MINOR BRIDGE : 289+890 (1 x 20.

0 PSC I Girder)
Length of Span (Exp. To Exp.) 20 20 Skew angle 0
Deck Width 12.00 No of Deck 2
Carriageway width 9.00 No of Span 1
Foundation Length/Width 12.000 5.50 No of Expansion joint 2
Width of Abutment 12.000 No of Girder 4
Length of Cap 12.000 No of Return Wall 2
Width of Footpath 1.50 Median Wall 2
Length of Return Wall 4.10 Median Width 2.3
Lengrh of Independent Wall 0.00

563.694 FRL
0.22
0.5 0.905
1.2

0.60
561.749
1.1 0.3
0.3
0.5

560.324

3.500 1.00 1 556.824


0.7
0.3 555.824

5.50

S. No Description Unit No Length Width Area Depth Quantity Total Qty.


1 Earthwork Excavation
For Abutment cum 2 12.50 6.00 150.00 4.60 690.00
Median Wall cum 2 2.25 6.70 30.15 2.70 81.41
Independent Wall cum 0 0.20 6.70 0.00 2.70 0.00
771.41 1543
Excavation in Soil 75% 578.55
Excavation in Rock 25% 192.85

2 Annular Filling PCC M-15


For abutment cum 0 12.50 0.50 0.00 0.30 0.00
cum 0 12.50 2.75 0.00 0.70 0.00
0.00

3 PCC Leveling course M-15


For Abutment cum 2 12.20 5.70 139.08 0.10 13.91
Median Wall cum 2 2.25 6.50 29.25 0.10 2.93
Independent Wall cum 0 0.10 6.50 0.00 0.10 0.00
16.83 34

4 RCC M-35 for foundation


For Abutment I step cum 2 12.00 5.50 132.00 0.30 39.60
For Abutment II step cum 2 12.00 3.25 78.00 0.70 54.60
94.20 188
RCC M-25 for foundation
Median Wall cum 2 2.25 4.58 20.59 20.59
Independent Wall cum 0 0.00 4.58 0.00 0.00
20.59 41

5 RCC M-35 for Sub Structure


For Abutment cum 2 12.00 0.75 18.00 4.32 77.85
Pedestal cum 8 0.8 0.80 5.12 0.40 2.05
For Dirt Wall cum 2 12.00 0.3 7.20 1.95 14.00
Gifford India Pvt. Ltd. 1 of 28 MNB289+890 OLD
Bracket cum 2 12.00 0.45 10.80 0.30 3.24
97.14 194
RCC M-25 for Substructure
Median Wall cum 2 2.25 3.53 15.89 15.89
Return Wall cum 2 3.50 0.611 4.28 7.22 30.88
cum 2 0.60 0.45 0.54 0.70 0.38
Independent Wall cum 0 0.00 3.53 0.00 0.00
47.15 94
6 RCC M-35 for CAPs
Cap (Rectangular) cum 2 12.00 1.10 26.40 0.30 7.92
Cap (trapezoidal) cum 2 12.00 0.80 19.20 0.30 5.76
13.680 27

7 RCC Slab M-35 cum 1 20.00 12 240 0.22 52.80


Extra Thickness at edge cum 2 12.00 1.150 27.60 0.18 4.97
57.77 116

8 RCC M-35 for Cross Girder


At End cum 2.0 6.51 0.40 5.208 0.80 4.17
At Mid cum 0.0 8.7 0.30 0 0.80 0
4.17 8

9 Pre Cast PSC M-45 Girder


As per Girder Sheet cum 4 #REF! #REF!
#REF! #REF!

10 HT Steel
For PSC Girder( 45 kg/cum) MT 0.045 #REF! #REF!

11 Steel (TMT Bars) Fe 500 Steel per KG


Superstructure RCC Slab( 150 kg/cum) MT 0.150 8.67 17
RCC cross girder( 150 kg/cum) MT 0.150 0.62 1
PSC Main girder( 100 kg/cum) MT 0.100 #REF! #REF!
Substructure Abut. ( 120 kg/cum) MT 0.120 9.34 19
Pedestal ( 150 kg/cum) MT 0.150 0.31 1
Bracket & Dirt Wall ( 100 kg/cum) MT 0.100 1.72 3
Return/median Wall ( 68 kg/cum) MT 0.068 4.61 9
Abutment cap ( 125 kg/cum) MT 0.125 1.71 3
Foundation ( 100 kg/cum) MT 0.100 9.42 19
Total #REF! #REF!
P=90T HL=35T HT=15T
12 POT-PTFE Bearing Nos Free 8 Fixed 4 Guided 4

13 Strip Seal Expansion Joint Rm 2.0 12.50 25.00 50

14 PCC M-15 Below approach Slab m3 2.0 9.00 3.50 63.00 0.15 9.45 19

Approach slab M-30 Grade including


15 m3 2.0 9.00 3.50 63.00 0.30 18.90 38
Reinforcement

16 Drainage Spouts (100mm dia MS ) Nos. 3.0 3 6

Crash Barrier M-40 including steel (Area 0.35


17
sqm)
Deck m 2.0 20.00 40.00
Approaches m 2.0 7.00 14.00
m total 54.00 108

18 M-25 Grade RCC Railing kerb cum 1.0 27.00 0.4 10.13 0.30 3.04 6

19 RCC Railing Rm 1.0 27.00 27.00 54

20 Weep Hole
For Abutment m 2.0 10 1.0 20 40
For Return Wall m 2.0 2 1.0 4 8

21 Tack Coat for wearing coat sqm 0.0 27.0 9.00 0.00 0.00 0
Gifford India Pvt. Ltd. 2 of 28 MNB289+890 OLD
Wearing Coat 65 mm (40mmThick BC+25mm
22 sqm 1.0 27.00 9.00 243.00 243.00 486
mastic)

22 Painting new letters and figures No 1 1 2

23 Enamel Painting
On Crash Barrier sqm 1 54.00 1 54 54.00 108

24 Stone Pitching
In Front of Abutment cum 2 14.25 2.50 71.25 0.30 21.38
Quadrate Slop cum 2 23.81 47.62 0.30 14.29
Extra Length cum 2 4.00 7.54 60.28 0.30 18.09
53.75 107
25 Filter Material Underneath Pitching
Quadrate Slop cum 2 23.81 47.62 0.15 7.14
Extra Length cum 2 4.00 7.54 60.28 0.15 9.04
16.19 32

26 Back Filling cum 2 17.14 1.95 33.35 2.69 89.70 179

27 Filter Media cum 2 16.10 0.60 19.32 2.69 51.97 104

Gifford India Pvt. Ltd. 3 of 28 MNB289+890 OLD


CHAPTER-6 BOX CULVERT
Description
S.No. Unit 2x2_1 2x2_2 4x3_1 4x3_2 6x4_1 6x4_2 Total Qty SOR Rate Amount

Earth work in excavation of foundation of


structures as per drawing and technical
specification, including setting out, construction of
shoring and bracing, removal of stumps and
other deleterious matter for all leads and lifts,
6.01
dressing of sides and bottom and backfilling with
approved material, etc. complete . Ref. Technical
specification 304. of MORT&H

a) All Types of soils including marshy soil. Cum 463.00 772.00 801.00 835.00 1,088.00 1,134.00 5093.0 180.8 920,559.75
b) Soft/Ordinary Rock Cum 0.0 -
c) Hard Rock ( Blasting Prohibited) Cum 0.0 -
d) Hard Rock ( with controlled Blasting ) Cum 0.0 -
Dismantling of existing structures like bridges,
retaining walls and other structure comprising of
masonry, cement concrete, wood work, steel
work, including T&P and scaffolding wherever
necessary, sorting the dismantled material,
disposal of unserviceable material and stacking
6.02 the serviceable material with all lifts and lead and 0.0 -
/ or salvaging material as per Technical
Specifications clause 202 and section 2800 of
MORT&H .By Mechanical Means for

a) Dismantling of stone masonry Cum 0.0 -


b) Dismantling of plain cement concrete Cum 0.0 -
c) Dismantling of Reinforced cement concrete Cum 0.0 -
d) Scrapping wearing coat Cum 0.0 -
Dismantling of dry boulder apron, flexible apron,
e) stone pitching, including removal of wire crates, Cum 0.0 -
etc.
Dismantling rigid apron of PCC or Boulders
f) embeded in PCC Cum 0.0 -
Dismantling of RCC/ Steel Railing including Road
g Kerbs, Gutters, Pipes, etc. Rmt 0.0 -
h) Dismantling / Removal of Drainage Spouts Nos. 0.0 -
0.0
6.03 Structural steel 0.0 -
a) Boulders/ stones Cum 0.0 -
b) M.S.Pipe Rmt 0.0 -
c) MS/ HYSD steel MT - - - - - - 0.0 76,832.00 -
d) Structural steel MT 0.0 -
Providing & laying plain cement concrete of M15
grade in levelling course below open foundation,
6.04 pile cap, etc. complete as per drawing and Cum 41.00 75.00 60.00 63.00 92.00 97.00 428.0 5,954.00 2,548,312.00
technical specification section 1100, 1500,1700
of MORT&H.

