Professional Documents
Culture Documents
School of Engineering
Dept. of Civil & Environmental Engineering
Planning
The specific approach to construction begins with a complete analysis of the job down
to its smallest part
Construction of each element is planned in terms of materials, taking into account
labour and equipment resources
The whole projects is then fitted into a closely integrated programme of construction,
the ideal being that:
flow of work should be logical and in a single direction;
distances travelled and amount of lifting and handling of materials during this flow should be
minimised;
Equipment and labour should be employed to capacity without breaks or delays due to
shortages or errors in the programme.
On the other hand, management is the art of physically making the plan work.
Planning should:
give the client intended completion or hand-over dates.
notify suppliers and sub-contractors when their goods or services will be required.
give contractor knowledge of future commitments to staff, labour, and plant.
Before starting site operations, adequate time should be made available for:
proper planning of equipment and methods
ordering of materials.
preparation of a balanced programme.
Planning shows possible problems in advance and thus provide opportunities for their
avoidance.
Increased productivity is made possible by reduction in double-handling, and improved
operational methods devised by work study techniques also result in reduced labour
and plant costs.
The continuity essential for early completion of the works can be maintained by
introduction of financial incentives scheme, this gives a higher level of earning and
motivation to the operatives.
Faster, more efficient construction means a shorter contract period, with less on-costs
and lower overheads, so that the resultant total cost is effectively reduced.
Programmes also provide a useful basis for ordering materials and a comparative
reference for assessing progress.
To all these advantages, add the growing record of comprehensive and realistic
company standards made possible by the detailed analysis of achievement against
plans for completed jobs, which in due course is reflected in more accurate and keener
estimating.
The reservoir site must be cleared before the dam is completed and the storage of
water begins.
It may be necessary to complete the concrete portion of the dam, and to install control
gates in order that this structure may serve as a means of diverting the water in the
stream while the earth fill is being placed.
The pump station, transmission line and treatment plant should be completed by the
time the reservoir has stored sufficient quantity of water to be usable.
Projects are usually divided into construction operations to facilitate job planning. A
construction operation is a portion of a project which may be performed by a
classification of labourers or a single type of equipment.
In constructing a reinforced concrete retaining wall, the project might be divided into
the following operations:
Excavation, machine
Excavation, hand
Formwork
steel fixing
Concreting.
In planning the construction of a highway requiring a new location, the project might be
divided into the following operations (which in this case can be stages):
moving to the project and setting up equipment
cleaning and grubbing the right of way
Earthwork, cut and fill
Drainage structures, box culverts.
Pavement
Clean-up and removal of plant.
To estimate the progress in constructing a project, the job planner should determine the
quantity of work to be constructed for each operation, expressed in an appropriate unit.
Then estimation should be made of probable rate at which work will be performed,
allowing for estimated loss in time due to bad weather or any other cause.
From this information, it is possible to estimate the total time required to complete each
operation.
It can be seen that stages may comprise various operations. If a project is thoroughly
analysed and the operation durations and sequence in each construction stage are
known, total estimated project duration can be arrived at.
Projects with durations of less than a year may be divided into weeks, while schedules
for projects requiring more than a year generally will be divided into months. The
schedule should show the dates clearly. If the time is divided into weeks, it is good
practice to show the end of the week, Saturday, as the effective date, with a notation
reading “For week ending.”
Every construction schedule should be identified with the particular project by placing
on it:
the job number;
the name of the project;
the name of the client;
the location; and
possibly names of consulting firms.
Job description:
The area in timber is slightly more than one-half of the total area of the right of way. The
specifications require the contractor to remove all trees and roots to a depth of 0.46m and to
burn the timber on the right of way.
The earth is a mixture of sand and clay, whose average borrow-pit weight is 1488 kg/m3. The
average swell will be 25%. It is estimated that the average initial moisture content will be 8% by
weight. Specifications require a moisture content of 12% during compaction. The earth is to be
placed in layers not exceeding 20cm in thickness when loose, and compacted to a density of
1554kg/m3
Task
Prepare a construction schedule for the job.
Moving in
The moving-in operation consists of transporting to and setting up at the project:
a two compartment aggregate - batching bin
a bulk-cement storage bin
a tools warehouse
offices
testing laboratory
equipment - repair and servicing facilities
construction equipment required for the project.
