Professional Documents
Culture Documents
To cite this article: Hidde Siemonsma, Wouter Van Nus & Patrick Uyttendaele (2012): Awarding
of Port PPP contracts: the added value of a competitive dialogue procedure, Maritime Policy &
Management: The flagship journal of international shipping and port research, 39:1, 63-78
This article may be used for research, teaching, and private study purposes. Any
substantial or systematic reproduction, redistribution, reselling, loan, sub-licensing,
systematic supply, or distribution in any form to anyone is expressly forbidden.
The publisher does not give any warranty express or implied or make any representation
that the contents will be complete or accurate or up to date. The accuracy of any
instructions, formulae, and drug doses should be independently verified with primary
sources. The publisher shall not be liable for any loss, actions, claims, proceedings,
demand, or costs or damages whatsoever or howsoever caused arising directly or
indirectly in connection with or arising out of the use of this material.
MARIT. POL. MGMT., JANUARY 2012,
VOL. 39, NO. 1, 63–78
1. Introduction
In recent decades, the international port sector has been structurally reformed,
allowing the private sector to enter the market for port and terminal management
and stevedoring operations. The increasingly dominant structure within which ports
are organised nowadays is the so-called landlord model. In this institutional setup, a
Port Authority (PA), which is usually a public body or a corporatised public entity,
is the landlord for various private Terminal Operators (TOs) offering cargo
handling and storage services to shipping lines or cargo owners. In a landlord
environment, private TOs usually lease their terminal from the PA and the
investments and operating activities are allocated amongst both the PA and the TO:
a so-called Port Public–Private Partnership (‘Port PPP’).
The awarding of a Port PPP contract is a highly specific activity as any Port
PPP requires a tailor-made solution in order to fit the specific objectives of the PA,
local circumstances and (supra)national legislation. Usually, this is not considered
Maritime Policy & Management ISSN 0308–8839 print/ISSN 1464–5254 online ß 2012 Taylor & Francis
http://www.tandfonline.com/TMPM
http://dx.doi.org/10.1080/03088839.2011.642314
64 H. Siemonsma et al.
day-to-day business for a PA. This complexity is one of the main reasons why
in the practice of awarding of Port PPP contracts many initiatives are not
successfully implemented. Unsuccessful awarding processes either result in a
suboptimal allocation of responsibilities and risks, significant implementation
delays or even cancellation of the project. In addition, it can become a financial
burden for both PA and private sector candidates, as the Transaction Costs (TCs)
involved are relatively high. Besides this, failed award processes can cause significant
reputational damage to the PA, which can result in decreased credibility for future
attempts to involve the private sector in its port. From the authors’ experience in the
industry, it appears that involving the private sector candidates for a Port PPP at an
early stage in the design and execution of the award process significantly contributes
to the successful awarding of Port PPP contracts.
A wide variety of typologies and definitions for different Port PPP awarding
Downloaded by [Central U Library of Bucharest] at 06:48 09 July 2012
methods are used in the industry. UNCTAD [1], for example, proposed guidelines
for bidding procedures for the privatisation of port facilities. Pallis et al. [2] and
Theys et al. [3] explain direct negotiation, selection from a qualified pool,
competitive bidding and the tender procedure [4]. They define the difference
between a competitive bidding and a tender procedure as follows: in the
competitive bidding procedure, negotiations are held with the preferred bidder
after his appointment, whereas in the tender procedure, all contractual details are
specified in advance. They also provide empirical evidence suggesting that PAs may
prefer competitive bidding, since in this case, the terms of the concession do not
have to be specified in advance. There are several risks, however, when the
detailing of the contract is postponed towards the final negotiation of the contract.
These risks include significant delays and deal creep [5]. This research argues that
the advantages of a tender procedure (optimal transparency and fairness) and the
competitive bidding procedure (flexibility to optimise the contract details) can be
merged into one procedure: the competitive dialogue procedure. In such procedure,
shortlisted candidates are invited by the PA to submit suggestions for improve-
ments to the contract prior to the final submission of proposals and selection of
preferred candidate. Such improvements can relate to the proposed technical
solution or financial arrangements of the deal. The PA then chooses which
improvements are incorporated in the final contract. In recent years, there has been
a growing interest in the potential for integrating a competitive dialogue phase in
the award procedure [6].