Providing and laying plain cement concrete in


open foundations and substructure of abutment,
pier, wing wall, return wall, retaining wall, toe
wall, median wall and complete curtain wall, etc.
excluding reinforcement complete as per
6.05 0.0 -
drawings and Technical Specifications
Sections1500, 1700, 2100 and 2200 of MORT&H
or as directed by engineer incharge.

a) M-15 Garde Cum 0.0 -


b) M-20 Garde Cum 39.00 94.00 60.00 60.00 86.00 86.00 425.0 6,376.30 2,709,927.50
c) M-25 Garde Cum 0.0 -
d) M-30 Garde Cum 0.0 -
Providing and laying reinforced cement concrete
in open foundations of abutment, pier, box
structure, wing wall, return wall, retaining wall,
median wall and etc. complete excluding
6.06 reinforcement complete as per drawings and 0.0 -
Technical Specifications Sections 1500, 1700
and 2100 of MORT&H or as directed by engineer
incharge.

a) M-20 Garde Cum 61.00 140.00 37.00 44.00 138.00 152.00 572.0 6,656.05 3,807,260.60
b) M-25 Garde Cum 0.0 -
c) M-30 Garde Cum 0.0 -
d) M-35 Garde Cum 0.0 -
e) M-40 Garde Cum 0.0 -
Providing and laying Reinforced Cement
Concrete in substructure of wing walls, return
walls, Piers, Pier caps, Abutments, Abutment
caps, dirt wall, Pedestal, retaining wall & median
wall, etc. excluding reinforcement complete as
6.07 per drawings and Technical Specifications 0.0 -
Sections 1500, 1700 and 2200 of MORT&H or as
directed by engineer incharge.

a) M-20 Garde Cum 54.00 138.00 43.00 52.00 156.00 173.00 616.0 6,656.05 4,100,126.80
b) M-30 Garde Cum 0.0 -
c) M-30 Garde Cum 0.0 -
d) M-35 Garde Cum 0.0 -
e) M-40 Garde Cum 0.0 -
Providing and laying Reinforced Cement
Concrete/Prestressed Cement Concrete in
superstructure of solid slab, Voided Slab, RCC T-
beam, Box Structres, I-girder, Box Girder, etc.
6.08 excluding reinforcement complete as per 0.0 -
drawings and Technical Specifications Sections
1500, 1700 and 2300 of MORT&H or as directed
by engineer incharge.

a) M-25 Grade Cum 72.00 75.00 251.00 262.00 257.00 261.00 1178.0 7,741.90 9,119,958.20
b) M-30 Grade Cum 0.0 -
c) M-35 Grade Cum 0.0 -
d) M-40 Garde Cum 0.0 -
e) M-45 Grade Cum 0.0 -
Supplying, Fitting and Placing un-coated Fe 500
TMT-HYSD bar Reinforcement in Foundation ,
substructure & superstructure complete as per
6.09 Drawing and Technical Specifications. Ref. to 0.0 -
Technical specification 1600 , 2100, 2200 & 2300
of MORT&H

a) Foundation Kg 4,873.00 11,207.00 2,985.00 3,549.00 11,034.00 12,136.00 45784.0 78.00 3,571,152.00
b) Substructure Kg 4,355.00 11,064.00 3,461.00 4,166.00 12,461.00 13,838.00 49345.0 78.00 3,848,910.00
c) Superstructure Kg 7,924.00 8,254.00 27,606.00 28,775.00 28,291.00 28,749.00 129599.0 78.00 10,108,722.00
Filling annular space around footing in rock. Lean
cement concrete of Grade M 15 as per Clause
6.10 No 2104 of Technical Specification of MORT&H. Cum 0.0 -
CHAPTER-6 BOX CULVERT
Description
S.No. Unit 2x2_1 2x2_2 4x3_1 4x3_2 6x4_1 6x4_2 Total Qty SOR Rate Amount

Providing and laying of Filter media with granular


materials/stone crushed aggregates satisfying
the requirements laid down in clause 2504.2.2. of
Technical specifications to a thickness of not less
than 600 mm with smaller size towards the soil
and bigger size towards the wall and provided
over the entire surface behind abutment, wing
wall and return wall to the full height compacted
6.11 to a firm condition complete as per drawing and Cum 81.00 81.00 201.00 201.00 156.00 156.00 876.0 1,247.00 1,092,372.00
Technical Specification.Ref. to 710.1.4 of IRC :78
Technical specification 2500 of MORT&H.

Providing and laying Back filling behind


abutment, wing wall and return wall with selected
imported granular material of approved quality
including compaction, including all leads and lifts
6.12 Cum 66.00 243.00 111.00 163.00 444.00 569.00 1596.0 270.40 431,558.40
complete as per drawing and Technical
Specification Ref. to 710.1.4 of IRC :78 Technical
specification 305 & 2500 .

Providing and fixing Steel void formers painted


with zinc rich paints in voided concrete slabs
including sealing of joints and tie rods of 20 mm
6.13 dia. etc complete as Technical specifications 0.0 -
clause 1700,1800 and 1900.

a) 600 mm dia Rmt 0.0 -


b) 700 mm dia Rmt 0.0 -
c) 800 mm dia Rmt 0.0 -
d) 1000 mm dia Rmt 0.0 -
Providing and fixing Low Relaxation High tensile
steel wires/strands including all accessories for
stressing and stressing and grouting complete
6.14 as per drawing and Technical Specifications MT 0.0 -
1800 of MORT&H and as per Engineer incharge.

Providing and laying plain cement concrete of


M15 Grade leveling course below approach slab
6.15 complete as per drawing and Technical Cum - - - - - - 0.0 5,954.00 -
specification. 2700.

Providing and Laying Reinforced cement


concrete of Grade M-30 in approach slab
including reinforcement and formwork complete
6.16 as per drawing and Technical specification Cum - - - - - - 0.0 7,811.65 -
1500,1600,1700 & 2704 of MORT&H.

Providing and fixing Drainage Spouts complete


6.17 as per drawing and Technical specification 2705 Nos. 4.00 4.00 4.00 4.00 4.00 4.00 24.0 2,023.00 48,552.00
of MORT&H.
Providing reinforced cement concrete crash
barrier in M-40 grade including reinforcement and
6.18 G.I. pipe complete as per drawing and Technical Rmt 8.00 13.00 14.00 14.00 20.00 20.00 89.0 7,951.20 707,656.80
specifications sections 1500, 1600, 1700, 2700 &
clause 809 of MORT&H.

Providing weep holes in Brick masonry/Stone


masonary/ Plain/ Reinforced concrete abutment,
wing wall, return wall, retaining wall, etc. with 100
mm dia AC pipe, extending through the full width
6.19 of the structure with slope of 1V:20H towards Nos. 236.00 356.00 312.00 312.00 284.00 284.00 1784.0 227.00 404,968.00
drawing face. Complete as per drawing and
Technical specification 2706 & 2200.

Providing and laying of asphaltic plug joint to


provide for horizontal movement of 25 mm and
vertical movement of 2 mm, depth of joint varying
from 75 mm to 100 mm, width varying from 500
mm to 750 mm (in traffic direction), covered with
a closure plate of 200mm x 6mm of weldable
structural steel conforming to IS: 2062, asphaltic
6.20 plug to consist of polymer modified bitumen Rmt 0.0 -
binder, carefully selected single size aggregate of
12.5 mm nominal size and a heat resistant foam
caulking/backer rod, all as per approved
drawings and Technical specifications section
2600 of MORT&H.

Supplying, fitting and fixing in position true to line


and level elastomeric bearing conforming to IRC:
83 (Part-II) section IX and clause 2005 of
Technical specifications complete including all
6.21 Cu.cm 0.0 -
accessories as per drawing and Technical
Specifications 2000 of MORT&H.

