A project sponsor tells the project manager that stakeholder expectations and risk thresholds have not been addressed
by a particular document. Project planning cannot begin until the sponsor approves this document.
Hint:
The project manager is in the process of developing the project charter.
Correct Answer: B
Explanation:
The question suggests that the project manager has developed a draft of the project charter, which must be reviewed
and approved by the project sponsor before project planning can begin. High-level risks may be captured in the project
charter and may be of particular importance if key stakeholders have low-risk tolerances. Stakeholder expectations and
risk thresholds are part of the enterprise environmental factors, which may serve as an input into the development of the
project charter. Therefore, of the available answer choices, the project manager most likely did not adequately consider
the enterprise environmental factors.
https://www.project-management-prepcast.com/6-pmp-exam-simulator/task,stu_result/stu_id,1061810/id,6/quiz_id,127?task=stu_result&tmpl=quiz&id=6 1/2
28/8/2019 Incorrect. Although organizational process assets are
Online inputs- PMP
Courses into Exam
the development
Simulator of the project charter, which is
the document described in the question, stakeholder expectations and risk thresholds are not an element of the
organizational process assets.
Reference:
A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute
Inc., 2017, Page(s) 78