Professional Documents
Culture Documents
MANAGEMENT 2
Discounted Pay
Back Period Method
The length in years required to recover the initial cash out lay on the present value
basis is called
the discounted pay back period.
The opportunity cost of capital is used for calculating present values of cash inflows.
Discounted pay back period for a project will be always higher than simple pay back
period
because the calculation of discounted pay back period is based on discounted cash
flows.
For example:
Calculate the discounted pay back period for the following, considering a 10% discounting
factor.
0 (4,00,000)
1 2,00,000
2 1,75,000
3 25,000
4 2,00,000
5 1,50,000
Solution :
Year Project A Cash flows PV factor at 10% PV of Cash flows Cumulative positive Cash flows
0 (4,00,000) 1 (4,00,000)
1 2,00,000 0.909 1,81,800 1,81,800
2 1,75,000 0.826 1,44,550 3,26,350
3 25,000 0.751 18,775 3,45,125
4 2,00,000 0.683 1,36,600 4,81,725
5 1,50,000 0.621 93,150 5,74,875
1. Estimation of cash flows, both inflows and outflows of a project over the
entire life of the project.
3. Sum of the present value of cash outflows is deducted from the sum of
present value of cash inflows to arrive at net present value of cash flows, the
most popular techniques of DCF methods.
The Net Present Value
1. Forecast the cash flows, both inflows and outflows of the projects to be taken
up for execution.
2. Decisions on discount factor or interest factor. The appropriate discount rate is
the firms cost of capital or required rate of return expected by the investors.
3. Compute the present value of cash inflows and outflows using the discount
factor selected.
4. NPV is calculated by subtracting the PV of cash outflows from the present
value of cash inflows.
Accept or Reject Criterion
NPV method can be used to select between mutually exclusive projects by examining whether
incremental investment generates a positive net present value.
Merits of NPV Method
1. Forecasting of cash flows in difficult as it involves dealing with the effect of elements
of uncertainties on operating activities of the firm.
2. To decide on the discounting factor, there is the need to assess the investor’s
required rate of return But it is not possible to compute the discount rate precisely.
3. There are practical problems associated with the evaluation of projects with unequal
lives or under funds constraints.
For ranking of projects under NPV approach the project with the highest positive NPV is
preferred to that with lower NPV.
Illustration:
A project costs Rs.25000 and is expected to generate cash in flows as
1. C system with a high initial cost but low annual operating costs.
2. F system which costs less but have considerably higher operating costs.
The decision to construct the plant has already been made, and the choice here will have no effect on the
overall revenues of the project. The cost of capital of the plant is 12% and the projects expected net costs
are listed below:
Which method should be chosen? Give your answer based on the incremental approach.
Solution: Computation of present value
Year C Systems F Systems Incremental
1 (66,000) (96,000) 30,000
2 (66,000) (96,000) 30,000
3 (66,000) (96,000) 30,000
4 (66,000) (96,000) 30,000
5 (66,000) (96,000) 30,000
Since the present value of incremental net cash inflows of C system over F system is negative.
As even at a higher discount rate investment B gives a higher present value, investment B
Should be preferred.
Question:
A firm has to choose between three possible projects and the details of each project are as
follows:
For B
To get the present values, multiply the net cash flow for that year by the discount factor. This gives
present values as follows:Net cash flow Present value ($000) Year 1 75 92.6 Year 2 125 171.4 Year 3 125
238.2 Year 4 100 220.5 Year 5 75 102.15 The total present value is therefore $824,850. If we deduct the
capital cost of $500,000, then this gives a net present value of $324,850.
For C
To get the present values, multiply the net cash flow for that year by the discount factor. This gives
present values as follows:Net cash flow Present value ($000) Year 1 75 46.3 Year 2 125 64.275 Year 3 125
198.5 Year 4 100 220.5 Year 5 75 136.2 The total present value is therefore $665,775. If we deduct the
capital cost of $450,000, then this gives a net present value of $215,775.
Profitability
Index
Profitability Index
Demerits of PI
1. Estimation of cash flows and discount rate cannot be done accurately with certainty.
2. A conflict may arise between NPV and profitability index if a choice between mutually
exclusive projects has to be made.
Accept or Reject Criterion
PI = PV of Cash inflows
Initial cash outlay
An investment proposal requires an initial outlay of Rs. 4000/- with an expected cash inflow of Rs. 1000/-
per year for 5 years.
i) PV @ 15% = 3354
PV @ 6% = 4212