Technical Paper

What successful Cost Estimators know. . . . and you should, too.

>>>>>>> AN ESTIMATOR’S GUIDE TO POLICIES,


>>>>>>>>>>> PROCEDURES, AND STRATEGIES

ESTIMATE THE COST OF

Repairing a 3-Story,
3-Unit Apartment
Damaged by Fire in the
First Floor Apartment
submitted by Bradley Arthur Andrews, CPE

Bradley Arthur Andrews, CPE is a General Construction


Estimator in West Sacramento, California. Brad’s career began 1) Introduction

as a junior project engineer preparing construction estimates 2) Types and Methods of Measurements
from drawings as he finished his Bachelors of Science degree in 3) Specific Factors
Applied Science and Engineering from Portland State University.
4) Overview of Labor, Materials, Equipment,
He continued his work to becoming a Senior Field Engineer then
as a General Construction Estimator for an industrial building Indirect Costs, & Approach to Markup

contractor. He worked as an estimator of a structural steel 5) Special Risk Considerations


fabricator and erector before starting his own general building
6) Ratios and Analysis
construction firm. He was the construction manager for a
7) Misc. Pertinent Information
university and then the estimator for a regional environmental
remediation contractor. For the last 24 years he has been a 8) Sample Sketches

General Building Estimator with construction consulting firms 9) Sample Takeoff & Pricing Sheets
specializing in building repair related work. He is currently
working for Madsen, Kneppers & Associates, Inc. and has been
for the last 13 years. Today he is a member of ASPE Chapter 11.

www.aspenational.org February 2012 11


Estimate the Cost of: REPAIRING 3-STORY, 3-UNIT APT DAMAGED BY FIRE ON 1ST FLOOR APT