Supplying, fitting and fixing in position true to line


and level all types of POT-PTFE bearing
consisting of a metal piston supported by a disc
or unreinforced elastomer confined within a metal
cylinder, sealing rings, dust seals, PTFE surface
sliding against stainless steel mating surface,
complete assembly to be of cast steel/fabricated
structural steel, metal and elastomer elements to
6.22 be as per IRC: 83 part-II & III respectively and 0.0 -
other parts conforming to BS: 5400, section 9.1 &
9.2 and clause 2006 of Technical Specifications
complete as per approved drawing and Technical
Specifications 2000 and 2200 of MORT&H.

a) 700 MT capacity Nos. 0.0 -


b) 500 MT capacity Nos. 0.0 -
c) 350 MT capacity Nos. 0.0 -
d) 250 MT capacity Nos. 0.0 -
e) 200 MT capacity Nos. 0.0 -
f) 150 MT capacity Nos. 0.0 -
The Rates of POT bearings shall be same for
capacities 10% above or below of above 0.0 -
mentioned capacities.
Providing and laying Tar paper bearing /Bitumen
paper on abutment as a bearing for receiving
RCC work in superstructure tar paper bearing
6.23 shall be of reinforced bitumen laminated craft Sqm 0.0 -
paper conforming to IS 1398.
CHAPTER-6 BOX CULVERT
Description
S.No. Unit 2x2_1 2x2_2 4x3_1 4x3_2 6x4_1 6x4_2 Total Qty SOR Rate Amount

Providing & fixing filler type expansion joint with


movement up to 20 mm as per IRC SP:67 and
6.24 section 2600 of Technical Specifications of Rmt 20.00 20.00 33.00 33.00 47.00 47.00 200.0 290.00 58,000.00
MORT&H
Providing and fixing of a strip seal expansion joint
catering to maximum horizontal movement upto
70 mm, complete as per approved drawings and
standard specifications to be installed by the
manufacturer/supplier or their authorised
6.25 representative ensuring compliance to the Rmt 0.0 -
manufacturer's instructions for installation. Ref. to
Technical specification 2607 of MORT&H

Providing and laying Stone Pitching with 1:3


cement mortar on slopes laid over already
6.26 prepared filter media laid over quadrant complete Cum 0.0 -
as per drawing and Technical specifications 2504
of MORT&H.
Providing and laying dry Stone Pitching on slopes
laid over already prepared filter media laid over
6.27 quadrant complete as per drawing and Technical Cum 10.00 43.00 12.00 15.00 80.00 84.00 244.0 2,357.56 575,243.56
specifications 2504 of MORT&H.

Providing and laying Filter material underneath


pitching in slopes complete as per drawing and
6.28 Technical Technical specification 2504 of Cum - 9.00 - - 25.00 25.00 59.0 -
MORT&H
Providing & laying 65mm thick wearing course
consisting of 40mm thick asphaltic concrete with
25mm thick mastic asphalt on top including tack
6.29 coats complete as per specifications section Sqm - - - - - - 0.0 282.40 -
2700 of MORT&H

Painting of Structure No., span arrangement, flow


directions etc. as per Technical Specifications
6.30 Section 800 or as directed by Engineer. Nos 1.00 1.00 1.00 1.00 1.00 1.00 6.0 100.00 600.00

Painting two coats after filling the surface with


synthetic enamel paint in all shades on new
6.31 plastered concrete surfacesRef. to Technical Sqm 39.00 94.00 60.00 60.00 86.00 86.00 425.0 82.40 35,020.00
specification 803 of MORT&H.
Construction of flexible apron comprising of loose
stone boulders weighing not less than 40 kg
6.32 including wire crates as per drawing and as per Cum 36.00 36.00 52.00 52.00 59.00 59.00 294.0 1,247.25 366,691.50
Technical clause 2507.2 of MORT&H.

Construction of 450 mm thick Rigid apron


comprising of 300 thk. M15 Grade concrete
embeded with 150 mm flat stone and 150 mm
6.33 thick M15 Grade concrete PCC as per drawing Sqm 13.00 13.00 25.00 25.00 27.00 27.00 130.0 1,786.20 232,206.00
and technical specification Clause 2505 of
MORT&H.

Construction of Toe wall, Curtain wall, abutment,


pier, wing wall, etc. of coursed rubble Stone
6.34 masonry in cement mortar (1:3) complete as per Cum 0.0 -
drawing and Technical specification 1400 &
2507.1 of MORT&H.

RCC Railing

6.35 Rmt 0.0 -

Construction of Bored cast-in situ M-35 grade


RCC piles complete as per drawings & Technical
6.36 Specifications Section 1100 of MORTT&H. 0.0 -
excluding reinforcement in all strata as per
relevant code.

1200 mm dia vertical pile in all types of strata


C other than hard rock Rmt 0.0 -
Providing & laying Reinforced cement concrete
M35 in pile cap excluding reinforcement
complete as per drawings & Technical
6.37 Specifications Clause 1114, Sections 1500 & Cum 0.0 -
1700 of MORT&H or as directed by engineer
incharge.

Carrying out load test on any Pile as per standard


procedure laid down in the IS-2911 specification
including constrcution of test pile ,dismanting the
cap after test & cleaning the site & maintening
6.38 0.0 -
complete records of load as per technical
specification section 1100 of MORT&H

Carrying out initial vertical load test for bored


cast-in-site piles complete as per MORT&H
a) Nos. 0.0 -
specifications section 1100

Carrying out confirmatory boreholes at foundation


locations as shown in drawings or as directed by
Engineer, before commencement of foundation 0.0 -
works as per Technical Specifications Section
2400.

(a) In soil Rm 10.00 10.00 10.00 10.00 10.00 10.00 10.00 70.0 1,200.00 84,000.00
(b) In Soft rock Rm 5.00 5.00 5.00 5.00 5.00 5.00 5.00 35.0 1,800.00 63,000.00
(c) In Hard rock Rm 0.0
Total Amount for bill no. 6 B 44,834,797.11
TOTAL FOR BILL NO. 6 B 4.48
MINOR BRIDGE :292+580 (2 x 20.0 PSC I Girder)
Length of Span (Exp. To Exp.) 20 40 Skew angle 0
Deck Width 12.00 No of Deck 2
Carriageway width 9.00 No of Span 2
Foundation Length/Width 12.00 10.50 No of Expansion joint 3
Width of Abutment 12 No of Girder 8
Length of CapAbut/Pier 12 10 No of Return Wall 2
Width of Footpath 1.50 Median Wall 2
Length of Return Wall 16.10 Median Width 2.25
Lengrh of Independent Wall 9.60
length of pier foundation 10.00
Length of pier shaft 5.50
556.584 FRL
0.22
0.5 0.5
1.2

0.00
554.639 0.25
1.1 0.3 1.7 0.5
0.3
0.5

1.5

544.856

6.500 1.50 2.5 543.556 3.5


1.25 1.2
0.45 541.856 0.3

10.50 10

S. No Description Unit No Length Width Area Depth Quantity Total Qty.


1 Earthwork Excavation
For Abutment cum 2 12.50 11.00 275 3.1 852.5
For Pier cum 1 10.50 10.50 110.25 3.1 341.775
Median Wall cum 2 2.25 10.20 45.9 2.5 114.75
Independent Wall cum 2 9.80 10.20 199.92 2.5 499.8
1808.825 3618
Excavation in Soil 75% 1356.6
Excavation in Rock 25% 452.2

2 Annular Filling PCC M-15


For abutment cum 0 12.50 0.50 0 0.45 0
cum 0 12.50 5.00 0 0.55 0
0

3 PCC Leveling course M-15


For Abutment cum 2 12.20 10.70 261.08 0.1 26.108
For Pier cum 1 10.20 10.20 104.04 0.1 10.404
Median Wall cum 2 2.25 10.00 45 0.1 4.5
Independent Wall cum 2 9.70 10.00 194 0.1 19.4
60.412 121

4 RCC M-35 for foundation


For Abutment I step cum 2 12.00 10.50 252 0.45 113.4
For Abutment II step cum 2 12.00 6 144 1.25 180
ForPier I step cum 1 10.00 10.00 100 0.3 30
ForPier II step cum 1 10.00 6.75 67.5 1.2 81
404.4 809
RCC M-25 for foundation
Median Wall cum 2 2.25 7.26 32.67 32.67
Independent Wall cum 2 9.60 7.26 139.392 139.392
172.062 344
Gifford India Pvt. Ltd. 7 of 28 MNB292+580old
5 RCC M-35 for Sub Structure
For Abutment cum 2 12 1.00 24 10.483 251.592
For pier cum 1 4.00 1.50 6 10.483 62.898
cum 1 1.76625 1.76625 10.483 18.516
Pedestal cum 16 0.8 0.80 10.24 0.40 4.096
For Dirt Wall cum 2 12.00 0.3 7.2 1.945 14.004
Bracket cum 2 12.00 0.45 10.8 0.3 3.240
354.346 709
RCC M-25 for Substructure
Median Wall cum 2 2.25 10.67 48.015 48.015
Return Wall cum 2 6.50 0.933 12.12445 13.653 165.535
cum 2 0.00 0.5 0 0.500 0.000
Independent Wall cum 2 9.60 10.67 204.864 204.864
418.414 837
6 RCC M-35 for CAPs
Abutment Cap (Rectangular) cum 2 12 1.10 26.4 0.3 7.92
Abutment Cap (trapezoidal) cum 2 12 0.80 19.2 0.3 5.760
Pier Cap (Rectangular) cum 1 10 1.70 17 0.25 4.25
Pier Cap (trapezoidal) cum 1 7.75 1.70 13.175 0.5 6.588
24.518 49

7 RCC Slab M-35 cum 1 40.00 12 480 0.22 105.60


Extra Thickness at edge cum 4 12.00 1.150 55.20 0.18 9.94
115.54 231

8 RCC M-35 for Cross Girder


At End cum 4.0 7.125 0.30 8.55 0.80 6.84
At Mid cum 0.0 8.7 0.30 0 0.80 0
6.84 14

9 Pre Cast RCC M-35 Girder


As per Girder Sheet cum 8 #REF! #REF!
#REF! #REF!

