Professional Documents
Culture Documents
Mrs. Meenakshi
Stay Ahead
Stay Relevant
Stay Connected
What do you infer?
Pro active,
Prevent Loss
Reactive,
Reduced Profits
Stay Ahead
Stay Relevant 2
Stay Connected
What do you infer?
Pro active ,
Prevent Loss
Reactive,
Reduced Profits
Stay Ahead
Stay Relevant 3
Stay Connected
Risk Definition
• Project Risk:
Any possible event that can impact a project (Positive or Negative)
(Positive effect generally called as “Opportunity”).
• Risk Management:
The Art and Science of Identifying, Analyzing and Responding to risk factors
throughout the life of a project and in the best interest of its objectives.
• Risk :
• Which we assumed, but did not anticipate
• Something which we did not see but occurred
• Can arise from internal sources or external sources
• May also happen from some strategic business decision, which has gone
wrong
Stay Ahead
4 Stay Relevant
Stay Connected
Causes of Risk
Changing Technology Govt Regulations Trouble in land acquisition Outbreak in epidemic
Stay Ahead
5 Stay Relevant 5
Stay Connected
Objective of Today’s session
Stay Ahead
6 Stay Relevant
Stay Connected
Enterprise Risk Management Process Flow
Risk
Identification
What can go wrong?
Risk Risk
Monitoring Communication Analysis
and feedback
HowHow
has has
the the
riskrisk What is the likelihood
changed? and impact
and impact of
of risk?
risk?
changed?
Risk
Response
Should it be avoided,
transferred, reduced or Stay Ahead
or accepted?
accepted? Stay Relevant
Stay Connected
What is the difference between Risk & Problem
• A problem statement would be: “We have insufficient resources for installation
& commissioning activities which will delay the project by one week.”
• A risk statement could be: “We may have insufficient resources for installation &
commissioning activities which would delay the project by one week.”
• Problem is a certainty – Something that requires immediate action to solve it
• If a risk is not identified and managed, it can cause a problem.
Stay Ahead
8 Stay Relevant
Stay Connected
Uncertainty to Disaster
Stay Ahead
9 Stay Relevant 9
Stay Connected
Goal of effective Project Risk Management
1, 3- Uncertainties can 4 - A project becomes more
impact Project processes prone to profitability
and outcomes leakage if more unknown
unknowns surface during
execution. Hence goal
High should be to reduce these
uncertainty
1
x 4
unknown unknowns to a
reasonable extent.
RM Focus
Stay Ahead
10 Stay Relevant
Stay Connected
Uncertainty Spectrum
Stay Ahead
11 Stay Relevant
Stay Connected
Terminology
Risk Appetite and Risk Threshold refer to level of Risk an individual or an
organization is willing to accept.
Stay Ahead
13
13 Stay Relevant
Stay Connected
Risk Management Plan
• Approach, tools and data sources that may be used to perform risk
Methodology management on the project
Roles and responsibilities • Defines roles and responsibilities of risk management team
Risk Categories • A structure that indicates all risks typically referred to as Risk Breakdown Structure (RBS)
Probability and impact matrix • Prioritizing risks basis their probability and impact
• Document how risk activities will be recorded for the benefit of the current
Tracking project, as well as for future needs and lessons learnt. How risk
management processes will be audited. Stay Ahead
Stay Relevant
Stay Connected
Risk Identification
Stay Ahead
15
15 Stay Relevant
Stay Connected
Risk Identification Checklist
Stay Ahead
16
16 Stay Relevant
Stay Connected
Risk Register
• A tool to note all risks at one place
• Used to identify potential risks in a project
• Includes all information about each identified risk, such as
- The nature of that risk,
- Level of risk,
- Who owns it and
- What are the mitigation measures in place to respond to it.
• It helps to have a plan in place to respond quickly before risks become problems
Stay Ahead
17 Stay Relevant
Stay Connected
Risk Register
Stay Ahead
Stay Relevant
Stay Connected
Perform Qualitative Analysis
Stay Ahead
19
19 Stay Relevant
Stay Connected
Risk Assessment Matrix
High
High
Likelihood
Medium
Probability
Low
Low
Low Consequences High
Consequences
Stay Ahead
21 Stay Relevant 21
Stay Connected
Risk Profile : Impact (Severity of Consequence)
Stay Ahead
22 Stay Relevant
Stay Connected
Risk Matrix : L&T Template
Probability
A -Most Likely Medium High Critical Critical Critical
1.00>P>0.75
B -Likely
0.75>P>0.50 Medium High High Critical Critical
C -Occasional
0.50>P>0.25 Low Medium High Critical Critical
D -Unlikely
0.25>P>0.10 Low Low Medium High High
E -Remote
0.10>P>0.00 Low Low Low Medium Medium
Severity V IV III II I
Insignificant Minor Significant Major Catastrophic
S<0.25 0.25>S>0.5 0.5<S<1.0 1.0<S<2.0 S>2.0
Stay Ahead
Stay Relevant
Stay Connected
Perform Quantitative Analysis
Stay Ahead
24
24 Stay Relevant
Stay Connected
EMV Analysis ( Expected Monetary Value)
• Statistical Analysis
• Calculates the average outcomes of the scenarios
• Adopts a Risk neutral assumption
• Assessment : Probability X Impact
• Decision Tree
• Opportunities : + ve Value
• Threats : -ve Value
Stay Ahead
25 Stay Relevant
Stay Connected
Decision Tree – Product Decision Example
• To absorb some short-term excess production capacity at it’s Faridabad plant, Special
Instrument Products is considering a short manufacturing run either of two new
products,
- A temperature sensor OR
- A pressure sensor
• Market for each product is known if the products can be successfully developed.
