Professional Documents
Culture Documents
Objectives of The Experiment
Objectives of The Experiment
The objectives of the experiment were based exclusively on operating the cooling tower to collect the
relevant raw data which included the inlet and outlet temperatures together with the water flow rate as
well as the wet bulb and dry bulb temperatures of the inlet and outlet air streams.
In conjunction with collecting the raw data as stated above, the first objective was based on determining
the minimum air flow rate whilst the second objective was based on graphically drawing the operating line
for the cooling tower at the current operations.
EXPERIMENTAL DATA:
The Flow Meter was read using the gauge - 0.001 m3 / revolution = 1 L / revolution
IN ORDER TO COLLECT THE RAW DATA DEPICTED ABOVE, THE FOLLOWING PROCEDURE
WAS FOLLOWED IN THE LABORATORY UTILIZING THE COOLING TOWER EQUIPMENT:
1. Firstly the cooling tower was allowed to reach a steady state in which the operating conditions
were determined for a given cooling water flow rate.
2. When steady state has been reached, the inlet and outlet temperatures were recorded together
with the water flow rate.
3. The wet bulb and dry bulb temperature of the inlet and outlet air streams were also measured
utilizing a digital hygrometer.
4. Once the relevant raw data were gathered, the results were calculated using the appropriate
equations that are applied to a cooling tower.
BELOW IS A PIPING AND INSTRUMENTATION DIAGRAM OF THE EQUIPMENT
USED WHICH IS THE COOLING TOWER:
G2 L2
H2
HY2
TG L
TL
G1
T G1 L1
Ht T L1
H Y1
WHERE:
Where:
T = Temperature (°C)
WHERE:
Hy1 = Enthalpy of air- water vapour mixture entering the tower (kJ/kg dry air)
Hy2 = Enthalpy of air- water vapour mixture leaving the tower (kJ/kg dry air)
Where:
Hy1 = Enthalpy of air- water vapour mixture entering the tower (kJ/kg dry air)
Hy2 = Enthalpy of air- water vapour mixture leaving the tower (kJ/kg dry air)
TABLE 1: Table of Enthalpies, inlet and out let gas and liquid temperatures, cooling water flow
rate and flow rate of the air for loads 1, 2 and 3
LOAD 1 2 3
In the experiment different levels of loads were used. From the results obtained, we have deduced that
the amount of water transfer to the air is very low and minimal.
1. ANALYZING THE AIR FLOW RATE AND WATER FLOW RATE (REFER TO TABLE 1)
The air flow rate for load 1 was calculated to be 0.187 Kg/s whilst for load 2, the air flow rate was
calculated to be 0.197 Kg/s and for load 3, the air flow rate was 1.17Kg/s. It is without any doubt, that the
air flow rate for load 1 is relatively higher than load 2, whilst the air flow rate of load 1 as compared to load
3 are relatively the same and differ minorly.
On the other hand, the water flow rate for load 1 was calculated to be 0.0345 Kg/s, and for load 2 it was
determined to be 0.0333 Kg/s, whilst at load 3, the water flow rate was calculated to be 0.0303 Kg/s.
Once again the flow rates for load 1 are higher than that of load 2 and 3.
The inlet water temperature for load 1 was measured to be 42.5.°C, for load 2 it was measured to be 45°C
whilst for load 3, the inlet water temperature was measured to be 51°C. The outlet water temperatures
ranged from 21.5 °C, 22°C, and 22.9°C. We can clearly see that the outlet water temperatures are lower
than that of the inlet water temperature because of the latent heat of vaporization which does correlate
with theory.
All cooling towers operate on the principle of removing heat from water by evaporating a small portion of
the water that is recirculated through the unit. The heat that is removed is called the latent heat of
vaporization. The amount of heat lost by the water depends on the temperature rise of the ambient air
before it leaves the tower. This means that both the dry bulb and wet bulb temperatures of the air are
important. When Wet bulb temperature is equivalent to the dry bulb temperature, this condition
corresponds to 100% relative humidity that implies the air is fully saturated. The air will no longer accept
water and the lack of evaporation does not allow the wetted bulb to reject heat into the air by evaporation.