10 HT Steel
For PSC Girder( 0 kg/cum) MT 0 #REF! #REF!

11 Steel (TMT Bars) Fe 500 Steel per KG


Superstructure RCC Slab( 150 kg/cum) MT 0.150 17.33 35
RCC cross girder( 150 kg/cum) MT 0.150 1.03 2
RCC Main girder( 175 kg/cum) MT 0.175 #REF! #REF!
Substructure Abut. ( 120 kg/cum) MT 0.120 30.19 60
Substructure Pier. ( 120 kg/cum) MT 0.120 9.77 20
Pedestal ( 150 kg/cum) MT 0.150 0.61 1
Bracket & Dirt Wall ( 150 kg/cum) MT 0.150 2.59 5
Return/median Wall ( 82 kg/cum) MT 0.082 48.42 97
Abutment cap ( 125 kg/cum) MT 0.125 1.71 3
Pier cap ( 175 kg/cum) MT 0.175 1.90 4
Foundation ( 100 kg/cum) MT 0.100 40.44 81
Total #REF! #REF!
V=80T HL=30 HT=15
12 POT-PTFE Bearing Nos Free 16 Fixed 8 Guided 8

13 Strip Seal Expansion Joint Rm 3.0 12.50 37.50 75

14 PCC M-15 Below approach Slab m3 2.0 9.00 3.50 63.00 0.15 9.45 19

Approach slab M-30 Grade including


15 m3 2.0 9.00 3.50 63.00 0.30 18.90 38
Reinforcement

16 Drainage Spouts (100mm dia MS ) Nos. 7.0 7 14

Crash Barrier M-40 including steel (Area 0.35


17
sqm)
Deck m 2.0 40.00 80.00
Approaches m 2.0 7.00 14.00
Gifford India Pvt. Ltd. 8 of 28 MNB292+580old
m total 94.00 188

18 M-25 Grade RCC Railing kerb cum 1.0 47.00 0.4 17.63 0.30 5.29 11

19 RCC Railing Rm 1.0 47.00 47.00 94

20 Weep Hole
For Abutment m 2.0 10 8.0 160 320
For Return Wall m 2.0 14 9.0 252 504

21 Tack Coat for wearing coat sqm 0.0 47.0 9.00 0.00 0.00 0

Wearing Coat 65 mm (40mmThick BC+25mm


22 sqm 1.0 47.00 9.00 423.00 423.00 846
mastic)

22 Painting new letters and figures No 1 1 2

23 Enamel Painting
On Crash Barrier sqm 1 94.00 1 94 94.00 188

24 Stone Pitching
In Front of Abutment cum 2 14.25 2.50 71.25 0.30 21.38
Quadrate Slop cum 2 290.00 580.01 0.30 174.00
Extra Length cum 2 16.00 26.22 839.19 0.30 251.76
447.13 894
25 Filter Material Underneath Pitching
Quadrate Slop cum 2 290.00 580.01 0.15 87.00
Extra Length cum 2 16.00 26.22 839.19 0.15 125.88
212.88 426

26 Back Filling cum 2 29.42 6.77 199.19 11.05 2200.65 4401

27 Filter Media cum 2 28.10 0.60 33.72 11.05 372.54 745

Gifford India Pvt. Ltd. 9 of 28 MNB292+580old


647272887.xlsx

BOX :( 1 X 2 X 2 RCC Box )


No of Opening 1.00
No of Bridge 1.0
Total Structure width 27.50
Height diffrence due to 2.5% slope
0.275
2.50 Bracket Area 0.000
Haunch Area 0.05
0 0.25 Top Slab Area 0.63
0 0.6 0.15 Column Area 1.07
0.15 Bot. Slab Area 0.75
0.45
Clear opening Ht 2.000 Area of the Box Sec. 2.49
Average Ht. 2.1375 shear Key Area 0.360
0.250
Clear Opening width 2.00 2.55 FRL 102.315
EGL 100.000
Min. excation 1.500
PCC thick 0.15

0.000 Carriageway 15.00

0.300 Median Wall 0


length of Median Wall 0
2.50

Crash barrier/ Parapet wall


Nos. 4 Nos.
Length 2.50
Width 0.5
Height 1.60

Depth/ Area/ Cross Total Qty for 1


Sl. No. Item Unit No. Length Breadth Heigth section Area One Box Quantity No's MNB
1 Excavation for foundation

for RCC Box cum 1 28.00 3.00 1.95 163.80


For Wing Wall cum 4 5.59 3.84 0.95 81.57
for Return Wall cum 4 5.00 1.96 1.15 45.08
For Curtain Wall D/S cum 1 6.00 2.65 2.65 42.14
For Curtain Wall U/S cum 1 5.00 2.30 2.15 24.73

For Retaining Wall/ RE/ Abutment cum 4 5.00 4.24 1.25 106.00

Toe Wall cum 0 23.00 2.20 1.10 0.00

463.31 463.00

2 PCC M-15 for Foundation

for RCC Box cum 1 28.10 3.10 0.150 13.07


For Wing Wall cum 4 5.19 3.14 0.150 9.78
for Return Wall cum 4 4.60 1.56 0.150 4.31
For Curtain Wall D/S cum 1 5.60 2.25 0.150 1.89
For Curtain Wall U/S cum 1 5.00 1.90 0.150 1.43

For Retaining Wall/ RE/ Abutment cum 4 4.60 3.84 0.150 10.60

Toe Wall cum 0 22.60 1.80 0.150 0.00

Gifford India Pvt. Ltd. 10 of 28 2x2_1


647272887.xlsx
41.06 41.00

3 RCC M-30 for foundation

For Wing Wall cum 4 4.59 0.85 15.64


for Return Wall cum 4 4.00 0.96 15.36

For Retaining Wall/ RE/ Abutment cum 4 4.00 1.87 29.92

Toe Wall cum 0 22.00 0.54 0.00

60.92 61.00

4 RCC Sub structure

For Wing Wall cum 4 4.59 0.69 12.74


for Return Wall cum 4 4.00 0.48 7.68
For Retaining Wall/ RE/ Abutment cum 4 4.00 2.13 34.02
Toe Wall cum 0 22.00 0.56 0.00

54.44 54.00

5 RCC Box

RCC BOX cum 1 27.50 2.49 68.44


Extra for Shear key cum 4 2.50 0.36 3.60
Deduction for Slab opening cum 0 2.00 2.50 0.25 0.00 0.00

72.04 72.00

6 Steel (HYSD bars)

Foundation Mt 80.0 Kg/cum 60.92 4873.50 4873.00


Sub Structure Mt 80.0 Kg/cum 54.44 4354.98 4355.00
for RCC Box Mt 110.0 Kg/cum 72.04 7924.47 7924.00

12279.45 12279.00

7 PCC M-15 Below approach Slab m3 0 27.50 3.50 0.15 0.00 0.00 0.00

8 Approach slab . M30 m3 0 27.50 3.50 0.30 0.00 0.00 0.00

9 Crash Barrier Rm 4 2.50 0.50 1.60 8.00 8.00

10 Expansion Joint
Filler Type Joint m 2 2.50 2.55 20.20 20.00

11 Tar Paper Bearing sqm 2.0 2.50 0.30 1.50 1.50 2.00

11 Tack Coat sqm 0 2.50 15.00 0.00 0.00 0.00

12 65 mm thik wearing Coat sqm 0 2.50 15.00 0.00 0.00 0.00

13 Weep Holes

for RCC Box Nos. 1 26.00 3 ( Layers) 2 ( sides) 156


For Wing Wall Nos. 4 3.00 4 ( Layers) 1 ( sides) 48
for Return Wall Nos. 4 2.00 1 ( Layers) 1 ( sides) 8
For Curtain Wall D/S Nos.
For Curtain Wall U/S Nos.
For Retaining Wall/ RE/ Abutment Nos. 4 2.00 3 ( Layers) 1 ( sides) 24

Gifford India Pvt. Ltd. 11 of 28 2x2_1


647272887.xlsx
Toe Wall Nos. 0 20.00 2 ( Layers) 1 ( sides) 0

236.00 236.00

14 Drainage Spouts (100mm dia MS ) Nos. 4.0 4.00 4.00

15 Filter medium cum 2.0 31.50 0.60 2.14 37.80 80.80 81.00

Painting Numbering and span


16 arrangement of Culverts No 1 1.00 1.00
Lettering (English & Roman)

17 Painting of Crash Barrier Sqm 4.0 2.50 0.50 1.60 24.20 38.72 39.00

18 Stone Pitching
In Front of Retaining Wall/ RE/
Abutment cum 2 4.00 0.30 4.05 9.72
Quadrate Slop cum 0 10.90 0.30 0.00 0.00
Extra Length cum 0 4.00 5.18 0.30 0.00 0.00