However, there is some chance that it will not be possible to successfully develop them.
• Revenue
- A temperature sensor : Rs. 1.0 Cr
- A pressure sensor : Rs. 40 L
• If developed is unsuccessful for a product then there will be no sales, and the
development cost will be totally lost.
• Development Cost
- A temperature sensor : Rs. 10.0 L
- A pressure sensor : Rs. 1.0 L
Stay Ahead
26 Stay Relevant
Stay Connected
Decision Tree : Product Decision
Development Cost Development Outcome Sales Revenue Net Profit
Success 1,00,00,000
90,00,000
10,00,000
Failure 0
Temperature Sensor -10,00,000
Failure 0
-1,00,000
Neither
0
Stay Ahead
27 Stay Relevant
Stay Connected
EMV : Product Decision
Development Cost Development Outcome Sales Revenue Net Profit
Stay Ahead
31
31 Stay Relevant
Stay Connected
Negative Risks Response Strategies
RISK
Stay Ahead
32 Stay Relevant
Stay Connected
Avoid
• You try to eliminate the risk or its impact.
• Mainly used for critical risks (such as catastrophic events)
• You do this by changing your plan, by changing the project scope, or by changing
the schedule.
• Used when you identify the risk in a very early stage;
• Else it’s difficult to adopt at a later stage as changing scope /schedule is costly
Example
• You observe that during certain periods of your project there is a chance of rain
and you have planned outdoor activities at that time.
• You move these activities to a few days later to avoid the impact of rain.
Stay Ahead
33 Stay Relevant
Stay Connected
Mitigate
• You will try to lessen the impact of the risk.
• Also decreases the severity of the risk.
• You do so by either by decreasing the probability of the risk happening or the
effect of the risk
Example
• Installation of sprinkler system in a building.
• Sprinklers cannot prevent fire but are aimed at reducing loss caused by fire
should one break out.
• You mitigate the risk this way.
Stay Ahead
34 Stay Relevant
Stay Connected
Transfer
• Used when you lack skills or resources to manage the risk
• You transfer the risk to a third party to manage it.
• Transferring does not eliminate the risk; it only shifts the responsibility of
managing the risk to the third party.
Example
• There is a task to install some equipment, and you do not have expertise in
this task.
• The task is complex, and few contractors have successfully installed it
before.
• Therefore, you sub contract this activity to the Contractor.
• Thus, you have transferred the responsibility of the whole task to a third
party
Stay Ahead
35 Stay Relevant
Stay Connected
Accept
• You take no action to manage the risk except acknowledging it.
• You use this strategy when the risk is not critical.
• If it is not possible or practical to respond to the risk through the other
strategies, or
• You can accept the risk acknowledging it actively or passively.
- Active : By keeping provision of contingency amount
- Passive : By just noting in risk register
Example
• You are digging to construct a building, and there is ac chance that you may find
artifacts, though probability is low.
• So you note it down and take no action. A response plan may cost you a lot with
no guarantee of finding an object of interest.
Stay Ahead
36 Stay Relevant
Stay Connected
Other Risks
• Secondary Risks
- It is the type of risk which
occurs due to effect of risk
treatment.
- E.g. You put of fire using water.
But used so much of water that
now surface becomes slippery
and pose hazard.
• Residual Risks
- It is a portion of a risk that is
“left after a risk treatment”
- E.g. You put of the fire, but still
hot surface remains. You have
to wait till it cools down.
Stay Ahead
37 Stay Relevant
Stay Connected
Enhance
• You try to increase the chance of a opportunity happening to get benefits out of
this opportunity.
• This response strategy is opposite of the mitigation risk response strategy.
Example
• Let us say your project will be completed in three months.
• You find out that the government is about to float a similar type of project in two
months.
• Therefore, you can bid for a new project if you can complete your project in two
months.
• You try to compress the schedule so that the project can be completed ahead of
time and enhance your chance to bid for the new project
Stay Ahead
38 Stay Relevant
Stay Connected
Exploit
• Exploiting is about doing everything to ensure that the event happens.
• You make sure you realize the opportunity.
• You take the opportunity seriously and develop a strategy to realize it.
Example
• Suppose you are constructing a building, and suddenly the client tells you that if
you complete the project two months before the actual completion date, he will
give you a financial incentive.
• This is an opportunity for you
• You exploit this opportunity to complete the project ahead of time.
• You give overtime to your team members, bring in more employees, motivate the
team members by announcing rewards if they help you complete the project
ahead of time, etc
Stay Ahead
39 Stay Relevant
Stay Connected
Enhance Vs Exploit
Enhance Exploit
You try to realize the opportunity You ensure that you will realize the
opportunity.