1. Introduction 06 17 00 - Shop-Fabricated Structural Wood Brief Description


06 22 00 - Millwork
This technical paper is intended The author will present the
06 43 00 - Wood Stairs and Railings requirements of the Construction
to provide the reader with a general 06 44 00 - Ornamental Woodwork
understanding of performing professional Estimator to inspect the site, to interact
06 48 00 - Wood Frames with the design engineer, to review
construction estimating services as they
relate to determining the cost of repairing 07 01 00 - Operation and Maint. of existing plans, to develop specifications
Thermal and Moisture Protection and a scope of work, to perform a review
fire damage to three stacked condominium
apartments at the end of a three story 07 21 00 - Thermal Insulation of the scope of work, to perform quantity
building that houses 24 apartments. 07 26 00 - Vapor Retarders takeoffs, to collect and compile direct
Determining the extent of damage and 07 31 00 - Shingles and Shakes and indirect costs, and to develop a cost
the most efficient method of repairing the 07 51 00 - Built-Up Bituminous Roofing estimate, factoring the available data
damage in a safe manner while meeting 07 62 00 - Sheet Metal Flashing and Trim and using labor and equipment rates
the requirements of code officials are but 08 01 00 - Operation and Maintenance
that are commensurate with working
a few of the factors for the estimator to of Openings in an occupied apartment building.
consider while preparing the estimate. 08 14 00 - Wood Doors The paper will be presented from
The estimator must familiarize themselves 08 17 00 - Integrated Door Opening
the General Contractor Construction
with the building, construction of the Assemblies Estimator’s point of view in preparing
building elements, and site conditions by 08 32 00 - Sliding Glass Doors
a bid rather than that of materials
inspecting the site. suppliers and subcontractor estimators.
08 51 00 - Metal Windows
The assumptions, used in preparing this
The repair work to these three 08 71 00 - Door Hardware
paper, are that floor plans exist for the
apartments is more challenging than 08 81 00 - Glass Glazing project, the specifications and structural
constructing the entire building as new 08 83 00 - Mirrors plans cannot be located, and that the
construction. Maintaining the access for 08 95 00 - Vents design engineer has prepared shoring
the tenant/owners to the undamaged 09 01 00 - Maintenance of Finishes and repair drawings. These types of
adjoining 21 apartments as well as utility 09 22 00 - Supports for Plaster and projects are typically bid on a fixed
services, parking, and driveways adds Gypsum Board price basis, with the understanding that
to the general conditions or unit costs. 09 24 00 - Portland Cement Plastering the scope of work may change due to
This estimate will include the following 09 29 00 - Gypsum Board hidden conditions.
specification divisions and subdivisions:
09 63 00 - Masonry Flooring
Main CSI Divisions: 09 65 00 - Resilient Flooring 2. Types and Methods
01 – General Requirements 09 68 00 - Carpeting of Measurements
02 – Existing Conditions 09 91 00 - Painting The preparation of an estimate for the
03 - Concrete 10 21 00 - Compartments and Cubicles bid to a building repair project requires
06 – Wood, Plastics and Composites 10 28 00 - Toilet, Bath, and Laundry the quantity takeoff that measure
07 – Thermal and Moisture Protection Accessories multiple items that include rough
08 - Openings 10 31 00 - Manufactured Fireplaces carpentry lumber framing removal
09 - Finishes 12 21 00 - Window Blinds and installation by the board foot (BF)
10 - Specialties 12 36 00 - Countertops or lineal foot (LF); framing hardware,
11 - Equipment 14 24 00 - Hydraulic Elevators known lengths of lumber and building
12 - Furnishings 14 27 00 - Custom Elevator Cabs materials and specific unit items such
14 - Conveying Equipment 22 01 00 - Operation and Maintenance as equipment, locksets, plumbing and
22 - Plumbing of Plumbing electrical fixtures by each (EA) item;
22 11 00 - Facility Water Distribution finishes such as gypsum drywall, painting,
23 - Heating, Ventilating and AC
22 33 00 - Electric Domestic Water Heaters floor coverings and finished concrete
26 - Electrical by square feet (SF); finish carpentry
22 41 00 - Residential Plumbing Fixtures
Main CSI Subdivisions: and painting of trim, plumbing piping,
23 31 00 - HVAC Ducts and Casings
electrical wiring, telecommunications
02 41 00 - Demolition 23 34 00 - HVAC Fans
cable, and ventilation ducts by lineal
02 82 00 - Asbestos Remediation 26 05 00 - Common Work Results feet (LF); roofing by square feet divided
03 01 00 - Maintenance of Concrete for Electrical
by 100 known as squares (SQ); carpet
03 64 00 - Injection Grouting 26 27 00 - Low-Voltage Distribution and plaster/stucco by the square yard
03 80 00 - Concrete Cutting Equipment
(SY); plumbing rough-in typically by the
03 82 00 - Concrete Boring 26 51 00 - Interior Lighting
fixture (FIXT); and general demolition and
06 05 00 - Common Work Results for 27 15 00 - Communications Horizontal repair quantities of labor or equipment
Wood, Plastics & Composites Cabling
use, emergency shoring, preparation
06 11 00 - Wood Framing 27 30 00 - Voice Communications time or work that is not common such as
06 13 00 - Heavy Timber Construction 28 31 00 - Fire Detection and Alarm miscellaneous repairs will be estimated
06 16 00 - Sheathing 32 12 00 - Flexible Paving by the use hour or man hour (HR).

12 February 2012 www.aspenational.org


Estimate the Cost of: REPAIRING 3-STORY, 3-UNIT APT DAMAGED BY FIRE ON 1ST FLOOR APT

