1 Excv Extrac Kurang Lebih
1 Excv Extrac Kurang Lebih
----------------------------------------
- SAP :19-0342
- Estate : Pelalawan
*- Plan Activity :*
*- Actual :*
Felling(5.8ha).
Bunching(5.2ha).
Extraction(4.8ha).
2. SA compt J.029
PICA :
Problem-Identification
Corrective-Action:
Terima kasih
Daily Report Progress Harvesting
Tgl: 07/08/2019
PT : SMGG TPK 16
**************
A. Resources
*1.Comp. J.033*
Size : 25 ha
Status : Felling/Bunching
Felling :3/25/22
Prebunch :1.5/25/23.5
Extract :0/28.5/25
Spreading:0/25/25
*2.Comp. J.030*
Size : 23 ha
Status : SA
Felling :23/23/0
Prebunch :23/23/0
Extract :23/23/0
Spreading:23/23/0
*3.Compt. J.029*
Luas : 24.6 ha
Status :Spreading
-Felling :24.6/24.6/0
-Prebunch :24.6/24.6/0
-Extraction:24.6/24.6/0
-Spreading:9/24.6/15.6
*4.Comp. J031*
Size. : 28.8 Ha
Status : Felling/Prebunch/Extract
Felling :12.8/28.8/16
Prebunch :9/28.8/19.8
Extract :7.8/28.8/21
Spreading:0/28.8/28.8
***************