You increase probability by certain You increase the probability to 100%
percentage
Opposite of the mitigation risk response Opposite of the avoid risk response strategy.
Takes the situation leniently Takes it aggressively
Stay Ahead
40 Stay Relevant
Stay Connected
Share
• When you are not capable of realizing the opportunity on your own.
• You team up with another company and work together to realize the
opportunity.
Example
• Suppose that due to the lack of a specific technical capability, you are not able to
bid for a project, but your company wants to get this project.
• You team up with another company that is capable of doing this task and jointly
bid for the project.
• You share the opportunity here since you are sharing profits with other company
Stay Ahead
41 Stay Relevant
Stay Connected
Accept / Ignore
• You take no action to realize the opportunity
• You leave the opportunity as is, and if it happens on its own, you will benefit
from it.
• When the cost of the response is high, and there is less of a chance of it
occurring or the benefit does not outweigh the effort involved.
Example
• Suppose you need skilled resources in your project
• And you understand some other project has such resources available for you but
at a higher cost
• You don’t pursue this opportunity, accept the situation and decide to manage till
possible
Stay Ahead
42 Stay Relevant
Stay Connected
Risk Response Strategies
Stay Ahead
43 Stay Relevant
Stay Connected
Exercise
Figure out which risk response technique is being used in these situations
Stay Ahead
44 Stay Relevant
Stay Connected
Implement Risk Response
Stay Ahead
45
45 Stay Relevant
Stay Connected
Implement Risk Response
List Critical
Avoid
Risks
Identify
Create a
Accept Residual
watch list
Risks
List
Non-Critical
Risks
Stay Ahead
46 Stay Relevant
Stay Connected
Monitor & Control Risks
Stay Ahead
47
47 Stay Relevant
Stay Connected
Risk Matrix and Tolerance Bandwidths
Probability
A -Most Likely
1.00>P>0.75
B -Likely
0.75>P>0.50 High
X
C -Occasional
X = Pre-Mitigation Risk
Likelihood
0.50>P>0.25
Y = Risk w/Mitigation
D -Unlikely
0.25>P>0.10
= Current Status
E -Remote Y
0.10>P>0.00
Low
Severity V IV III II I
Insignificant Minor Significant Major Catastrophic
S<0.25 0.25>S>0.5 0.5<S<1.0 1.0<S<2.0 S>2.0
Consequence/Impact
Stay Ahead
Stay Relevant
Stay Connected
Question 1
If an un-identified risk occurs:
Stay Ahead
50 Stay Relevant
Stay Connected
Question 1
If an un-identified risk occurs:
Stay Ahead
51 Stay Relevant
Stay Connected
Question 2
The Project Manager and the team have just completed determining what will be
done if risk events happen and who will be responsible for executing those
actions. Which of the following roles will be responsible for acting if the risk
events happen?:
A. Customer
B. Discipline Lead
C. Project Manager
D. Risk Owner
Stay Ahead
52 Stay Relevant
Stay Connected
Question 2
The Project Manager and the team have just completed determining what will be
done if risk events happen and who will be responsible for executing those
actions. Which of the following roles will be responsible for acting if the risk
events happen?:
A. Customer
B. Discipline Lead
C. Project Manager
D. Risk Owner
Stay Ahead
53 Stay Relevant
Stay Connected
Question 3
You have identified a large number of risks during your risk identification
process. What will be your next step?
A. You will prioritize them using the Qualitative Risk Analysis process
B. Go for the Quantitative Risk Analysis
C. Assign the risk owner to each risk
D. Calculate the contingency reserve
Stay Ahead
54 Stay Relevant
Stay Connected
Question 3
You have identified a large number of risks during your risk identification
process. What will be your next step?
A. You will prioritize them using the Qualitative Risk Analysis process
B. Go for the Quantitative Risk Analysis
C. Assign the risk owner to each risk
D. Calculate the contingency reserve
Stay Ahead
55 Stay Relevant
Stay Connected
Question 4
In risk management, you have many strategies to manage risks. Which strategy
will you not use with the negative risks?
A. Mitigate
B. Exploit
C. Transfer
D. Avoid
Stay Ahead
56 Stay Relevant
Stay Connected
Question 4
In risk management, you have many strategies to manage risks. Which strategy
will you not use with the negative risks?
A. Mitigate
B. Exploit
C. Transfer
D. Avoid
Stay Ahead
57 Stay Relevant
Stay Connected
Question 5
A risk is a bad event that will adversely impact the project. This statement is:
A. Always true
B. Always false
C. Sometimes true
D. None of the above
Stay Ahead
58 Stay Relevant
Stay Connected
Question 5
A risk is a bad event that will adversely impact the project. This statement is:
A. Always true
B. Always false
C. Sometimes true
D. None of the above
Stay Ahead
59 Stay Relevant
Stay Connected
For the queries, please contact
madura.meenakshi@lntipm.org
Stay Ahead
60 Stay Relevant
Stay Connected
Stay Ahead
61 Stay Relevant
Stay Connected