A repair project to an existing building of furnishing and installing plumbing These conditions as well as local labor
requires that the construction estimator items in the wall and floor up to the hourly rates and economic conditions
becomes knowledgeable of how the building utility connection into one unit vary from region to region, state to state,
facility was constructed. Quite often cost. These include piping supply lines, and city to city. As an example, rates in
the only information available is on site. waste lines and vent lines. the San Francisco area are higher than
The estimator may need to measure Finally there are items that require those in Sacramento. More union activity
the entire building, room by room and occurs in larger urban environments than
hourly units of measure (HR). Those
construction element by construction does in the outlying areas which also tend
construction or repair items that are
element and even count the items that to drive costs upward.
reliant upon historical experience and
are observed to have been installed.
Where framing materials lengths are
knowledge of the estimator, such as Seasonal Effect on Work
the repair of a door, or upon the total
indeterminate and the nominal size of Weather considerations must also be
time required to perform several other
the framing member is known the unit of accounted for in the scope of work and
tasks, such as crane equipment, are
board feet (BF) is used. This unit is also costs for installation. Northern coastal
estimated by the HR.
used in estimating the framing in most areas and those areas influenced by
projects; however, in repair projects the 3. Specific Factors coastal and mountain conditions,
quantities and dimensions of materials especially in northwestern regions
vary significantly and often become Small Quantities of the country, normally experience
cumbersome when using this unit. vs. Large Quantities more rainfall in the fall, winter, and
Lineal footage (LF) is used for Economies of scale are very apparent spring seasons than do inland and
framing and finish materials, gutters in many projects. A larger project has southern areas. Weather protection
and downspouts, plumbing piping, lower unit costs for labor, materials, and is increased and labor productivity is
heating and ventilating duct work and equipment because of the increased decreased in rainy weather and thus
painting estimating where the length efficiency in utilization of labor hours costs are driven upward. Additionally,
and dimension of the materials can be over a larger quantity of materials. The freezing temperatures affect working
determined either by measurement on large quantity of materials being used conditions, scheduling, and productivity.
site or from plans when available. decreases the shipping and handling Productivity decreases in both hot and
costs as well as packaging / bulking cold conditions. Above grade framing
Where there is a substantial portion work becomes more dangerous as the
of the building to be repaired remaining costs and increased efficiency in using
equipment eliminating down time. A working surfaces become slick in icy
intact, the estimator can count the or wet conditions. The construction
elements or items that can be removed larger project allows for a more even
distribution of overhead, indirect and estimator must be cognizant of the
and installed by historical data. These production schedule and season that
items are quantified estimated by the direct costs. Building repair projects
can be anywhere in the scale of large affects each task when considering the
unit each (EA). costs for the project. Historical data
to small depending upon the damages
The construction estimator, incurred to the facility. Repairing one for similar projects is invaluable in
from the length, width, and height room or one apartment is much more producing the estimate.
measurements can readily calculate costly than repairing eleven rooms each Special Considerations
the square footage (SF) of the surfaces in three apartments and thus the unit
that lend themselves to costing by Affecting Construction
costs will be lower in the larger project. Repairs to an Occupied
this unit. As mentioned before, the
SF is used in sheathing, gypsum Geographic Location Multilevel Apartment Building
wallboard, texturing, wallpaper and Geographic locations and regions There are several additional factors
painting and, when necessary, general affect the unit costs to be considered to consider when proceeding with the
rough in for electrical wiring. This on any project. Labor availability, estimating of the repairs to an occupied
unit of measurement is converted specifically skilled crafts persons for multilevel apartment building. Among
to square yards (SY) for carpet and high quality construction are quite often these factors are accessibility to the work
stucco surfaces. The SF unit is also not locally available and the labor rate area, maintenance of services to the
converted to squares (SQ) when can thus be higher than the local skilled occupied apartments, noise that affects
estimating roofing materials. labor which also varies per region within the tenants, accessibility for the tenants
In a repair project, there is often in the state. Material availability as well to their parking spaces, living spaces
difficulty in determining exact quantities as material delivery costs also factor and common usage areas, delivery
of individual elements that comprise into the local unit costs for the project. of materials to a multilevel building,
a unique assembly. The estimator Material delivery costs also vary by the maneuvering on site, structural integrity,
must use historical data available from existing site conditions. Equipment and safety of personnel and protection
personal records, company records, or required for the project, especially of the structure from additional damage.
reference documents. Plumbing rough- hoisting and pumping equipment, are When developing the scope of work for
in is an example of a unique assembly very often not locally available or may be the project, the construction estimator
and is estimated by the fixture (FIXT). in high demand which causes increased must consider where utilities are located
This unit of measure combines the costs costs and scheduling difficulties. in the walls including natural gas, water,

www.aspenational.org February 2012 13


Estimate the Cost of: REPAIRING 3-STORY, 3-UNIT APT DAMAGED BY FIRE ON 1ST FLOOR APT

