Professional Documents
Culture Documents
Rock As The Construction Material For Tunnels: June 2017
Rock As The Construction Material For Tunnels: June 2017
net/publication/322317905
CITATIONS READS
0 123
1 author:
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
Fracture mechanics and rock mechanics applied to tunnels, cliffs, mountain walls and mountains View project
All content following this page was uploaded by Nick Ryland Barton on 08 January 2018.
2. JOINTED ROCK (2a. Arching and over-break, 2b. NMT and over-break
2c. Control of water in NMT and NATM, 2d. Lattice girders, steel sets, RRS
CONCLUSIONS
1. INTACT ROCK
(i.e. massive rock)
TUNNELS IN MASSIVE ROCK: STRESS (or strain?) INDUCED
FAILURE? We traditionally expect ‘stress-induced’ failure when:
σθ max /σc > 0.4 +/- 0.1 …..Maximum tangential stress from: σθ max = 3σ1 - σ3
1.0 1.0
CRACKING IS ACTUALLY CAUSED BY
1.0
Y Axis (m)
Y Axis (m)
X Axis (m) X Axis (m)
0 3.0 0
-1.5 -1.0 -0.5 0 0.5 -3.0 1.0 -2.5 1.5-2.0 2.0-1.5 2.5-1.0 -0.5
3.0 0 0 0.5 1.0 1.5 2.0 2.5
3.0 3.0 3.0
Flow Time (s): 0E+0
ure
-0.5
2.5
Flow Time Step (s): 0E+0
Thermal Time (s): 0E+0
Cycle: 30 of 44
Elastic fracture
-0.5
2.5 STRAIN: -0.5
2.5
-2.0 -2.0
-2.5 -2.5
0.5 0.5
-2.5 0.5
Y Axis (m)
Y Axis (m)
Y Axis (m)
-3.0 -3.0
X Axis (m)
-0.5 -0.5 -0.5
-1.5
-2.0
-1.5
-2.0
σcritical tangential stress ≈ ( 0.4 X UCS) ≈
-1.5
-2.0
σt /ν
-2.5 -2.5 -2.5
-3.0 -3.0
σt /ν ≈
HYDRO-ELECTRIC PROJECT:
ALL (10) TUNNELS (and spillway)
SUFFERED EXTENSION
CRACKING.
INSUFFICIENT UCS IN
RELATION TO DEPTH
(Max. up to 2.5 km)
TANGENTIAL STRESS
CAUSES TOO MUCH
EXTENSION STRAIN:
DYNAMIC SHEARING,
BURSTING.
2a. JOINTING
(arching and over-break)
ILLUSTRATES ‘ARCHING’
STRESSES AND THE
EFFECT OF JOINTS
tic fracture
n fracture 7
ping fracture
ture with Water
6
m Ltd
(HELPS TO DISSIPATE FRACTURING THAT STARTS WITH EXTENSION STRAIN 5
004 11:00:09
7 7
2
6 6
5 1 5
Y Axis (m)
4 4
0
X Axis (m) 3 3
-6 -4 -2 0 2 4 6 2
8 -1
10 2
Tunnel failure mechanisms
1 10 1
-8 -7 -6 -5 -4 -3 -2 -1
X Axis (m)
0 1 2 3 4 5 6 7 8
Y Axis (m)
Y Axis (m)
8 8
0 0
-2 7 7
-1 -1
6 6
-2
-3 8 -2
5 5
-3 -3
4 4
-4 -4
-4
3 3
-5 -5
-6 -5
6 -6
2 2 Tunnel failure mechanisms
X Axis (m)
1 1 -8 -7 -6 -5 -4 -3 -2 -1 0 1 2 3 4 5 6 7 8
-7 -7
8 8
Y Axis (m)
Y Axis (m)
-8 -6 -8 0 0
-8 -7 -6 -5 -4 -3 -2 -1 0 1 2 3 4 5 6 7 8 7 7
4 X Axis (m) -1 -1
6 6
-7 -2 -2
5 5
-3 -3
-8 4 4
-5 -4 -3 -2 -1 0 1 2 3 4 5 6 7 8 2 -4 -4
X Axis (m) 3 3
-5 -5
2 2
Y Axis (m)
-6 -6
1 1
-7 -7
Y Axis (m)
Y Axis (m)
0 0 0
-8 -8
-8 -7 -6 -5 -4 -3 -2 -1 0 1 2 3 4 5 6 7 8
X Axis (m) -1 -1
-2 -2
-2 -3 -3
-5
-4
-5
-4 Shen, 2017) -6 -6
-7 -7
-8 -8
-8 -7 -6 -5 -4 -3 -2 -1 0 1 2 3 4 5 6 7 8
-6 X Axis (m)
INTRODUCTION TO OVER-BREAK – CAUSED BY JOINTING
TWO OF THE
Q-SYSTEM
PARAMETERS
CONTROL
OVER-BREAK
(Ja helps too!)
NOTE TO
CONTRACTORS:
Barton, 2007.
2b.
NMT and over-
break
NMT OPERATIONS: in summary
YES !
APPROPRIATE
SUPPORT
VANDEVALL, 1990
NO !
IN NMT OVER-BREAK HAS
LIMITED IMPACT. DO NOT
HAVE TO FILL WITH
SHOTCRETE or CONCRETE!
(ASG, 2010)
(for Q ≈ 0.004)
(double layer,
6 bars, 45cm
thick arch,
1.7m c/c)
TAKE TIME TO
GET THE LOCAL
HEAVY SUPPORT
APPROPRIATE TO
THE JOB IN HAND
(AVOID COSTLY
COLLAPSE as in
next screens)
Grimstad in Barton
and Grimstad, 2014
3.1 COLLAPSE # 1
A TWIN-MOTORWAY TUNNEL
(with light, inadequate, temporary support, and
anisotropic challenges from an actual rock mass)
OPTIMISTIC SYMMETRIC
DESIGN, WHEN ACTUALLY
SLOPING GROUND.
RAPID PROGRESSION
TOWARDS MASSIVE FAILURE
(3DEC modelling by
Dr. Stavros Bandis)
ROTATED
ROAD,
TREES
AND
TELEGRAPH
POLE (after
140m failure
of second
• Some
tube, some
months later)
ΣFAILURE = 280m
3.2 COLLAPSE # 2
CAVERN ARCH WITH STEEL SETS
(no change of design when encountering
fault zone on ‘left’ side of the arch)
COLLAPSE IN PARTLY
COMPLETED D/S SURGE
CHAMBER ARCH.
NOTE: AR = PR.U
written as:
(Barton, 2000)
Q-VALUE CORRELATES WITH (-) m WHEN Q IS LOWER THAN 1.0.
DOUBLE-SHIELD, PRE-GROUTING, HELP ‘push the hill’ to the left.
WORLD
RECORDS
COLLECTED
IN SIZE
BRACKETS:
(3-6m, 6-10m,
> 10m).
MOSTLY
ROBBINS
WORLD RECORD WORLD
DRILL-AND-BLAST RECORDS)
5.8 km, 54 weeks
Barton, 2013
1. AR = PR x U
(All TBM must follow this).
2. U = Tm
(Reducing utilization with time,
DECELERATION (-m) time T must always be quoted!
3. T = L / AR
m = (-) 0.7 ? Time T for advancing length L.
(Also applies to walking!)
4. T = (L/PR)1/(1+m)
THIS IS (-ve) !!
4. NEED NOT FEAR OVER-BREAK WITH NMT. A BIGGER PROBLEM FOR NATM.