The equipment that will be needed first should be moved to the project as early as possible,
though it may not be desirable to transport all the construction equipment to the project prior to
beginning construction.
It is estimated that 1 week will be required for moving in and setting up the plant.
Drainage structures
If water courses are dry during the construction of drainage structures, the operations will consist
of excavating to the required grade and constructing the concrete slab, walls, roof and wing
walls.
If flowing water is expected during construction, it may be desirable to construct temporary
earth dams upstream and downstream the structure to divert the water through a ditch dug to
the side of the culvert, using a bulldozer to excavate the earth from the ditch.
The actual time required to construct a culvert may be determined as follows:
Bulldozer constructing temporary dams, excavating diversion ditch, and excavating culvert base
1 day
Fine grading, by hand 1 day
Erecting forms & placing reinforcing steel for base 1.5 days
Placing concrete for base 0.5 days
Erecting forms for walls and roof & placing reinf. steel 3 days
Placing wall & roof concrete 1 day
Removing & cleaning forms 1 day
Total 9 days
Add 20% for lost time 2 days
Total time 11 days
It is not necessary to complete one culvert prior to starting another. Assume that three culverts
are under construction at the same time. Under this schedule, one culvert should be finished
each week, with time allowed for the curing of concrete. Thus, a total of 12 weeks will be
required to complete the culverts.
Construction on the culverts should not be started until a sufficient portion of the right of way is
cleared to permit the construction to be continued without interruption. The culverts will be
started 2 weeks after clearing is started.
Earth fill
The earth for the fill will be excavated with a 1.14m3 power shovel, whose output should be
approximately 114m3 per hour bank volume. A truck having a struck capacity of 4.56m3 should
haul 4.56m3 bank volume if the heaped capacity is 5.6m3 loose measure.
Under reasonably good haul-road conditions, a truck should make a round trip in 12 min. If it is
assumed that a truck will operate an average of 50min per hr, because of necessary delays, the
number of trucks required will be obtained as follows:
An extra truck should be provided as a stand-by unit for use in the event of a breakdown by one
of the trucks.
Volume of earth placed in a week will be, 114m3/hr x40 = 4560m3
Time required to complete the fill will be;
Working time, 104 524 m3 @ 4560m3 per week = 22.9wks
Lost time = 5.7wks
Total time = 28.6 wks
Round time to: 29 weeks
In addition to the shovel and trucks, it will be necessary to provide one or more heavy-duty
graders to smooth and shape the earth in the fill and to maintain the haul roads, one or more
sheep’s-foot rollers to compact the earth, and enough sprinkler trucks to supply the required
water.
It is estimated that placing the fill can be started 2 weeks after clearing & grubbing is started.
Pavement
Area of concrete pavement =100,638m2
Volume will be 100,638x0.23= 23,147m3 (with no allowance for wastage or overrun in thickness)
A 34E dual-drum paving mixer, producing 1.156 m3 of concrete per batch, can mix a batch in 1
min. under favourable conditions.
Assume that the mixer will actually operate 50min. per hr, an average of 50 batches per hr can
be mixed and placed.
This is equal to, 1.16x50 = 58 m3 per hour or 58×40÷(1/0.23) = 10,087m2 per wk.
Time required to complete the operation will be:
Working time, 100,638 m2 @ 10,087 m2 per wk = 10 wks
Add 20% for lost time = 2 wks
Total 12 weeks
Unless it is practical to increase the rate of placing the fill, the concrete pavement should not be
started until 21 weeks after the construction of the fill is started. This will permit the last portion of
the fill to cure 4 weeks prior to placing the last pavement, as required by the specifications.
General clean-up & moving out
Assuming this operation will take 2 weeks, it can be started 11 weeks from the date work started
on the pavement.
There are the two basic possibilities of utilising available resources. In the case of
resource levelling, available resources are fixed crew right from the beginning to the
end whilst in resource smoothing there is variation in number of crews to be used but the
variation is not large.
In the example below in resource levelling 3 persons have been used from first to the last day of
the work while in resource smooth 3 persons have been used for 6 days and there is variation in
number of persons from 2 to 4 persons depending upon the amount of work to be executed.