sewer and electrical feeds. Disturbing 4. Overview of that is at the job site, a staging site, or
the continuity of these services to Labor, Material, the contractor’s home site. Materials
the existing tenants is problematic. quotations are solicited from suppliers
Maintenance of these services adds to Equipment, Indirect and may be either manufacturers or
the costs of the repairs and must be Costs and Approach dealers. The materials for a repair
considered in the estimate. to Markups contract can include manufactured
Noise from the work also affect the tresses, sheathing, gypsum wallboard
The construction estimator historically and accessories, and framing lumber
tenants; therefore, normal work hours computes labor and equipment costs on
must be adhered to which may interrupt depending on the scope of work
an hourly basis. Typically, projects that determined for the repair.
the completion of specific work such as are not publicly owned are not subject to
pouring and finishing concrete. This may prevailing wages known as Davis-Bacon Specialty subcontractor quotations
add to the cost due to additional loads Wages; however, this project is located are solicited for scaffolding, roofing,
of material delivery and equipment in a popular resort area where there plumbing, electrical, painting, floor
usage time. is high competition for skilled labor. coverings, and gypsum wallboard
Tenant accessibility as well as the Because of this competition and the installation on larger projects; however,
contractor’s accessibility to their necessity for quality of construction at the general contractor’s estimator
respective areas affects maneuverability the site, skilled labor rates are calculated may simply obtain unit costs from the
of equipment and the method of based on the published prevailing rates. specialty contractors and determine
delivery of materials. Cranes and Table 1 illustrates the calculations for the total costs from quantities that
forklifts may not be useable which may Section 4
regular work hour, straight time wages the estimator has calculated. This is
necessitate hand delivery of materials by the hour. normally done for trades requiring
Overview of Labor, Material, Equipment, Indirect Costs
specialty and Approach
training to Markups
and licensing such as
from the delivery vehicle to the work Equipment rates for specialty
area. Storage or staging of materials plumbing and electrical.
equipment
The such as
construction cranes historically
estimator and forkliftscomputes labor and equipment costs on an
may require an offsite location rather are obtained from local rental equipment After the general construction
than storing the material adjacent to hourly basis. Typically, projects that are not publicly ownedhas
suppliers. estimator established
are not subject to the hard
prevailing
the work area. costs for a project the length of time
Unit known
wages costs for
as materials
Davis-Baconare based
Wages;onhowever,
to complete
this projectthe project inora popular
is located project
Delivery of materials to a multilevel the quantities in the takeoff. The unit
apartment building is also affected duration needs to be established. The
costs include
resort waste
area where factors
there thatcompetition
is high the project duration
for skilled labor.is significant
Because ofwhen this
by stairwells and elevators. The construction estimator has determined
construction estimator must factor the determining the indirect or soft costs
from historical
competition or calculated
and the methods.
necessity for quality of construction
that need at to the
be site, skilled labor
estimated rates
or applied
availability and access to the upper The cost for materials also includes
floors and the efficiency of the hand to the total estimate. First, the General
freight
are costs to
calculated the point
based on theatpublished
which the prevailing rates. The
Conditions or following
conditions tablespecific
illustrates
to
delivery and elevator delivery to these contractor accepts delivery whether
areas if high reach forklifts and cranes the project need to quantified or
the calculations for regular work hour, straight time wages by the hour.
cannot access the site.
The existing site conditions must be Table 1 Total Fringe Total Wage
examined thoroughly to insure that Total GC Wage Subcont.
Benefits incl. (excludes
Trade Base for Estimate
the damaged structure is safe or can Gov't. reqmnts and Subcont.
Wages Estimate Rate
be made safe in order to perform the workers Comp markups)
repairs. The construction estimator Asbestos Removal
needs to factor the costs to examine, – Specialist $24.90 $19.30 $44.20 $45.00 $56.00
design, and install temporary shoring Carpenter $40.24 $35.46 $75.70 $80.00 $95.00
based on examination of the site. Safety Cement Mason $33.79 $20.69 $54.48 $70.00
items for installation of this shoring as Drywall - Installer /
well as consideration for workers safety lather $40.24 $30.13 $70.37 $72.00 $88.00
Electrician -
above grade to a multilevel structure, $96.00
Journeyman $39.48 $31.50 $70.98
including the use of scaffolding needs to Floor covering -
be factored into the project costs. Journeyman $43.61 $10.84 $54.45 $70.00
In summary, the construction Glazier $41.51 $28.41 $69.92 $88.00
Laborer - Group 3 $29.17 $19.74 $48.91 $49.00 $62.00
estimator must become familiar with Marble Mason $39.22 $28.14 $67.36 $85.00
and consider the multitude of factors Operating Engineer $42.50 $25.16 $67.66 $85.00
that will affect the costs of the work. Painter -
Economies of scale, work schedule, Journeyman $33.95 $24.90 $58.85 $74.00
labor rates, safety, weather conditions Plaster $31.01 $21.33 $52.34 $66.00
and site conditions all significantly affect Plumber -
Journeyman $40.20 $36.02 $76.22 $96.00
the final cost reflected in the estimate. Roofer $28.68 $17.78 $46.46 $60.00
Sheet Metal Worker $37.32 $33.69 $71.01 $96.00
Tile Finisher $38.51 $22.44 $60.95 $77.00

