can be delayed date. columns. (e.g. Pareto Chart)
Activity Sequencing (P) without delaying early start of its successor. Actual Cost (AC): Actual Cost 4. Pareto Chart: Stocking problems into piles.
Activity Resource Estimating (P) Budget at Completion (BAC) Eliminate the larger ones. 80% of problems
Activity Duration Estimating (P) Project Float: Time a project can be delayed Estimate at Completion (EAC) = BAC/CPI = are due to 20% of the root causes.
Schedule Development (P) without delaying required completion date. AC + ETC = AC + BAC – EV 5. Run Chart: Charted progress and look for
Schedule Control (M) Estimate to Completion (ETC) = EAC – AC trends.
Schedule Compression Variance at Completion (VAC) = BAC – EAC 6. Scatter Diagram: Tracks 2 variables to see
Activity Definition: Breaking down work packages 1) Fast Tracking: Doing critical path Cost Variance (CV) = EV – AC if they are related.
Further. activities in parallel. Often results in re-work. Schedule Variance (SV) = EV – PV 7. Control Chart: Monitor production & (cont…)
2) Crashing: Often results in increase. Cost Performance Index (CPI) = EV/AC
other processes to see if they are within - Consultative - Improper Encoding Risk Response Strategies
acceptable limits & if actions are required. - Consensus - Hostility - Avoid: Eliminate threat
- Upper and lower limits - Language - Mitigate: Reduce probability or
- Average Conflict Management: Not bad, depends who - Culture impact
- Out of control needs to solve conflict. - Transfer: Make another party
- Rule of 7 Sources of Conflict: Project Risk Management responsible
- Schedules Risk Management Planning (P)
Project Human Resource Management - Priorities Risk Identification (P) Strategies for Opportunities
Human Resource Planning (P) - Resources Qualitative Risk Analysis (P) - Exploit: Add/change work to make
Aquire Project Team (E) - Technical Opinions Quantitative Risk Analysis (P) sure opportunity occurs
Develop Project Team (E) - Administrative Procedures Risk Response Planning (P) - Enhance: Increase
Manage Project Team (M) - Cost Risk Monitoring & Controlling (M) probability/impact
- Personality - Share: Partner to achieve
Roles & Responsibilities must be clearly Threats: Negative risks. opportunity
defined and communicated. Conflict Reolutions: Opportunities: Positive risks.
- Confronting: Problem Solving For Both
Responsibility Assignment Matrix - Compromising: Lose-Lose Risk Factors: - Accept
- Withdrawal: Avoidance - Probability
- Smoothing: Emphasis on - Impact Outputs
agreement. - Timing Risk Register
P: Primary - Forcing - Frequency - Residual risks
S: Secondary - Response owners
Project Communications Management Risk Averse: One who does not want to take - Triggers
Also known as RACI Chart Communications Planning (P) any risks.
R: Responsible Information Distribution (E) Workarounds: For unplanned responses.
A: Accountable Performance Reporting (M) Risk Tolerance & Thresholds Risk Audits
C: Consulted Manage Stakeholders (M) Tolerance: Acceptable/Unacceptable. Risk Re-Assessment: Revisit & modify plan.
I: Informed Threshold: Amount of risk that is acceptable.
Effective Communications Outputs
Staffing Management Plan: When/how team 55% of communications is non-verbal. Risk Management Planning Outputs - Risk Register Updates
members will be added and released. Plus Paralingual Pitch and tone. - Risk Management Plan Creation of risk templates, checklist, etc.
how to develop them. Feedback: “Do you understand what I said?” - Risk Categories
Resource Histogram: Number of resources o By source Procurement Management
per time period. Communications Technology: Deciding which o By external, internal, Centralized vs. Decentralized Contracting
Recognition & awards motivates. is the best form of communications. technical &
unforeseeable Plan Purchase & Acquisitions (P)
Acquire project team = Acquire FINAL project Communications Methods o By Company’s Plan Contracting (P)
team. Negotiations involved. Formal written: Complex problems, PM Plan, Projects Request Seller Responses (E)
Charter. Select Sellers (E)
Halo Effect: Tendency to rate high or low on Formal verbal: Presentations, speeches. Risk Breakdown Structure (RBS) Contract Administration (M)
all factors due to impression of a high/low Informal written: Memo, Emails, Notes. Contract Closure (C)
rating on a specific factor. Informal verbal: Meetings, conversations. Risk Identification: Involve stakeholders and
team. Happens at Initiation & Planning. Make or Buy Analysis