9.72 10.00

Filter Material Underneath


19 Pitching

Quadrate Slop cum 0 Nos. 10.90 0.15 0.00 0.00


Extra Length cum 0 4.00 5.18 0.15 0.00 0.00
0.00 0.00

20 Plain Cement Concrete M-20

Curtain Wall D/S cum 1 5.00 1.90 9.49


Curtain Wall U/S cum 1 4.80 1.65 0.55 7.92 4.36

13.84 14.00

21 Rigid floor apron 450mm thk.


D/S Sqm 1 6.50 4.30 0.45 12.58
U/S Sqm 1 6.50 3.00 0.45 8.78
Deduct soil fill Sqm 4 4.00 4.30 -8.60

12.75 13.00

22 Flexible Apron
D/S cum 1 6.50 4.30 0.75 20.96
U/S cum 1 6.50 3.00 0.75 14.63

35.59 36.00

23 Backfill

Behind Retaining Wall/ RE/ cum 4 4.00 2.34 3.55 66.41


Abutment
Toe Wall cum 0 20.00 0.87 1.50 0.00

66.41 66.00

24 RCC Railling
Deck & Approach m 0 2.50 0.00 0.00
Railing Kerb M-25 cum 0 2.50 0.50 0.30 0.00 0.00 0.00

0.00 0.00

Gifford India Pvt. Ltd. 12 of 28 2x2_1


647272887.xlsx

BOX :( 1 X 2 X 2 RCC Box )


No of Opening 1.00
No of Bridge 1.0
Total Structure width 27.50
Height diffrence due to 2.5% slope
0.275
2.50 Bracket Area 0.000
Haunch Area 0.05
0 0.25 Top Slab Area 0.63
0 0.6 0.15 Column Area 1.07
0.15 Bot. Slab Area 0.88
0.45
Clear opening Ht 2.000 Area of the Box Sec. 2.61
Average Ht. 2.14 shear Key Area 0.316
0.250
Clear Opening width 2.00 2.60 FRL 102.315
EGL 100.000
Min. excation 1.500
PCC thick 0.15

0.000 Carriageway 15.00

0.350 Median Wall 0


length of Median Wall 0
2.50

Crash barrier/ Parapet wall


Nos. 4 Nos.
Length 2.50
Width 0.5
Height 2.60

Depth/ Area/ Cross Total Qty for 1


Sl. No. Item Unit No. Length Breadth Heigth section Area One Box Quantity No's MNB
1 Excavation for foundation

for RCC Box cum 1 28.00 3.00 2.00 168.00


For Wing Wall cum 4 7.12 4.68 0.95 126.62
for Return Wall cum 4 5.00 1.96 1.15 45.08
For Curtain Wall D/S cum 1 6.00 2.65 2.65 42.14
For Curtain Wall U/S cum 1 5.00 2.30 2.15 24.73

For Retaining Wall/ RE/ Abutment cum 8 5.00 5.08 1.25 254.00

Toe Wall cum 2 23.00 2.20 1.10 111.32

771.88 772.00

2 PCC M-15 for Foundation

for RCC Box cum 1 28.10 3.10 0.150 13.07


For Wing Wall cum 4 6.72 3.98 0.150 16.05
for Return Wall cum 4 4.60 1.56 0.150 4.31
For Curtain Wall D/S cum 1 5.60 2.25 0.150 1.89
For Curtain Wall U/S cum 1 5.00 1.90 0.150 1.43

For Retaining Wall/ RE/ Abutment cum 8 4.60 4.68 0.150 25.83

Toe Wall cum 2 22.60 1.80 0.150 12.20

Gifford India Pvt. Ltd. 13 of 28 2x2_2


647272887.xlsx
74.77 75.00

3 RCC M-30 for foundation

For Wing Wall cum 4 6.12 1.10 27.03


for Return Wall cum 4 4.00 0.96 15.36

For Retaining Wall/ RE/ Abutment cum 8 4.00 2.31 73.94

Toe Wall cum 2 22.00 0.54 23.76

140.09 140.00

4 RCC Sub structure

For Wing Wall cum 4 6.12 0.83 20.20


for Return Wall cum 4 4.00 0.48 7.68
For Retaining Wall/ RE/ Abutment cum 8 4.00 2.68 85.68
Toe Wall cum 2 22.00 0.56 24.75

138.31 138.00

5 RCC Box

RCC BOX cum 1 27.50 2.61 71.88


Extra for Shear key cum 4 2.50 0.32 3.16
Deduction for Slab opening cum 0 2.00 2.50 0.25 0.00 0.00

75.04 75.00

6 Steel (HYSD bars)

Foundation Mt 80.0 Kg/cum 140.09 11207.19 11207.00


Sub Structure Mt 80.0 Kg/cum 138.31 11064.48 11064.00
for RCC Box Mt 110.0 Kg/cum 75.04 8254.47 8254.00

19318.95 19319.00

7 PCC M-15 Below approach Slab m3 0 27.50 3.50 0.15 0.00 0.00 0.00

8 Approach slab . M30 m3 0 27.50 3.50 0.30 0.00 0.00 0.00

9 Crash Barrier Rm 4 2.50 0.50 2.60 13.00 13.00

10 Expansion Joint
Filler Type Joint m 2 2.50 2.60 20.40 20.00

11 Tar Paper Bearing sqm 2.0 2.50 0.30 1.50 1.50 2.00

11 Tack Coat sqm 0 2.50 15.00 0.00 0.00 0.00

12 65 mm thik wearing Coat sqm 0 2.50 15.00 0.00 0.00 0.00

13 Weep Holes

for RCC Box Nos. 1 26.00 3 ( Layers) 2 ( sides) 156


For Wing Wall Nos. 4 4.00 4 ( Layers) 1 ( sides) 64
for Return Wall Nos. 4 2.00 1 ( Layers) 1 ( sides) 8
For Curtain Wall D/S Nos.
For Curtain Wall U/S Nos.
For Retaining Wall/ RE/ Abutment Nos. 8 2.00 3 ( Layers) 1 ( sides) 48

Gifford India Pvt. Ltd. 14 of 28 2x2_2


647272887.xlsx
Toe Wall Nos. 2 20.00 2 ( Layers) 1 ( sides) 80

356.00 356.00

14 Drainage Spouts (100mm dia MS ) Nos. 4.0 4.00 4.00

15 Filter medium cum 2.0 31.50 0.60 2.14 37.80 80.80 81.00

Painting Numbering and span


16 arrangement of Culverts No 1 1.00 1.00
Lettering (English & Roman)

17 Painting of Crash Barrier Sqm 4.0 2.50 0.50 2.60 36.20 94.12 94.00

18 Stone Pitching
In Front of Retaining Wall/ RE/
Abutment cum 4 4.00 0.30 5.10 24.48
Quadrate Slop cum 2 10.90 0.30 21.81 6.54
Extra Length cum 2 4.00 5.18 0.30 41.41 12.42

43.45 43.00

Filter Material Underneath


19 Pitching

Quadrate Slop cum 2 Nos. 10.90 0.15 21.81 3.27


Extra Length cum 2 4.00 5.18 0.15 41.41 6.21
9.48 9.00

20 Plain Cement Concrete M-20

Curtain Wall D/S cum 1 5.00 1.90 9.49


Curtain Wall U/S cum 1 4.80 1.65 0.55 7.92 4.36

13.84 14.00

21 Rigid floor apron 450mm thk.


D/S Sqm 1 6.50 4.30 0.45 12.58
U/S Sqm 1 6.50 3.00 0.45 8.78
Deduct soil fill Sqm 4 4.00 4.30 -8.60

12.75 13.00

22 Flexible Apron
D/S cum 1 6.50 4.30 0.75 20.96
U/S cum 1 6.50 3.00 0.75 14.63

35.59 36.00

23 Backfill

Behind Retaining Wall/ RE/ cum 8 4.00 2.94 4.60 216.71


Abutment
Toe Wall cum 2 20.00 0.87 1.50 25.98

242.69 243.00

24 RCC Railling
Deck & Approach m 0 2.50 0.00 0.00
Railing Kerb M-25 cum 0 2.50 0.50 0.30 0.00 0.00 0.00

0.00 0.00

Gifford India Pvt. Ltd. 15 of 28 2x2_2


647272887.xlsx

BOX :( 1 X 4 X 3 RCC Box )


No of Opening 1.00
No of Bridge 1.0
Total Structure width 49.50
Height diffrence due to 2.5% slope
0.275
4.60 Bracket Area 0.000
Haunch Area 0.08
0 0.3 Top Slab Area 1.38
0 0.6 0.2 Column Area 1.88
0.2 Bot. Slab Area 1.61
0.45
Clear opening Ht 3.000 Area of the Box Sec. 4.95
Average Ht. 3.14 shear Key Area 0.316
0.300
Clear Opening width 4.00 3.65 FRL 103.365
EGL 100.000
Min. excation 1.500
PCC thick 0.15