14 February 2012 www.aspenational.org


Estimate the Cost of: REPAIRING 3-STORY, 3-UNIT APT DAMAGED BY FIRE ON 1ST FLOOR APT

estimated. The General Conditions Often, as in this repair project, the 7. Other Pertinent
include Project Management and roof has been compromised leaving the Information
supervision, safety training, site offices building open to rainy weather conditions.
and communications, vehicles and The estimator must account for weather Repair of damaged buildings,
operation, sanitary facilities, materials protection and the costs of maintaining not unlike a new structure, include
storage, utilities usage and temporary the environment of the existing building inspections by building officials from
connections, scaffolding and hoisting to prevent further damage. the local regulatory governmental
equipment that will be used throughout agency. Quite often the building official
There are also the possibilities of will require work that is not readily
the project, site security, and necessary hidden conditions within the existing
public domain interruption such as apparent to the construction estimator.
building that a condominium owner Of course the construction estimator
traffic flow and sidewalks permits and may have altered from the original
barricades. cannot include costs for this work in
plans. Demolition activities must be the estimate; however, prior to bidding
Other indirect costs will also need approached such that and accident be the work, the construction estimator
to be applied to the estimate. These prevented should a building element be should, if possible, inquire or involve the
include bonds and insurance applied removed that may cause a collapse. The building officials to determine any code
to the total of the hard costs and the contractor should engage the services requirements for the project that are
general conditions. The home office of an engineering design professional to not readily apparent. Communications
costs factor, known as Overhead is then determine how and where the structure with the owner, design consultants,
applied to the total of the site specific should be shored. and other responsible parties must be
costs and the bonds and insurance. The The construction estimator has a entertained and initiated to insure that
Overhead figure is normally determined responsibility to include costs in the the total project costs are included in the
by the contractors’ annual costs for estimate for outside consulting services estimate and resulting bid for the work.
operating the construction business. as well as adjust unit costs for the actual If possible, the building officials should
These costs include accounting, site conditions. meet at the site with the responsible
administration, fixed office rental costs, parties at a pre-bid conference to
copying and communication equipment, 6. Ratios and Analysis accomplish the inclusion of all work in
legal services, and owner/management the scope for preparing the estimate.
There are a number of publications
salaries. The total of these costs, on an
and services available today that provide
annual basis, is then applied to each
project based on a percentage of gross
information that can aid the estimator 8. Sample Sketch
with determining if the estimate unit See sketch on the next page. The sketch
annual volume of work.
costs and total costs are correct and is also available in PDF format, as is the
Finally, the construction estimator accurate. Some of these publications Takeoff & Pricing Sheets in Section 9. Click
needs to confer with their company include “R.S. Means Construction Cost on the pictures or the PDf icon to view
owners or head management to Data” which is published annually by the documents.
determine the profit margin to be Reed Construction Data Construction
applied to the project. Multiple factors Publishers & Consultants and “Design
affect the profit margin percentage. Cost Data” (DCD) which is a bi-
The profit margin can be high for high monthly publication prepared by DC&D
risk projects or nothing when the Technologies, Inc. These publications
construction economy is weak, there is concentrate on new construction which
low risk, and the competition is strong seldom assists the contraction estimator
for the project. with accurate tests for a repair project.
A contractor that engages in repairing
5. Special Risk existing damage buildings should
Considerations maintain historical records that will build
The repair of an occupied building a data base of similar work for which
challenges the contractor with the estimator can rely on to compare
many risks as discussed in previous the estimate they are preparing.
sections of this paper. Maintaining A construction estimator always has
utility connections and service to the a responsibility to revisit the quantity
apartments that are occupied and takeoffs to compare them to the available
controlling interference with those plans and/or site information. Accuracy
tenants requires additional scheduling is paramount for both quantities and
and attention to communication with specified materials in preparing the
the tenants should interruptions become estimate that binds a contractor to a
necessary. Slower production rates can fixed price contract.  
be encountered due to interruptions
and tenant access requirements.

www.aspenational.org February 2012 15


Estimate the Cost of: REPAIRING 3-STORY, 3-UNIT APT DAMAGED BY FIRE ON 1ST FLOOR APT

Section 8

Sample Plan
8. Sample sketch

The plan illustration above is of one of the three stacked apartments. The actual site
The plan illustration above is of one of the three stacked apartments. The actual site conditions revealed that two of the
apartments had been altered to enclose the patio deck outside of the Den - Study.
conditions revealed that two of the apartments had been altered to enclose the patio

deck outside of the Den - Study.