Team Building: Meetings: Buy: Decrease risk
1) Training - Have time limit Information Gathering Techniques: Make: Idle plant, proprietary information &
2) Ground Rules - Agendas - Brainstorming procedures
3) Co-Location (War Room) - Purpose - Delphi Technique: Consensus of
4) Team Performance Assessment: PM - Have Rules experts. Contracts
evaluates & enhance effectiveness of team. - Interviewing - Cost Reimbursable (CR): Buyer
Communications Channels = (N/(N - 1))/2 - Root Cause Analysis with most risk
Project Performance Appraisals: Team & where N is the number of communicators. - SWOT: Strengths, Weaknesses, o Cost + Fee: Illegal
supervisors provide input (360 view) on the Opportunities & Threats. o Cost + Percentage
project. Lessons Learned o Cost + Fixed Fee
Issue Logs - Technical aspects of project Outputs - Time & Materials (T&M)
- Project Management Risk Register: Document where risk - Fixed Price (FP): Seller with most
Powers of Project Manager: - Management information is kept. risk
- Formal - List of Risks o Fixed Price Incentive
- Reward* Who contributes - Potential Responses Fee
- Penalty - Stakeholders - Root Cause Risks o Fixed Price Economic
- Expert* - Project Management Team - Risk Categories Price Adjustment
- Referent: Someone higher - Team o Purchase Order
referring PM authority. - Project Manager Subjective analysis of riks identified:
*Best form - Customers Probability x Impact (Probability & Impact Contract SOW: Describes what work is to be
Matrix) completed under the contract.
Expectancy Theory: Expected to be rewarded Status Reports: Where the project now stands. Risk Urgency Assessment: Nothing risks that
for efforts. Progress Reports: What has been should more quickly through the process. Types:
Arbitration: 3rd party resolve disputes. accomplished. Watchlist: Non-critical risks. - Performance: Able to accomplish
Perquisites: Special rewards. Trend Report: Examine project results if they - Functional: Characteristics of
Fringe Benefits: Benefits to all employees. are improving or detiorating. Numerical analysis of probability & impact of product
Motivation Theory: Give rewards to motivate. Forecasting Report: Predicting future. highest risks from qualitative risk analysis. - Design: Precisely what work is to
McGregor’s Theory: X – People need to be Variance Report: Compare results to be done
watched. Y – People don’t need supervision. baselines. Risk assessment > Risk identification through
Earned Value: Integrating scope, cost & quantitative risk analysis. Procurement Docs (incl. Evaluation Criteria)
Leardership Styles: schedule measures to assess project Expected Monetary Value: Probability x - Request for Proposal, Invitation
- Directing performance. impact. for Bid, Request for Quote
- Facilitating Monte Carlo Analysis: Simulation of project Non-Disclosure Agreement: All information is
- Coaching Communication Blockers given variables. confidential
- Supporting - Noise Decision Tree: Decisions regarding individual Standard Contracts: Pre-Authorized contracts
- Autocratic - Distance risks. Arbitration: Method to resolve disputes with a
3rd party. Notes:
Breach/Default
Force Majeure: Act of God
Indemnification: Who is liable for injury

Bidder Conferences
Proposal or Bid: Seller’s response
Qualified seller list

Weighting system
Negotiation: Objective is to develop good
relationship.
Tactics: Attacks, insults, good/bad guy,
deadline, lying, limited authority, missing man,
delay

Contract Administration: Assuring both parties


meet contractual requirements.
Contract Manager has authority to change
contract (Contract Change Control System)
Buyer-Conducted Performance Review: To
see if seller is performing.
Claims Administration: Buyer hurt seller and
seller is asking for compensation.
Records Management System
Contract Interpretation: Based on analysis of
the intent of the parties. Contract supersedes
anything prior to contract signing.

All contracts must be closed.


Contract closure before project closure.
Admin closure can be done at the end of each
phase or project. Contract closure done only
once.
Admin closure: Lessons learned
Contract closure: Procurement Audit
- Product verification
- Financial closure
- Update Records
Termination: Buyer terminates if seller
breaches contract or if work is no longer
needed.

Notes by Josefino Sarmiento on A Guide to


the Project Management Body of Knowledge
and Rita Mulcahy’s PMP Exam Prep books.

Notes:

You might also like