0.000 Carriageway 15.00

0.350 Median Wall 0


length of Median Wall 0
4.60

Crash barrier/ Parapet wall


Nos. 4 Nos.
Length 4.60
Width 0.5
Height 1.50

Depth/ Area/ Cross Total Qty for 1


Sl. No. Item Unit No. Length Breadth Heigth section Area One Box Quantity No's MNB
1 Excavation for foundation

for RCC Box cum 1 50.00 5.10 2.00 510.00


For Wing Wall cum 0 9.00 4.72 0.95 0.00
for Return Wall cum 0 5.00 1.96 1.15 0.00
For Curtain Wall D/S cum 1 13.60 2.65 2.65 95.51
For Curtain Wall U/S cum 1 13.60 2.30 2.15 67.25

For Retaining Wall/ RE/ Abutment cum 4 5.00 5.12 1.25 128.00

Toe Wall cum 0 23.00 2.20 1.10 0.00

800.76 801.00

2 PCC M-15 for Foundation

for RCC Box cum 1 50.10 5.20 0.150 39.08


For Wing Wall cum 0 8.60 4.02 0.150 0.00
for Return Wall cum 0 4.60 1.56 0.150 0.00
For Curtain Wall D/S cum 1 13.20 2.25 0.150 4.46
For Curtain Wall U/S cum 1 13.60 1.90 0.150 3.88

For Retaining Wall/ RE/ Abutment cum 4 4.60 4.72 0.150 13.03

Toe Wall cum 0 22.60 1.80 0.150 0.00

Gifford India Pvt. Ltd. 16 of 28 4x3_1


647272887.xlsx
60.44 60.00

3 RCC M-30 for foundation

For Wing Wall cum 0 8.00 1.12 0.00


for Return Wall cum 0 4.00 0.96 0.00

For Retaining Wall/ RE/ Abutment cum 4 4.00 2.33 37.31

Toe Wall cum 0 22.00 0.54 0.00

37.31 37.00

4 RCC Sub structure

For Wing Wall cum 0 8.00 0.83 0.00


for Return Wall cum 0 4.00 0.48 0.00
For Retaining Wall/ RE/ Abutment cum 4 4.00 2.70 43.26
Toe Wall cum 0 22.00 0.56 0.00

43.26 43.00

5 RCC Box

RCC BOX cum 1 49.50 4.95 245.15


Extra for Shear key cum 4 4.60 0.32 5.82
Deduction for Slab opening cum 0 4.00 4.60 0.3 0.00 0.00

250.97 251.00

6 Steel (HYSD bars)

Foundation Mt 80.0 Kg/cum 37.31 2984.64 2985.00


Sub Structure Mt 80.0 Kg/cum 43.26 3460.80 3461.00
for RCC Box Mt 110.0 Kg/cum 250.97 27606.45 27606.00

31067.25 31067.00

7 PCC M-15 Below approach Slab m3 0 49.50 3.50 0.15 0.00 0.00 0.00

8 Approach slab . M30 m3 0 49.50 3.50 0.30 0.00 0.00 0.00

9 Crash Barrier Rm 4 4.60 0.50 1.50 13.80 14.00

10 Expansion Joint
Filler Type Joint m 2 4.60 3.65 33.00 33.00

11 Tar Paper Bearing sqm 2.0 4.60 0.30 2.76 2.76 3.00

11 Tack Coat sqm 0 4.60 15.00 0.00 0.00 0.00

12 65 mm thik wearing Coat sqm 0 4.60 15.00 0.00 0.00 0.00

13 Weep Holes

for RCC Box Nos. 1 48.00 3 ( Layers) 2 ( sides) 288


For Wing Wall Nos. 0 6.00 4 ( Layers) 1 ( sides) 0
for Return Wall Nos. 0 2.00 1 ( Layers) 1 ( sides) 0
For Curtain Wall D/S Nos.
For Curtain Wall U/S Nos.
For Retaining Wall/ RE/ Abutment Nos. 4 2.00 3 ( Layers) 1 ( sides) 24

Gifford India Pvt. Ltd. 17 of 28 4x3_1


647272887.xlsx
Toe Wall Nos. 0 20.00 2 ( Layers) 1 ( sides) 0

312.00 312.00

14 Drainage Spouts (100mm dia MS ) Nos. 4.0 4.00 4.00

15 Filter medium cum 2.0 53.50 0.60 3.14 64.20 201.43 201.00

Painting Numbering and span


16 arrangement of Culverts No 1 1.00 1.00
Lettering (English & Roman)

17 Painting of Crash Barrier Sqm 4.0 4.60 0.50 1.50 39.80 59.70 60.00

18 Stone Pitching
In Front of Retaining Wall/ RE/
Abutment cum 2 4.00 0.30 5.15 12.36
Quadrate Slop cum 0 23.77 0.30 0.00 0.00
Extra Length cum 0 4.00 7.52 0.30 0.00 0.00

12.36 12.00

Filter Material Underneath


19 Pitching

Quadrate Slop cum 0 Nos. 23.77 0.15 0.00 0.00


Extra Length cum 0 4.00 7.52 0.15 0.00 0.00
0.00 0.00

20 Plain Cement Concrete M-20

Curtain Wall D/S cum 1 12.60 1.90 23.91


Curtain Wall U/S cum 1 13.40 1.65 0.55 22.11 12.16

36.07 36.00

21 Rigid floor apron 450mm thk.


D/S Sqm 1 8.60 3.00 0.45 11.61
U/S Sqm 1 8.60 5.00 0.45 19.35
Deduct soil fill Sqm 4 4.00 3.00 -6.00

24.96 25.00

22 Flexible Apron
D/S cum 1 8.60 3.00 0.75 19.35
U/S cum 1 8.60 5.00 0.75 32.25

51.60 52.00

23 Backfill

Behind Retaining Wall/ RE/ cum 4 4.00 2.97 4.65 110.61


Abutment
Toe Wall cum 0 20.00 0.87 1.50 0.00

110.61 111.00

24 RCC Railling
Deck & Approach m 0 4.60 0.00 0.00
Railing Kerb M-25 cum 0 4.60 0.50 0.30 0.00 0.00 0.00

0.00 0.00

Gifford India Pvt. Ltd. 18 of 28 4x3_1


647272887.xlsx

BOX :( 1 X 4 X 3 RCC Box )


No of Opening 1.00
No of Bridge 1.0
Total Structure width 49.50
Height diffrence due to 2.5% slope
0.275
4.60 Bracket Area 0.000
Haunch Area 0.08
0 0.3 Top Slab Area 1.38
0 0.6 0.2 Column Area 1.88
0.2 Bot. Slab Area 1.84
0.45
Clear opening Ht 3.000 Area of the Box Sec. 5.18
Average Ht. 3.14 shear Key Area 0.275
0.300
Clear Opening width 4.00 3.70 FRL 103.365
EGL 100.000
Min. excation 1.500
PCC thick 0.15

0.000 Carriageway 15.00

0.400 Median Wall 0


length of Median Wall 0
4.60

Crash barrier/ Parapet wall


Nos. 4 Nos.
Length 4.60
Width 0.5
Height 1.50

Depth/ Area/ Cross Total Qty for 1


Sl. No. Item Unit No. Length Breadth Heigth section Area One Box Quantity No's MNB
1 Excavation for foundation

for RCC Box cum 1 50.00 5.10 2.05 522.75


For Wing Wall cum 0 9.00 5.56 0.95 0.00
for Return Wall cum 0 5.00 1.96 1.15 0.00
For Curtain Wall D/S cum 1 13.60 2.65 2.65 95.51
For Curtain Wall U/S cum 1 13.60 2.30 2.15 67.25

For Retaining Wall/ RE/ Abutment cum 4 5.00 5.96 1.25 149.00

Toe Wall cum 0 23.00 2.20 1.10 0.00

834.51 835.00

2 PCC M-15 for Foundation

for RCC Box cum 1 50.10 5.20 0.150 39.08


For Wing Wall cum 0 8.60 4.86 0.150 0.00
for Return Wall cum 0 4.60 1.56 0.150 0.00
For Curtain Wall D/S cum 1 13.20 2.25 0.150 4.46
For Curtain Wall U/S cum 1 13.60 1.90 0.150 3.88

For Retaining Wall/ RE/ Abutment cum 4 4.60 5.56 0.150 15.35

Toe Wall cum 0 22.60 1.80 0.150 0.00

Gifford India Pvt. Ltd. 19 of 28 4x3_2


647272887.xlsx
62.75 63.00

3 RCC M-30 for foundation

For Wing Wall cum 0 8.00 1.37 0.00


for Return Wall cum 0 4.00 0.96 0.00

For Retaining Wall/ RE/ Abutment cum 4 4.00 2.77 44.36

Toe Wall cum 0 22.00 0.54 0.00

44.36 44.00

4 RCC Sub structure

For Wing Wall cum 0 8.00 0.96 0.00


for Return Wall cum 0 4.00 0.48 0.00
For Retaining Wall/ RE/ Abutment cum 4 4.00 3.26 52.08
Toe Wall cum 0 22.00 0.56 0.00

52.08 52.00

5 RCC Box

RCC BOX cum 1 49.50 5.18 256.53


Extra for Shear key cum 4 4.60 0.28 5.06
Deduction for Slab opening cum 0 4.00 4.60 0.3 0.00 0.00