This article is aimed at informing port policy and decision makers, PAs and TOs
about the added value of a competitive dialogue procedure in the award of a
Port PPP contract. Therefore, a conceptual framework is developed to assess the
contribution of the competitive dialogue procedure to the value of a Port PPP,
which contributes to the issue of ‘award procedure for concessions’ identified in the
research agenda proposed by Theys et al. [3]. The arguments supporting the
conceptual framework in this research are based on the authors’ experiences and
observations in the industry practice of awarding Port PPPs.
This article provides the definitions and scope of a Port PPP, success measures
and competitive dialogue procedure in Section 2. The conceptual framework applied
in this research to assess the added value of a competitive dialogue procedure in the
awarding of Port PPP contracts is presented in Section 3. The conclusions and
recommendations of this research are presented in Section 4.
Awarding of Port PPP contracts 65
many nations in these regions have reformed their port sectors to facilitate the
involvement of the private sector.
Despite all the variations in private sector participation, the majority of
institutional frameworks in the port sector rely on cooperation of some sort between
a PA and a TO. The holistic term for such ‘cooperation’ is known as a Port PPP.
This cooperation is formally forged between the parties through Port PPP contracts.
In general, a Port PPP contract includes clauses which relate to (1) the allocation of
investment, operational and financing responsibilities and risks amongst both parties
and (2) clauses which protect the investors’ interest (PA and TO) and the public
interest (PA) such as the duration of the contract. A key challenge in structuring a
Port PPP is where to make the cut between public and private responsibilities and
how to protect both parties’ interests.
There is no generic answer to this question. In practice, however, the landlord
model, as described by the World Bank [7], has been widely applied. Although this
model suits many PAs around the world, specific circumstances and objectives make
other allocations of responsibilities and risks more feasible and attractive.
There are many examples of Port PPPs where a different allocation of
responsibility was applied. Two examples presented in Textbox 1 of Port PPP
structures give insight in variations between individual projects.
As illustrated in the Rotterdam and Monrovia examples, the way a Port PPP is
structured largely depends on the specific objectives of the PA and local circum-
stances. The main drivers behind a specific structure include (1) the experience of the
parties and their ability to manage and/or absorb risks, (2) the financial capabilities of
the partners, (3) the market power of the parties, and (4) local legislation. A typical
Port PPP structure as used in this research is visualised in Figure 1.
financial position and the lack of experience of the PA in developing these assets would have
resulted in increased project risk if allocated to this entity. Besides this, in the Monrovia
PPP contract, the general cargo and marine services (pilotage, towage, mooring) have also been
allocated to the TO. Rationale behind this broad concession scope is twofold. First, the
Government of Liberia expressed its ambition to transfer a maximum of investments and
operating activities in one concession to the private sector, therewith reducing the risk of
vanished market appetite for the remaining activities after awarding of the most attractive
activity of container handling. Second, the operational performance of marine services has been
poor for a long time, and if these services would continue to be managed by the PA, it might
have caused a significant risk exposure to the operational performance of the terminal. As the
Monrovia container terminal is the sole container terminal in the country and there are no
decent over-land rail/road connections with neighbouring countries, the TO practically enjoys a
monopolistic position. This position, if not properly addressed in the PPP contract, might be
harmful for the entire economy of Liberia. To protect the national economy, the PPP contract
also includes clauses on the tariff policy (tariffs caps), client base (multi-user terminal) and
service level (for stevedoring and marine services).
State Equity
Debt Debt
Infrastructure (Infrastructure)
Superstructure
Equipment
of future cash flows directly generated by the project for these parties. This method
is commonly applied to project appraisal and to support investment decisions. In the
DCF method, the NPV is determined as per Equation (1).
X
T
CFin CFout
NPV ¼ ð1Þ
t¼0
ð1 þ rÞt
This research takes into account the project cash flows before financing activities
for both the PA and TOseparately. The relevant incoming cash flows (CFin) are
revenues from operations, the relevant outgoing cash flows (CFout) consist of TCs,
investment costs and operational costs. For each party, the internal rate of return
of its relevant cash flows should be compared with the applicable discount rate (r).
The discount rate of the PA represents the financial costs to the PA of the project.
Downloaded by [Central U Library of Bucharest] at 06:48 09 July 2012
The discount rate of the TO represents its weighted average cost of capital, which
is the financial cost of both debt and equity for the TO of the project.