In construction (building and civil), resource smoothing is applied mostly. The nature of
construction works does not make resource levelling economical.
Crew Crew
This involves the summing together of resources on all activities during the same period.
For activities having float time, there is a choice between aggregating the resources
anywhere between the earliest time and the latest time.
Disadvantages
Loss of flexibility that occurs from reducing slack
Increases in the criticality of all activities
…Are projects that involve resources that are limited in quantity or by their availability
There are two fundamental approaches to Resource-Constrained allocation problems:
Heuristic Methods
Optimization Models
Heuristic approaches employ rules of thumb that have been found to work reasonably
well in similar situations
Optimization approaches seek the best solutions but are far more limited in their ability
to handle complex situations and large problems
An unarticulated rule: in later periods, do not move activities that have already started
Additional caveat: when considering activities not to delay, consider the resources each
activity uses.
Assume we only have 3 people available to do the following project, and we cannot
afford to hire more.
Materials Management
Construction schedule may be used as a guide in specifying the delivery dates for
materials. Materials should be delivered to a project far enough in advance of their
need to assure that there will be no delays.
However, it is not good practice to have materials at the job site too far in advance of
their need as they may:
deteriorate
be damaged
be lost
congest the working area
If proper information is given to material suppliers, they can arrange to furnish the
materials as they are needed. Revisions in delivery dates (from schedule) can be made,
if necessary, during the construction of the project.
The term generally applies to all items and materials purchased for use in construction. It
includes issuable articles, tools, equipment, fixtures, etc.
Fool-proof arrangements for receipt and issue are essential for stores. The storage
department should be divided into the following three sections:
receipt section
holding section
issue section
Complete record of all the materials received and issued should be maintained.
It is very costly and difficult to give equal attention to all the items of inventory
1. A-B-C Control Policy
A-B-C analysis is meant for relative inventory control in which maximum attention is given to
items which consume more money and a fair attention to medium value items, while the
attention to low value items can be reduced to routine procedure only
If a cost examination in terms of project materials consumption is undertaken, it will be found
that about:
10% of the items accounts for about 70% of the total project materials cost.
20% of the items account for about 25% of the total material cost
70% account for 5% of the total material cost
The first category, small number of high cost consumption items are called A - items. The
second category of medium cost consumption value items are known as B- items. The third
category, large number of items with small total cost are C - items.
30
10 B
A 70 95
Percentage of total cost
Graph between percentages of total items in each category Vs percentage of total project cost consumption
for each category
A-B-C analysis does not depend on the unit cost of the item but on its project cost consumption.
It also does not indicate the importance of any item. The category of every item is important.
A-B-C analysis is a basic technique of materials management and can be applied over almost
all aspects of materials management such as:
Purchase
Sale
Inspection
inventory control
store keeping
The control policies for A, B and C items are based on two principles
to keep capital tied up inventory as low as practicable
to ensure that all the materials would be available when required.
b)Policies of B-items
the policies for B items in general are in between those for A and C items
orders for these items must be placed less frequently than for A items.
2 SDE Analysis
Items can be classified according to their use, consumption, value, etc. A-B-C analysis is the
oldest and commonly used method. SDE analysis is based on availability position of each item.
In this analysis:
S - refers to Scarce items, which are in short supply and their availability is scarce. This includes
imported items
D - refers to Difficult items, which cannot be produced easily
E - refers to Easily available items
A periodical study is necessary for finding obsolete or surplus (not being used for a
considerable period) items.
Such items should be re-examined for their alternative use. If they cannot be used
anywhere, they must be disposed off.
Mode of disposal must be decided in the following priority:
send it back on resale to the original supplier if they are interested
sell it at best possible price. If not possible then
sell at any available price, even at scrap value
if it could not be sold at scrap or at any rate, give it away for keeping it year after year blocks
space
To maintain a reserve of goods that will ensure requirements at the lowest possible
ultimate cost. Losses from improper inventory include:
purchases in excess than is needed
cost of slowed down production resulting from materials not being available when needed.
Proper inventory control can greatly reduce costs by
promoting smooth operations
preventing materials pile up
preventing m/c idle time
To run the stores effectively - This includes layout, storage media (bins, shelves, & open space,
etc.)