261.59 262.00

6 Steel (HYSD bars)

Foundation Mt 80.0 Kg/cum 44.36 3549.12 3549.00


Sub Structure Mt 80.0 Kg/cum 52.08 4166.40 4166.00
for RCC Box Mt 110.0 Kg/cum 261.59 28775.31 28775.00

32941.71 32942.00

7 PCC M-15 Below approach Slab m3 0 49.50 3.50 0.15 0.00 0.00 0.00

8 Approach slab . M30 m3 0 49.50 3.50 0.30 0.00 0.00 0.00

9 Crash Barrier Rm 4 4.60 0.50 1.50 13.80 14.00

10 Expansion Joint
Filler Type Joint m 2 4.60 3.70 33.20 33.00

11 Tar Paper Bearing sqm 2.0 4.60 0.30 2.76 2.76 3.00

11 Tack Coat sqm 0 4.60 15.00 0.00 0.00 0.00

12 65 mm thik wearing Coat sqm 0 4.60 15.00 0.00 0.00 0.00

13 Weep Holes

for RCC Box Nos. 1 48.00 3 ( Layers) 2 ( sides) 288


For Wing Wall Nos. 0 6.00 4 ( Layers) 1 ( sides) 0
for Return Wall Nos. 0 2.00 1 ( Layers) 1 ( sides) 0
For Curtain Wall D/S Nos.
For Curtain Wall U/S Nos.
For Retaining Wall/ RE/ Abutment Nos. 4 2.00 3 ( Layers) 1 ( sides) 24

Gifford India Pvt. Ltd. 20 of 28 4x3_2


647272887.xlsx
Toe Wall Nos. 0 20.00 2 ( Layers) 1 ( sides) 0

312.00 312.00

14 Drainage Spouts (100mm dia MS ) Nos. 4.0 4.00 4.00

15 Filter medium cum 2.0 53.50 0.60 3.14 64.20 201.43 201.00

Painting Numbering and span


16 arrangement of Culverts No 1 1.00 1.00
Lettering (English & Roman)

17 Painting of Crash Barrier Sqm 4.0 4.60 0.50 1.50 39.80 59.70 60.00

18 Stone Pitching
In Front of Retaining Wall/ RE/
Abutment cum 2 4.00 0.30 6.20 14.88
Quadrate Slop cum 0 23.77 0.30 0.00 0.00
Extra Length cum 0 4.00 7.52 0.30 0.00 0.00

14.88 15.00

Filter Material Underneath


19 Pitching

Quadrate Slop cum 0 Nos. 23.77 0.15 0.00 0.00


Extra Length cum 0 4.00 7.52 0.15 0.00 0.00
0.00 0.00

20 Plain Cement Concrete M-20

Curtain Wall D/S cum 1 12.60 1.90 23.91


Curtain Wall U/S cum 1 13.40 1.65 0.55 22.11 12.16

36.07 36.00

21 Rigid floor apron 450mm thk.


D/S Sqm 1 8.60 3.00 0.45 11.61
U/S Sqm 1 8.60 5.00 0.45 19.35
Deduct soil fill Sqm 4 4.00 3.00 -6.00

24.96 25.00

22 Flexible Apron
D/S cum 1 8.60 3.00 0.75 19.35
U/S cum 1 8.60 5.00 0.75 32.25

51.60 52.00

23 Backfill

Behind Retaining Wall/ RE/ cum 4 4.00 3.58 5.70 163.23


Abutment
Toe Wall cum 0 20.00 0.87 1.50 0.00

163.23 163.00

24 RCC Railling
Deck & Approach m 0 4.60 0.00 0.00
Railing Kerb M-25 cum 0 4.60 0.50 0.30 0.00 0.00 0.00

0.00 0.00

Gifford India Pvt. Ltd. 21 of 28 4x3_2


647272887.xlsx

BOX :( 1 X 6 X 4 RCC Box )


No of Opening 1.00
No of Bridge 1.0
Total Structure width 27.50
Height diffrence due to 2.5% slope0.275
6.80 Bracket Area 0.000
Haunch Area 0.18
0 0.4 Top Slab Area 2.72
0 0.6 0.3 Column Area 3.31
0.3 Bot. Slab Area 2.89
0.45
Clear opening Ht 4.000 Area of the Box Sec. 9.10
Average Ht. 4.14 shear Key Area 0.255
0.400
Clear Opening width 6.00 4.83 FRL 104.465
EGL 100.000
Min. excation 1.500
PCC thick 0.15

0.000 Carriageway 15.00

0.425 Median Wall 0


length of Median Wall 0
6.80

Crash barrier/ Parapet wall


Nos. 4 Nos.
Length 6.80
Width 0.50
Height 1.50

Depth/ Area/ Cross Total Qty for 1


Sl. No. Item Unit No. Length Breadth Heigth section Area One Box Quantity No's MNB
1 Excavation for foundation

for RCC Box cum 1 28.00 7.30 2.08 424.13


For Wing Wall cum 0 9.00 5.66 0.95 0.00
for Return Wall cum 0 5.00 1.96 1.15 0.00
For Curtain Wall D/S cum 1 15.80 2.65 2.65 110.96
For Curtain Wall U/S cum 1 15.80 2.30 2.15 78.13

For Retaining Wall/ RE/ Abutment cum 8 5.00 6.06 1.25 303.00

Toe Wall cum 2 23.00 3.40 1.10 172.04

1088.26 1088.00

2 PCC M-15 for Foundation

for RCC Box cum 1 28.10 7.40 0.150 31.19


For Wing Wall cum 0 8.60 4.96 0.150 0.00
for Return Wall cum 0 4.60 1.56 0.150 0.00
For Curtain Wall D/S cum 1 15.40 2.25 0.150 5.20
For Curtain Wall U/S cum 1 15.80 1.90 0.150 4.50

For Retaining Wall/ RE/ Abutment cum 8 4.60 5.66 0.150 31.24

Toe Wall cum 2 22.60 3.00 0.150 20.34

Gifford India Pvt. Ltd. 22 of 28 6x4_1


647272887.xlsx
92.47 92.00

3 RCC M-30 for foundation

For Wing Wall cum 0 8.00 1.40 0.00


for Return Wall cum 0 4.00 0.96 0.00

For Retaining Wall/ RE/ Abutment cum 8 4.00 2.83 90.41

Toe Wall cum 2 22.00 1.08 47.52

137.93 138.00

4 RCC Sub structure

For Wing Wall cum 0 8.00 0.98 0.00


for Return Wall cum 0 4.00 0.48 0.00
For Retaining Wall/ RE/ Abutment cum 8 4.00 3.32 106.26
Toe Wall cum 2 22.00 1.13 49.50

155.76 156.00

5 RCC Box

RCC BOX cum 1 27.50 9.10 250.25


Extra for Shear key cum 4 6.80 0.26 6.94
Deduction for Slab opening cum 0 6.00 6.80 0.4 0.00 0.00

257.19 257.00

6 Steel (HYSD bars)

Foundation Mt 80.0 Kg/cum 137.93 11034.24 11034.00


Sub Structure Mt 80.0 Kg/cum 155.76 12460.80 12461.00
for RCC Box Mt 110.0 Kg/cum 257.19 28291.40 28291.00

40752.20 40752.00

7 PCC M-15 Below approach Slab m3 0 27.50 3.50 0.15 0.00 0.00 0.00

8 Approach slab . M30 m3 0 27.50 3.50 0.30 0.00 0.00 0.00

9 Crash Barrier Rm 4 6.80 0.50 1.50 20.40 20.00

10 Expansion Joint
Filler Type Joint m 2 6.80 4.83 46.50 47.00

11 Tar Paper Bearing sqm 2.0 6.80 0.30 4.08 4.08 4.00

11 Tack Coat sqm 0 6.80 15.00 0.00 0.00 0.00

12 65 mm thik wearing Coat sqm 0 6.80 15.00 0.00 0.00 0.00

13 Weep Holes

for RCC Box Nos. 1 26.00 3 ( Layers) 2 ( sides) 156


For Wing Wall Nos. 0 6.00 4 ( Layers) 1 ( sides) 0
for Return Wall Nos. 0 2.00 1 ( Layers) 1 ( sides) 0
For Curtain Wall D/S Nos.
For Curtain Wall U/S Nos.
For Retaining Wall/ RE/ Abutment Nos. 8 2.00 3 ( Layers) 1 ( sides) 48

Gifford India Pvt. Ltd. 23 of 28 6x4_1


647272887.xlsx
Toe Wall Nos. 2 20.00 2 ( Layers) 1 ( sides) 80

284.00 284.00

14 Drainage Spouts (100mm dia MS ) Nos. 4.0 4.00 4.00

15 Filter medium cum 2.0 31.50 0.60 4.14 37.80 156.40 156.00

Painting Numbering and span


16 arrangement of Culverts No 1 1.00 1.00
Lettering (English & Roman)