From the DCF method, it follows that the drivers of increased NPV of a project
are (1) increased and/or accelerated revenues, (2) reduced and/or postponed TCs,
operational costs and investment costs, and (3) minimised financing costs. These
value-increasing effects can be achieved by providing effective incentives for the
parties responsible for the different project components. Therefore,
risks should normally be borne by the party best able to assess, control, and manage
them, or by the party with the best access to hedging instruments, the greatest ability
to diversify risks, or the lowest cost of risk-bearing. The aim is to ensure that the party
with the ability to reduce risks has incentives to do so and that the remaining risks are
borne by the party for which it is least costly [9].
Market notification
Pre-qualification of candidates
Contract signature
Market notification
Pre-qualification of candidates
Dialogue phase
number of solutions / candidates can be reduced where
set out in descriptive document
Contract signature
EU Directive 2004/18/EC, recital 31: ‘Contracting authorities which carry out particularly
complex projects may, without this being due to any fault on their part, find it objectively
impossible to define the means of satisfying their needs or of assessing what the market can offer
in the way of technical solutions and/or financial/legal solutions. This situation may arise
in particular with the implementation of important integrated transport infrastructure projects,
large computer networks or projects involving complex and structured financing the financial
and legal make-up of which cannot be defined in advance. To the extent that use of open or
restricted procedures does not allow the award of such contracts, a flexible procedure should be
provided which preserves not only competition between economic operators but also the need
for the contracting authorities to discuss all aspects of the contract with each candidate.
However, this procedure must not be used in such a way as to restrict or distort competition,
particularly by altering any fundamental aspects of the offers, or by imposing substantial new
requirements on the successful tenderer, or by involving any tenderer other than the one selected
Downloaded by [Central U Library of Bucharest] at 06:48 09 July 2012
world, for decisions on the type of award procedure (restricted tender versus
competitive dialogue) for their specific Port PPPs. Especially when a Port PPP is
particularly complex, a competitive dialogue procedure gives way to a more
collaborative approach to defining the optimal deal solution, while adhering to the
key principles of public procurement: transparency, fairness and equality amongst
candidates.
Value’ or ‘TV’). Section 2.1 presented the scope of this research as being the typical
case of a PPP contract between a PA and TO. Therefore, the total TV can be
expressed as the sum of the TV to the ‘PA’ and TO ‘TO’ (Equation (2)).
NPVTV ¼ NPVTV,PA þ NPVTV,TO ð2Þ
Figure 4 conceptually presents the following two categories of cash flows that
together determine the overall TV to the parties (Equation (3)):
(1) Cash flows associated with the work that individuals or organisations have
to put into the project in terms of effort, time and various expenditures
in order to obtain relevant information with which to negotiate contracts,
including the process of bargaining and enforcing them (‘TC’) [15]; and
(2) Cash flows generated from the execution of the Port PPP contract by
project implementation (capital expenditures and financing) and operation
(revenues and operational expenditures) during the term of the contract
(‘Contract Value’ or ‘CV’).
NPVTV ¼ NPVTC þ NPVCV ð3Þ
Cash flow
Time
Combining Equations (2) and (3) result in the TV to the parties as expressed by
Equations (4) and (5).
NPVTV,PA ¼ NPVTC,PA þ NPVCV,PA ð4Þ
NPVTV,TO ¼ NPVTC,TO þ NPVCV,TO ð5Þ
From Equations (4) and (5), it follows that a competitive dialogue procedure
makes a positive contribution to the overall TV when any of the following effects
are realised as a result of including a competitive dialogue phase in the award
procedure:
(1) the NPV of TCs of the PA is lower [16]; and/or
(2) the NPV of TCs of the TO is lower [17]; and/or
(3) the NPV of CV of the PA is higher; and/or
Downloaded by [Central U Library of Bucharest] at 06:48 09 July 2012
3.2.1. Searching and information. The PA may face a lack of information needed
to draft the project information memorandum, request for proposals and PPP
contract (together known as the ‘tender documents’) often as a result of lack of
experience in organising award procedures and/or (over) ambitious objectives for
the project that are difficult to translate into reasonable project requirements in the
tender documents. Dialogue between public and private parties early in the award
procedure facilitates the efficient and effective exchange of information amongst the
parties. Prior to the dialogue phase, candidates are selected to participate in the
award procedure on the basis of their relevant experience. From their experience,
candidates have access to the relevant information required for the parties to discuss
the specifics of the transaction. Hence, despite of the cost of organising a dialogue
phase, the PA and candidates have a platform for efficient and effective exchange of
relevant information, resulting in a net savings in the costs of obtaining information.
