Professional Documents
Culture Documents
The utility electricity sector in Bangladesh has one national grid with an
installed capacity of 21,419 MW as of September 2019. The total installed
capacity is 20,000 MW (combining solar power). Bangladesh's energy
sector is booming. Recently Bangladesh started construction of the 2.4-
gigawatt. Rooppur Nuclear Plant expected to go into operation in
2023.[2] According to the Bangladesh Power Development Board in July
2018, 90 percent of the population had access to electricity. However
per capita energy consumption in Bangladesh is considered low.[3]
Electricity is the major source of power for most of the country's economic
activities. Bangladesh's total installed electricity generation capacity
(including captive power) was 15,351 megawatts (MW) as of January
2017[4] and 20,000 megawatts in 2018.[5]
The largest energy consumers in Bangladesh are industries and the
residential sector, followed by the commercial and agricultural sectors. [6]
As of 2015, 92% of the urban population and 67% of the rural population
had access to electricity. An average of 77.9% of the population had
access to electricity in Bangladesh.[7] Bangladesh will need an estimated
34,000 MW of power by 2030 to sustain its economic growth of over 7
percent.[8]
Problems in Bangladesh's electric power sector include high system
losses, delays in completion of new plants, low plant efficiency, erratic
power supply, electricity theft, blackouts, and shortages of funds for power
plant maintenance. Overall, the country's generation plants have been
unable to meet system demand over the past decade.
On 2 November 2014, electricity was restored after a day-long nationwide
blackout. A transmission line from India had failed, which "led to a cascade
of failures throughout the national power grid," and criticism of "old grid
infrastructure and poor management." However, in a recent root-cause
analysis report the investigating team has clarified that the fault was
actually due to lack of coordination and poor health of transmission and
distribution infrastructure that caused the blackout. [9][10] According to the
Bangladesh's Power Sector Master Plan 2016 (PSMP–2016), the country
has the potential to generate a combined 3.6 GW of electricity from
renewable energy sources.[15] Another research has estimated that the
potential from wind power alone stands at 20 GW.[15]
Bangladesh has 15 MW solar energy capacity through rural households
and 1.9 MW wind power in Kutubdia and Feni.[16] The government of
Bangladesh has approved the construction by private developers of 19 on-
grid solar parks, with would have cumulative generation capacity of 1070
MW.[17]A solar power plant having a power generation capacity of 28 MW
has recently started its operation in Teknaf of Cox's Bazar. Accounting this,
the power generation capacity from renewable energy sources exceeds
five percent of the country's total demand. Technical Solartech Energy Ltd
(TSEL) has installed this power plant in Teknaf utilizing a total of 116 acres
of land. Currently, the power plant is feeding 20MW to the national grid. [18]
Bangladesh has planned to produce 10% of total power generation by 2020
from renewable energy sources like wind, waste, and solar energy. The
country plans to increase its renewable energy share to 17% by 2041
under its Intended Nationally Determined Contribution (INDC) commitment
to reduce greenhouse gas emissions by 5% until 2030. [6]
The country's prospect of geothermal energy extraction has also been
discussed by researchers.[19] Studies carried out by geologists suggested
geothermal resources in northwest and southeast region. [20][21]
Waste Disposal
There are arguments in favor of nuclear energy when compared to the use
of coal.[dubious – discuss] For example, a single 1000 MW coal-fired plant
produces over 300,000 tons of ash, 44,000 tons of sulphur dioxide, 22,000
tons of Nitrous Oxide and 6 million tons of carbon. In contrast, a 1000 MW
of nuclear power plant produces 3 cubic meters of waste after reprocessing
the spent fuel, 300 tons of radioactive waste and 0.20 tons of plutonium.
However, a unit ton of nuclear waste is far more dangerous than the same
amount of coal-fired plant waste, if not managed properly. At the same
time, dealing with nuclear wastes is more expensive.[8]
Nuclear waste disposal will be managed by Radioactive Waste
Management Company, to be formed according to Bangladesh
government’s National Policy on Radioactive Waste and Spent Nuclear
Fuel Management-2019.[9] Bangladesh plans to store nuclear waste for a
given period, after which the waste will be brought to Russia.[9] Spent fuel
may be reprocessed in Russia for fast breeder reactors.[10]
According to the 4th IPCC, climate change in the region of the project area
could cause exacerbate significant river erosion, deposition and flooding
which would be of concern.[8] River erosion is a significant hazard along all
of Bangladesh's rivers which destroys land and critical infrastructure
continually, rendering thousands homeless and displaced every year. The
site area immediately downstream from the Indian border is in addition
vulnerable to unilateral bank protection construction.
Conclusion
Energy planning of a developing country such as
Bangladesh is a great challenge if a target is set to ensure
sustainable development. Being low the present energy
consumption of Bangladesh, the road map of its development
is affected greatly. Since the gap between demand and
generation for electricity is increasing day by day, there is no
alternative way to meet the power crisis without nuclear
power. If Bangladesh is to get out of the chronic power
shortage problem and look for energy security, entry into a
long term nuclear power program should not be delayed
anymore and decision has to be made by Bangladesh not by
other countries. Safety and safeguards issues can be dealt
with by BAEC and IAEA
References