You are on page 1of 2

18000

500 500 500 500


7000
1500 1500 1500 1500 1500 1500
CARRIAGE WAY

STONE PITCHING

STONE PITCHING
SHOULDER

SHOULDER
SHOULDER

SHOULDER
BERM / UTILITY

BERM / UTILITY
EARTHEN

EARTHEN
PAVED

PAVED
DRAIN

DRAIN
150MM THK. 150MM THK.
PROPOSED CL
ROW LIMIT

ROW LIMIT
GRANULAR MATERIAL GRANULAR MATERIAL

TURFING SELECTED EARTH SELECTED EARTH TURFING

2.5% 2.5%
1.5 1.5
1 1
G.L G.L

LIME GROUTED LIME GROUTED


STONE PITCHING STONE PITCHING

BITUMINOUS CONCRETE - 40mm


DENSE BITUMINOUS MACADAM - 60mm
WET MIX MACADAM - 250mm
GRANULAR SUBBASE - 200mm
SUBGRADE - 500mm

TCS -1 : TWO LANE CARRIAGEWAY WITH PAVED SHOULDER


(Open Country - Plain & Rolling Terrain)

AU106 EXTENSION
ROW 11000 to 15000
VARIES VARIES VARIES (6500 or 7000) VARIES VARIES
1500 1500
(500- (250-1500) CARRIAGE WAY (250-1500) (500-

PAVED STRIP
FOOTHPATH/

PAVED STRIP

FOOTHPATH/
1000) 1000)

SHOULDER/
SHOULDER/
DRAIN

DRAIN
UTILITY

UTILITY
PAVED
PAVED
ROW LIMIT

ROW LIMIT
HAND RAIL PROPOSED CL HAND RAIL

G.L G.L
2.5% 2.5%

BITUMINOUS CONCRETE - 40mm


DENSE BITUMINOUS MACADAM - 60mm
WET MIX MACADAM - 250mm
GRANULAR SUBBASE - 200mm
SUBGRADE - 500mm

TCS-2 : TWO LANE CARRIAGEWAY WITH PAVED SHOULDER (BUILT-UP SECTION)

NOTE:-
1. 1.5m Paved Shoulder/Paved Strip to be Constructed
subject to availability of ROW.
2. Utility Corridor 0.5m to 1.0m subject to availability of ROW.

AU106 EXTENSION