Authors’ recent involvement in the awarding of a Port PPP contract where the guiding principles
of the competitive dialogue procedure were applied resulted in significant improvements of the
contract prior to the submission of the final tender documents to the candidates. Key
contractual topics that were addressed and (to a large extent) resolved during the dialogue phase
included: duration of the contact, phasing of investments, performance guarantees, exclusivity
on operations, service rate caps, events of default and early contract termination compensation.
As a result, all candidates were enabled to prepare an optimised bid in a fair and level playing
field. The finalisation of the contract only resulted in a limited number of suggestions for
changes in the contract by the preferred candidate.
Downloaded by [Central U Library of Bucharest] at 06:48 09 July 2012
and possibly resolved, sufficient time is taken to make rational decisions and ideally
all relevant decision makers have ‘buy-in’ for the final solution to the deal.
In addition, the deal structure defined in the contract during the dialogue phase
is likely to have significant buy-in from candidates. Hence, there is no firm ground
for extensive negotiation of the contract after the selection of the preferred
candidate. This argument is supported by the fact that early competitive dialogue
amongst parties constitutes a track record of information and comments on the
contract by the candidates. As there are multiple candidates involved in the dialogue
phase and the PA is allowed to reduce the number of candidates at this stage, the risk
of human opportunistic behaviour is minimised. Candidates demonstrating such
behaviour are easier to identify due to inconsistency with the behaviour of other
candidates.
Early certainty on the outcome and course of the award procedure for candidates
contributes to the credibility, efficiency and effectiveness of the transaction.
Increased commitment of candidates to the transaction can also be achieved by
the PA through demonstrating its capabilities during the dialogue phase and drafting
tender documents that are reasonable and realistic, and in line with the dialogue
results. Textbox 3 provides an empirical example of contract improvements as a
result of a competitive dialogue procedure.
3.2.3. Monitoring and enforcement. Monitoring and enforcement of the Port PPP
contract can become an unnecessarily large administrative burden for both parties
when the contract contains many managerial provision such as monitoring Key
Performance Indicators (‘KPIs’), and enforcing penalty and bonus regimes. TCs can
be reduced by optimising the monitoring and enforcement requirements under the
contract. In practice, however, there is a tendency to overdo monitoring of Port
PPP contracts and focus too much on detailed operational KPIs, whereas the KPIs
should be aligned with the strategic objectives of the PA [19]. A competitive dialogue
procedure can contribute to optimised monitoring and enforcement of the contract
by discussing the actual high-level strategic objectives of the parties and coopera-
tively identifying the most suitable KPIs to safeguard their interests.
In order to take into account the risk of cost savings and overruns as a result of
(1) inefficient award procedures and/or (2) redoing the award procedure due to initial
failure of the procedure, the distribution of possible TCs is assumed to be adequately
represented by a simple triangular risk distribution with a minimum and maximum
Awarding of Port PPP contracts 73
Frequency
transaction cost
Transaction cost distribution in a restricted tender procedure (RTP)
Transaction cost distribution in a competitive dialogue procedure (CDP)
Frequency
possible value, and a most likely value (i.e. the mean). The Expected Value (‘EV’) of
the TC is the average value of the presented distribution.
Figure 5 shows the conceptual visualisation of a case where a Port PPP of low
complexity is awarded in a procedure with or without a competitive dialogue phase.
This conceptual case demonstrates that the risk on TC savings or overruns without
a competitive dialogue phase is relatively small but the EV of the TCs is increased.
As a result, the EV of the TCs increases due to the inclusion of the competitive
dialogue phase.
Figure 6 demonstrates a case where the project has such complexity that the
risk of TC overruns is significantly higher than in the project of low complexity.
The effect of improved risk management of the TCs as a result of the competitive
74 H. Siemonsma et al.
3.3.4. Minimised financing costs. Bankability and financing costs of a Port PPP
contract depend on a wide variety of risks to which the financiers of the parties are
exposed under the project. The lower the risk exposure of a party, the more beneficial
the financing costs to be charged by the financiers, which improves the overall CV
of the deal. Therefore, it is a key value driver of any Port PPP to allocate the risks to
the parties that are most capable of managing a risk (e.g. purchase of suitable
equipment based on experience), transferring a risk (e.g. transfer construction risk to
the building contractor), hedging a risk (e.g. hedge currency exchange risk), insuring
Awarding of Port PPP contracts 75
Frequency
contract value
Transaction cost distribution in a restricted tender procedure (RTP)
Transaction cost distribution in a competitive dialogue procedure (CDP)
Frequency
a risk (e.g. insurable force majeure, political risk insurance) and/or absorbing a risk
that cannot be managed by either party (e.g. non-insurable force majeure). Early
involvement of the parties’ financiers allows for optimal drafting of the contract
from a bankability and financing cost perspective.