16 February 2012
21
www.aspenational.org
Estimate the Cost of: REPAIRING 3-STORY, 3-UNIT APT DAMAGED BY FIRE ON 1ST FLOOR APT

9. Sample Take-off & pricing


Section 9

Sample Estimate – Takeoff and Pricing Sheets


Room Quantity Takeoff
ROOM QUANTITY TAKEOFF
Cost Estimate
Qty L W H Perim Unit Floor/ Unit Wall Unit CSI Item Description Qty Unit Mat’l Labor Equip Sub Total Cost
Description 02.411901 Remove Door
Feet LF Ceiling SF SF
frames 43 EA 0 6.48 0 0 $ 278.64
MASTER BEDRM 1 19.83 12.00 8.00 63.67 LF 238.00 SF 509.33 SF 02.411907 Remove Joist
Patio Door -1 8.00 6.67 -8.00 LF -53.33 SF charred ends 220 BF 0 0.64 0 0 $ 140.80
Door -1 2.67 6.67 -2.67 LF -17.78 SF 02.821311 Remove Drywall
Missing Wall -1 4.33 8.00 -4.33 LF -34.67 SF with mold
Net Total 48.67 LF 238.00 SF 403.56 SF (Asbestos
Drywall Total 421.33 SF Abatement
Conditions Storage
Smoke Seal 210.67 SF room ceilings 1'-4"
MASTER plus 2' down wall -
CLOSET 1 7.33 5.00 8.00 24.67 LF 36.67 SF 197.33 SF Storage 132 SF 0.54 2.55 0 0 $ 407.88
Door -1 2.50 6.67 -2.50 LF -16.67 SF 03.013061 Repair lightweight
Net Total 22.17 LF 36.67 SF 180.67 SF concrete infill 258.5 SF 0.26 1.31 0 0 $ 405.85
Smoke Seal 03.013071 R&R Light weight,
(common /Mbr) -1 7.33 8.00 -7.33 LF -58.67 SF gypsum concrete - $
Door -1 2.50 6.67 -2.50 LF -16.67 SF 1 1/2" thick 1347.68 SF 0.87 6.43 0.13 0 10,013.26
Smoke Seal LF 36.67 SF 122.00 SF 03.642313 Epoxy injection -
VANITY 1 4.33 5.33 8.00 19.33 LF 23.11 SF 154.67 SF concrete repair
Missing Wall -1 4.33 8.00 -4.33 LF -34.67 SF (per LF of crack) 2.5 LF 13.64 20.25 0 0 $ 84.73
Doors -2 2.50 6.67 -5.00 LF -33.33 SF 03.811301
Saw cut lightweight
Net Total 10.00 LF 23.11 SF 86.67 SF concrete 29.2 LF 0.58 1.28 0.4 0 $ 65.99
Floor Covering 15.89 SF 03.821309 Concrete Core
Vanity unit 1 4.33 2.00 2.50 -4.00 LF -8.67 SF -20.83 SF Drilling 1" dia. X 1"
Smoke Seal 1 4.33 8.00 4.33 LF 0.00 SF 34.67 SF deep 30 EA 0.07 5.25 0.25 0 $ 167.10
MASTER BATH 1 6.00 5.00 8.00 22.00 LF 30.00 SF 176.00 SF 06.052301 Drag strut
Door -1 2.50 6.67 -2.50 LF -16.67 SF connection 6 EA 7.04 26.24 0 0 $ 199.68
06.052304 Wedge anchor bolt
Net Total 19.50 LF 30.00 SF 159.33 SF
- 5/8" X 6" 5 EA 8.06 6.56 0 0 $ 73.10
Floor Covering 15.00 SF
06.052306 Framing hanger -
Smoke Seal large 63 EA 6.7 6.56 0 0 $ 835.38
(common /Hall) -1 6.00 8.00 -6.00 LF -48.00 SF
06.052308 Framing hurricane
Door -1 2.50 6.67 -2.50 LF -16.67 SF tie 250 EA 5.29 3.28 0 0 $ 2,142.50
Smoke Seal LF 30.00 SF 111.33 SF 06.052312 Framing hold down
Texture & - 16" 16 EA 66.03 65.6 0 0 $ 2,106.08
Paint -2 3.00 6.67 -6.00 LF -40.00 SF 06.052314 Framing strap -
(Shower) -1 5.00 6.67 -5.00 LF -33.33 SF CST16 120 EA 3.14 2.3 0 0 $ 652.80
Door -1 2.50 6.67 -2.50 LF -16.67 SF 06.052316 Framing strap -
Texture & Paint 30.00 SF 86.00 SF MST37 8 EA 16.95 16.4 0 0 $ 266.80
06.052318 Framing strap -
MST60 4 EA 36.86 22.96 0 0 $ 239.28
06.105301 R&R Stud wall - 2"
x 4" - 16" o.c. 1047.84 SF 0.37 2.23 0 0 $ 2,724.38
The above is a quantity takeoff of only four rooms in the project 06.105303 R&R Joist - 2x10
floor or ceiling
that are common to all three apartments. 06.105305
system
Sister joists 2 x 10
26.67
586.66
BF
BF
0.76
0.83
2.95
3.28
0
0
0
0
$ 98.95
$ 2,411.17
06.105306 2" x 4" x 8' #2 &
better Fir / Larch
(material only) 10 EA 2.47 0 0 0 $ 24.70