To ensure timely availability of materials and avoid build up of stock levels.
Technical responsibility for the state of materials; This includes:
methods of storing
maintenance procedures
studies of deterioration and obsolescence
Stock control system: Physical verification (stock taking) of records, ordering policies procedures.
Maintenance of specified raw materials: general supplies and component parts in sufficient quantities
to meet demand of production.
Protecting materials from losses due to improper handling and storing of goods and unauthorised
removal from stores
Pricing all materials supplied to the stores so as to estimate material cost.
In the second possibility, consumption rate may fall because of any of the following
reasons:
due to change in production plans; or
due to change in utilisation programme of a particular type of equipment.
In this case, rescheduling of the deliveries, or reducing the quantities of the pending
order must be resorted to, or if necessary pending orders be cancelled
Various records are kept in maintaining receipt and issue of materials such as;
receipt book
store issue register
bin cards
store ledger and issue indents, etc.
This is the process of putting the project back on track should adverse deviations from
what is planned occur. Control involves progress monitoring using the various
management instruments available and taking corrective action when deviations
occur.
At specified time intervals - daily, weekly, monthly; - reports should be submitted by
project supervisors to management, showing actual progress on each operation during
the specified time interval or at the effective date of the report.
This permits close monitoring of progress on a project. If progress on one or more
operations or on the entire project is behind schedule, such information will be known
early enough to take corrective steps.
It is better to take corrective steps during the early part of construction period instead of
waiting until there is no sufficient time to overcome the difficulties. Having to correct
time delays on short notice can be very expensive.
Project control is therefore a continuous activity. Effective control involves a regular
comparison of actual progress against required performance followed by appropriate
action to achieve desired objectives. This requires a constant interchange of
information which in turn pre-supposes good communications systems for effective
transmission of ideas, instructions and details.
Permits equipment to be shifted quickly from one operation to another, thereby reducing delays due to
equipment failure or reduces the amount of equipment required on a project because of efficient use.
Permits quick contact with the workshop in the event emergency repairs are required for equipment.
Expedites the distribution of materials to different operations.
Gives excellent control between concrete-mixing and placing operations. In the event of failure at either
location, the other can be notified immediately.
Permits quick calls for first aid or an ambulance in the event of injuries to personnel.
The aim of project supervision is to carefully monitor each of the individual project
components to ensure efficiency and cost saving.
Such supervision involves the following elements:
Labour
A regular comparison with anticipated project requirements of particular tradesmen would be more
helpful. The maintenance of the requisite labour force must be judged in conjunction with the progress
record
Plant
The plant schedule, from the method statement, prepared during the planning stage should be used to
ensure that machines are brought to the site at the appropriate time. Equally important is the necessity to
return equipment as soon as its use is finished. Instruction in the correct use and insistence on regular
maintenance is essential if standing time due to breakdowns is to be avoided.
Materials
Timed schedules of requirements prepared in conjunction with the contract programme should ensure that
materials are requisitioned and ordered in good time and assist the chasing of deliveries when suppliers fall
back or earlier despatch has to be effected. To check that all components are requisitioned, it is helpful to
prepare a materials scheduled for every drawing. This provides a means of supervising the initiation of
purchasing.
Information
It is necessary to institute a reliable record of site instructions in order to prevent later misunderstandings
and disputes. All verbal instructions given should be confirmed in writing and signed against.
Sub-contractors
Copies or abstracts of all relevant programmes, drawings, schedules, instructions, etc., must be passed on
to contractors concerned. Their labour strengths and progress achievements should be recorded and any
labour, material and information difficulties noted and followed up. Site meetings assist in settling queries.
Putting together the various parts of a project is one half of site management, while the
practical application of control techniques for their integration is another.
Progress
All agents should keep a site diary in which to record:
weather observations
work executed
delays experienced
comments and any noteworthy occurrences
Variations
The client, site conditions, or unforeseen circumstances, will inevitably produce a number of
variations as the contract proceeds. In order that financial adjustments may be settled
amicably, it is imperative that all changes should be methodically agreed and measured.
Original and final site levels, extra depths of excavation or concrete and all additional
construction details must be placed on record drawings and submitted signed.
works not immediately measurable should be recorded in day work sheets on a time and
material basis.
variation of price records should be kept right up-to-date and presented for regular inspection.