The higher the difference between dry bulb temperature and the wet bulb temperature, the lower is the
relative humidity, or the drier is the air. The lower relative humidity indicates greater capacity of air to
absorb or hold water and will result in efficient lowering of water temperatures. [cited in a pdf by A .Bhaita
about cooling towers]
The air humidity inlet in the first load is more than second and third load and the mass transfer coefficient
is approximately constant. In this experiment no resistance to heat transfer in liquid phase was assumed.
4. ANALYZING THE INLET AND OUTLET AIR TEMPERATURES (REFER TO TABLE 1 OF
RESULTS)
The inlet air temperature for load 1 was measured to be 26.14°C, whilst for load two, it was measured to
be 24.60°C and for load 3 the temperature was measured to be 24.80°C. The outlet air temperatures
ranged from 27.51°C, 26.60°C and 23.92°C. The outlet temperatures are higher than the inlet air
temperatures which can be explained through sensible cooling. The air temperature rises as it absorbs
sensible heat from the water. This sensible heat transfer occurs, if the dry bulb temperature of air is less
than the dry bulb temperature of water which account for 20% of the cooling theoretically.
Firstly the approach is the temperature difference between the cold water leaving the tower and ambient
wet bulb temperature. The average temperature of load 1 to load 3 is 22.13°C, hence the cooling tower
produces 22.13° C cold water when the ambient wet bulb is 20°C, then the cooling tower approach is
2.13°C.
The minimum air flow rate for load 1 was calculated to be 0.0227Kg/s, and for load 2 it was determined to
be 0.0175 Kg/s and for load 3, 0.0220 Kg/s. Once again the minimum air flow rate for load 1 is relatively
higher than that of load 2 and load 3.
The water flow rates for loads 1 to 3 are relatively the same, as well as the air flow rates. The inlet and
outlet water temperature differ by minor decimal values. The air inlet and outlet temperatures are also of
similar values.
CONCLUSIONS REACHED:
1. We have concluded that during the process of evaporation in the tower, only pure water is
discharged into the atmosphere as water vapor.
2. We have also concluded that sensible cooling takes place within the cooling tower regarding the
inlet and outlet air temperatures.
3. Cooling towers operate on the principle of removing heat from water by evaporating a small
portion of the water that is recirculated through the unit.
4. The amount of heat lost by the water depends on the temperature rise of the ambient air before it
leaves the tower.
5. Load 1 produces the best and optimum results and cools the water at a lower temperature as
compared to load 2 and load 3.
The Flow Meter was read using the gauge - 0.001 m3 / revolution = 1 L / revolution
Interpolation had to therefore be carried out between the percentage relative humidity of 40% and
50% and the dry bulb temperature of 27 °C and 24.8 °C respectively.
Interpolation:
50−40 24.8−27
=
40−43.9 27−T G 1
Therefore:
TG1 = 26.142 °C
Interpolation had to therefore be carried out between the percentage relative humidity of 60% and
70% and the dry bulb temperature of 28.5 °C and 26.6 °C respectively.
Interpolation:
70−60 26.6−28.5
=
60−65.2 28.5−T G 2
Therefore:
TG2 = 27.512 °C
For the cooling water flow rate 1 liter of water was collected during 1 revolution which took
29s.
1 Liter → 29s
x Liters → 1s
L = 0.0345 kg/s
6. FLOW RATE OF AIR (kg/s)
LC L (T L2−T L1)
G=
(H y 2−H yi )
Where:
Hy1 = Enthalpy of air- water vapour mixture entering the tower = 50 kJ/kg dry air
Hy2 = Enthalpy of air- water vapour mixture leaving the tower = 66kJ/kg dry air
Therefore:
(0.0345)( 4.12)(42.5−21.5)
G=
(66−50)
G = 0.187kg/s
7. MINIMUM AIR FLOW RATE (GMIN)
According to the operating line for load 1, where the slope is equal to:
LC L
Slope =
GMIN
The slope was calculated using points from this operating line:
Y 2−Y 1
Slope =
X 2−X 1
130−80
Slope =
34−26
Therefore
LC L
Slope =
GMIN
Where:
Therefore
L CL
GMIN =
Slope
(0.0345)(4.12)
GMIN =
6.25
GMIN = 0.0227 kg/s
NOMELATURE