General Conditions 23

The above estimate includes the General Conditions as listed in


Mat Labor Equip
the following table.
CSI Item qty unit Unit Unit Unit Unit Cost Total
Rate Rate Rate

Project Superintendent
01 31 01
01 41 26
- 1/2 time
Permits
312
1
HR
EA
0.00 78.00 0.00 $78.00
$10,298.25
$24,336.00
$10,298.25
Click on the
170.0
thumbnails to
01 52 13 Storage Container 3 MO 0.00 0.00 0 $170.00 $510.00 view the PDF.
Pick up & deliver 130.0
01 52 14 storage container 3 EA 0.00 0.00 0 $130.00 $390.00 Click on this PDF
Debris Chute Hopper -
01 54 09 2 each for 10 weeks 14 MO 0.00 0.00 36.00 $36.00 $504.00 icon to view as an
Debris Chute Section -
10 each - 10 weeks + entire document.
01 54 10 16 demo 96 WK 0.00 0.00 15.50 $15.50 $1,488.00
Debris Chute mounting
Hdwe 2 for 10 weeks +
01 54 11 2 wk demo 12 WK 0.00 0.00 21.25 $21.25 $255.00

01.54 18 Boom Lift 3 MO 0.00 0.00 2,300 $2,300.00 $6,900.00 Quote from the Author:
Boom Lift Delivery and 130.0
01 54 19 Pick-up 2 EA 0.00 0.00 0 $130.00 $260.00

01 54 21
Telescopic Fork Lift
and operator 12 HR 0.00 62.00 16.28 $78.28 $939.36
“Pursuing and achieving the ASPE Certified Professional Estimator status
01 54 22 Concrete Pump Truck 4 HR 0.00 0.00
240.0
0 $240.00 $960.00
proved both challenging and satisfying. The CPE Certification adds
01 54 23
Scaffold Set up and
take down 24 HR 0.00 48.75 0.00 $48.75 $1,170.00
a professional standard of credibility to both my estimates and those
01 54 24
Scaffold 10 sections
2.5 months + demo 27 MO
120.
00 0.00 0.00 $120.00 $3,240.00
produced under my supervision for our clients. I have been estimating
01 56 26
Fence, signs and
barricades 10 MO
100.
00 0.00 0.00 $100.00 $1,000.00
for over forty years and view the CPE process and achievement as
01 73 21 Misc Demolition 48 HR 0.00 51.00 0.00 $51.00 $2,448.00 authentication of the career I have chosen.”
General Cleaning -
01 74 13 Daily 64 EA 0.00 37.00 0.00 $37.00 $2,368.00  
560.0
01 74 14 Debris Box 24 EA 0.00 0.00 0 $560.00 $13,440.00 Bradley A. Andrews, CPE | Chief Estimator
TOTAL GENERAL
CONDITIONS
$70,506.61
Madsen, Kneppers & Associates, Inc.
West Sacramento, CA

www.aspenational.org February 2012 17