17 Painting of Crash Barrier Sqm 4.0 6.80 0.50 1.50 57.40 86.10 86.00

18 Stone Pitching
In Front of Retaining Wall/ RE/
Abutment cum 4 4.00 0.30 6.33 30.36
Quadrate Slop cum 2 42.06 0.30 84.12 25.24
Extra Length cum 2 4.00 9.98 0.30 79.87 23.96

79.56 80.00

Filter Material Underneath


19 Pitching

Quadrate Slop cum 2 Nos. 42.06 0.15 84.12 12.62


Extra Length cum 2 4.00 9.98 0.15 79.87 11.98
24.60 25.00

20 Plain Cement Concrete M-20

Curtain Wall D/S cum 1 14.80 1.90 28.08


Curtain Wall U/S cum 1 15.60 1.65 0.55 25.74 14.16

42.24 42.00

21 Rigid floor apron 450mm thk.


D/S Sqm 1 10.80 4.30 0.45 20.90
U/S Sqm 1 10.80 3.00 0.45 14.58
Deduct soil fill Sqm 4 4.00 4.30 -8.60

26.88 27.00

22 Flexible Apron
D/S cum 1 10.80 4.30 0.75 34.83
U/S cum 1 10.80 3.00 0.75 24.30

59.13 59.00

23 Backfill

Behind Retaining Wall/ RE/ cum 8 4.00 3.65 5.83 340.34


Abutment
Toe Wall cum 2 20.00 1.73 3.00 103.92

444.27 444.00

24 RCC Railling
Deck & Approach m 0 6.80 0.00 0.00
Railing Kerb M-25 cum 0 6.80 0.50 0.30 0.00 0.00 0.00

0.00 0.00

Gifford India Pvt. Ltd. 24 of 28 6x4_1


647272887.xlsx

BOX :( 1 X 6 X 4 RCC Box )


No of Opening 1.00
No of Bridge 1.0
Total Structure width 27.50
Height diffrence due to 2.5% slope0.275
6.80 Bracket Area 0.000
Haunch Area 0.18
0 0.4 Top Slab Area 2.72
0 0.6 0.3 Column Area 3.31
0.3 Bot. Slab Area 3.06
0.45
Clear opening Ht 4.000 Area of the Box Sec. 9.27
Average Ht. 4.14 shear Key Area 0.236
0.400
Clear Opening width 6.00 4.85 FRL 104.465
EGL 100.000
Min. excation 1.500
PCC thick 0.15

0.000 Carriageway 15.00

0.450 Median Wall 0


length of Median Wall 0
6.80

Crash barrier/ Parapet wall


Nos. 4 Nos.
Length 6.80
Width 0.50
Height 1.50

Depth/ Area/ Cross Total Qty for 1


Sl. No. Item Unit No. Length Breadth Heigth section Area One Box Quantity No's MNB
1 Excavation for foundation

for RCC Box cum 1 28.00 7.30 2.10 429.24


For Wing Wall cum 0 9.00 6.48 0.95 0.00
for Return Wall cum 0 5.00 1.96 1.15 0.00
For Curtain Wall D/S cum 1 15.80 2.65 2.65 110.96
For Curtain Wall U/S cum 1 15.80 2.30 2.15 78.13

For Retaining Wall/ RE/ Abutment cum 8 5.00 6.88 1.25 344.00

Toe Wall cum 2 23.00 3.40 1.10 172.04

1134.37 1134.00

2 PCC M-15 for Foundation

for RCC Box cum 1 28.10 7.40 0.150 31.19


For Wing Wall cum 0 8.60 5.78 0.150 0.00
for Return Wall cum 0 4.60 1.56 0.150 0.00
For Curtain Wall D/S cum 1 15.40 2.25 0.150 5.20
For Curtain Wall U/S cum 1 15.80 1.90 0.150 4.50

For Retaining Wall/ RE/ Abutment cum 8 4.60 6.48 0.150 35.77

Toe Wall cum 2 22.60 3.00 0.150 20.34

Gifford India Pvt. Ltd. 25 of 28 6x4_2


647272887.xlsx
97.00 97.00

3 RCC M-30 for foundation

For Wing Wall cum 0 8.00 1.64 0.00


for Return Wall cum 0 4.00 0.96 0.00

For Retaining Wall/ RE/ Abutment cum 8 4.00 3.26 104.18

Toe Wall cum 2 22.00 1.08 47.52

151.70 152.00

4 RCC Sub structure

For Wing Wall cum 0 8.00 1.11 0.00


for Return Wall cum 0 4.00 0.48 0.00
For Retaining Wall/ RE/ Abutment cum 8 4.00 3.86 123.48
Toe Wall cum 2 22.00 1.13 49.50

172.98 173.00

5 RCC Box

RCC BOX cum 1 27.50 9.27 254.93


Extra for Shear key cum 4 6.80 0.24 6.43
Deduction for Slab opening cum 0 6.00 6.80 0.4 0.00 0.00

261.35 261.00

6 Steel (HYSD bars)

Foundation Mt 80.0 Kg/cum 151.70 12136.32 12136.00


Sub Structure Mt 80.0 Kg/cum 172.98 13838.40 13838.00
for RCC Box Mt 110.0 Kg/cum 261.35 28748.61 28749.00

42587.01 42587.00

7 PCC M-15 Below approach Slab m3 0 27.50 3.50 0.15 0.00 0.00 0.00

8 Approach slab . M30 m3 0 27.50 3.50 0.30 0.00 0.00 0.00

9 Crash Barrier Rm 4 6.80 0.50 1.50 20.40 20.00

10 Expansion Joint
Filler Type Joint m 2 6.80 4.85 46.60 47.00

11 Tar Paper Bearing sqm 2.0 6.80 0.30 4.08 4.08 4.00

11 Tack Coat sqm 0 6.80 15.00 0.00 0.00 0.00

12 65 mm thik wearing Coat sqm 0 6.80 15.00 0.00 0.00 0.00

13 Weep Holes

for RCC Box Nos. 1 26.00 3 ( Layers) 2 ( sides) 156


For Wing Wall Nos. 0 6.00 4 ( Layers) 1 ( sides) 0
for Return Wall Nos. 0 2.00 1 ( Layers) 1 ( sides) 0
For Curtain Wall D/S Nos.
For Curtain Wall U/S Nos.
For Retaining Wall/ RE/ Abutment Nos. 8 2.00 3 ( Layers) 1 ( sides) 48

Gifford India Pvt. Ltd. 26 of 28 6x4_2


647272887.xlsx
Toe Wall Nos. 2 20.00 2 ( Layers) 1 ( sides) 80

284.00 284.00

14 Drainage Spouts (100mm dia MS ) Nos. 4.0 4.00 4.00

15 Filter medium cum 2.0 31.50 0.60 4.14 37.80 156.40 156.00

Painting Numbering and span


16 arrangement of Culverts No 1 1.00 1.00
Lettering (English & Roman)

17 Painting of Crash Barrier Sqm 4.0 6.80 0.50 1.50 57.40 86.10 86.00

18 Stone Pitching
In Front of Retaining Wall/ RE/
Abutment cum 4 4.00 0.30 7.35 35.28
Quadrate Slop cum 2 42.06 0.30 84.12 25.24
Extra Length cum 2 4.00 9.98 0.30 79.87 23.96

84.48 84.00

Filter Material Underneath


19 Pitching

Quadrate Slop cum 2 Nos. 42.06 0.15 84.12 12.62


Extra Length cum 2 4.00 9.98 0.15 79.87 11.98
24.60 25.00

20 Plain Cement Concrete M-20

Curtain Wall D/S cum 1 14.80 1.90 28.08


Curtain Wall U/S cum 1 15.60 1.65 0.55 25.74 14.16

42.24 42.00

21 Rigid floor apron 450mm thk.


D/S Sqm 1 10.80 4.30 0.45 20.90
U/S Sqm 1 10.80 3.00 0.45 14.58
Deduct soil fill Sqm 4 4.00 4.30 -8.60

26.88 27.00

22 Flexible Apron
D/S cum 1 10.80 4.30 0.75 34.83
U/S cum 1 10.80 3.00 0.75 24.30

59.13 59.00

23 Backfill

Behind Retaining Wall/ RE/ cum 8 4.00 4.24 6.85 465.09


Abutment
Toe Wall cum 2 20.00 1.73 3.00 103.92

569.01 569.00

24 RCC Railling
Deck & Approach m 0 6.80 0.00 0.00
Railing Kerb M-25 cum 0 6.80 0.50 0.30 0.00 0.00 0.00

0.00 0.00

Gifford India Pvt. Ltd. 27 of 28 6x4_2


BORE HOLE DEPTH FOR BRIDGES

Depth Per Bore hole Total Depth

Item No. Description of Item Type of foundation Unit Nos Soil Soft rock Hard Rock Soil Soft rock Hard Rock

B Major Bridges
1 187+404 Abut Pile Rm 2 35 70 0 0
Pier Pile Rm 2 35 70 0 0
2 218+460 Abut Pile Rm 2 35 70 0 0
Pier Pile Rm 3 35 105 0 0
Total 315 0 0

315