The range of outcomes of the CV of the Port PPP is also represented as a
triangular distribution of values. The impact of optimal allocation of project risks
and responsibilities as a result of the efforts of the PA and candidates during the
dialogue phase is reflected by (1) the increased most likely CV under a competitive
dialogue procedure and (2) the reduced spread around the most likely outcome
reflected by a minimum and maximum outcome. Figures 7 and 8 demonstrate that
the positive effects of the dialogue phase are achieved in both low- and high-complex
projects; the impact, however, is likely to be higher in the latter case.
76 H. Siemonsma et al.
PPP transactions for low-complex projects when the increased CV outweighs the
increased TCs.
4.2. Recommendations
On the basis of the analysis and conclusions from this research, the authors advise
port policy and decision makers, and especially PAs, to make a well-considered
choice of the most applicable award procedure for their projects. Especially in the
case of complex projects, a competitive dialogue procedure provides a valuable
approach to ensuring the successful award of Port PPP contracts.
On the basis of this research, additional issues for further research have been
identified:
(1) This research focussed on the added value of a competitive dialogue
Downloaded by [Central U Library of Bucharest] at 06:48 09 July 2012
Acknowledgement
The authors thank Robert Schot for his constructive suggestions for improvements
of this research.
5. Deal creep means the risk that the winner of a competitive award procedure manages to
realise such changes in the conditions and terms of its bid and the contract that it creates
an unfair competitive advantage towards the other candidates participating in the award
procedure.
6. WORLD BANK, 2009, Attracting Investors to African Public-Private Partnerships:
A Project Preparation Guide (Washington, DC: World Bank).
7. WORLD BANK, 2007, The World Bank Port Reform Tool Kit, 2nd ed. (Washington, DC:
World Bank).
8. DUTCH MINISTRY OF TRANSPORT, PUBLIC WORKS, and WATER MANAGEMENT, 2009,
Economische betekenis van Nederlandse zeehavens 2007 (Economic Performance of
Dutch Seaports 2007). Dutch: Dutch Ministry of Transport, Public Works and Water
Management.
9. KERF, M., 1998, Concessions for Infrastructure: A Guide to their Design and Award
(Washington, DC: World Bank).
10. The Directive defines these procedures as follows: ‘ ‘‘Restricted procedures’’ means
Downloaded by [Central U Library of Bucharest] at 06:48 09 July 2012
those procedures in which any economic operator may request to participate but only
those economic operators invited by the contracting authority may submit a
tender. ‘‘Competitive dialogue’’ is a procedure in which any economic operator may
request to participate and the contracting authority conducts a dialogue with the
candidates admitted to that procedure, with the aim of developing one or more suitable
alternatives capable of meeting its requirements, on the basis of which the candidates
chosen are invited to tender’.
11. EUROPEAN COMMISSION, 2004, Directive of the European Parliament and of the Council
of 31 March 2004 on the Coordination of Procedures for the Award of Public Works
Contracts, Public Supply Contracts and Public Service Contracts. 2004/18/EC. Brussels:
European Commission.
12. OFFICE OF GOVERNMENT COMMERCE, 2006, OGC Competitive Dialogue Procedure:
The Competitive Dialogue Procedure in the new Public Contracts Regulations. http://
www.ogc.gov.uk/
13. EUROPEAN COMMISSION, 2007, Communication on a European Ports Policy. COM (2007)
616 Final. Brussels: European Commission.
14. NOTTEBOOM, T., 2008, The Awarding of Seaport Terminals in Europe: Results from
the ITMMA Survey Commissioned by ESPO. Belgium: University of Antwerp, p. 28.
15. WILLIAMSON, O. E., 1985, The Economic Institutions of Capitalism (New York: The
Free Press).
16. The TCs of the PA do include the costs of managing all the candidates during the award
procedure.
17. The TCs of the losing candidates during the award procedure are left out of
consideration in this research as their impact on the CV is assumed to be negligible.
18. Bounded rationality means: (1) imperfect and incomplete information; (2) the complexity
of problems; (3) human information-processing capacity; (4) the time available for the
decision-making process; and (5) the conflicting preferences decision makers have for
organisational goals.
19. PORT STRATEGY, 2009, Key Performance Indicators: Keep it simple, Port Strategy, May,
pp. 20–21.