Grounds for claims should be notified in writing as quickly as circumstances allow, so that they
may be discussed and if possible settled at the next site meeting.
Prompt adjustment of variations is advantageous to all parties and promotes that friendly co-
operation so essential to a successful project execution.
Quality
Quality control includes accurate setting-out and levelling, fair faced brickwork and concrete
finishes, etc. Maintenance of quality is a most important factor in modern construction.
Co-ordination
An efficient network of communication both written and verbal is necessary for linking together
the various separate members of the construction team. The following procedures are widely
known (though not always practised).
Site report
Such a report may include the following; labour strength, plant, material; subcontractor’s labour, plant and materials
and any other information considered important or subcontractor shortages, delays incurred with causes e.g. weather,
breakdowns, instructions received, etc. A weekly (or daily) report should be submitted in order that the pulse of the job
can be watched and any assistance provided.
Weekly meetings
Such meetings for supervisory, technical and senior clerical staff together with chosen sub-contractors, are an excellent
way of exercising control. Progress can be related to the programme, shortages discussed and means of overcoming
them decided, anticipated problems settled or by-passed. Such a meeting every Friday to review the past week and
survey the week ahead can prove very useful.
Site meetings
Held at start of a contract and thereafter regularly each month, or as required during the progress of the work are highly
desirable. Well organised site meetings;
can resolve differences before they generate friction and lead to misunderstanding.
The agenda for such a meeting should always be sent out before hand. Any procedure for meetings should
include the following on its agenda;
list of persons present
acceptance of previous minutes
Matters arising from the minutes
progress of the works and causes of any delays; labour, plant or material shortages
outstanding information
review of nominated subcontractors and suppliers
variations/claims for extras
any other business and date of the next meeting
From what has been discussed it may seem that construction control and supervision is a
matter of checking and cross-checking. However, the sixth sense born of training and
experience is the irreplaceable of the personality in control because construction is subject to
chance in the form of weather, type of labour available and the vagaries of supplies.
Losses may be made on a construction project because of one or several reasons, such as:
• low bid
• insufficient knowledge of job conditions
• increase in costs of materials and labour
• adverse weather conditions
• improper selection of construction equipment
• inefficient management and supervision
The elements of any control system are:
• observation
• comparison of observation with some desired stand
• corrective action to take if necessary
A cost control system should enable a manager to observe current cost levels, compare them with a
standard plan, and institute corrective action to keep costs within acceptable bounds. The system should
help to identify where corrective action is necessary and to provide pointers as to what action should be.
There must always be a standard against which to compare recorded costs. In simple
projects, this might be the bill of quantities. However, a properly prepared and
appropriately updated contract budget forms a better basis.
Most control systems have a long response time. Even the best current system provides
information on what was happening the previous week or month.
As the work is part of a one-off project, it is quite likely that the information is only partly
relevant to the work going on.
The system might, for example, indicate on May 1, that the formwork operation in March
cost too much. If formwork operations are still continuing, the Manager will give this
work particular attention, but if formwork is complete, nothing can be done to correct
the situation.
The selection of a system depends in part on the size and complexity of the contact, but
more on the attitudes and level of sophistication of top management.
Overall Profit or Loss
The contractor waits until the contract is complete and then compares the sums of money that have been
paid to him with the monies incurred in purchasing materials, payment for labour, subcontractors, plant
and overheads.
This system is useful only on very small contracts of short duration. It scarcely qualifies as a control system as
the information it produces can only be used to avoid recurrence of gross errors in later contracts.
Unit costing
Costs of various types of work, such as mixing and placing concrete are recorded separately.
The costs, both on a periodic basis and cumulatively, are divided by the quantity of work of each type that
has been done. This provides unit cost which can be compared with those in tender.
Care must be taken to ensure that all costs are accounted for as mentioned earlier.
Any miscellaneous costs must be recorded and allowed for in some way, e.g., by proportional distribution
over the defined work types.
It is usually best to record site costs only and compare these with bill rates net of contribution for profit and
head office overheads.
Cost
However, there will come a point at
which extra effort will ensure no further Cost of control
cost reduction Optimum cost control level