Professional Documents
Culture Documents
Definition:
when each task will start and finish, ensuring that the project is
pletion date.
1
pessimistic, and most likely) to calculate expected durations
task durations.
ing progress.
the schedule.
2
4. Cost Control: Effective scheduling can lead to cost savings
struction Projects:
3
manageable components or work packages. It is a fundamental
project management tool that helps organize, plan, and track all
of the project.
Construction Project:
Level 1: Project
4
Level 3: Preliminary Design Phase
5
1.4.3 Pier Construction
1.5.3 Substructure
6
In this example, the WBS starts at the highest level (Level
major phases (Level 2) and further into detailed tasks (Level 3).
With this approach, we figure out what resources are needed for
each step, so that the work can flow smoothly without delays, and
we can meet our goals. This technique is handy for repetitive jobs
we can save time and money by using standardized designs for dif-
7
ferent parts of the job. We also make sure that the workers and
steadily. This way, we can keep putting similar pieces in place one
after the other, making the most of our workers and equipment
tion project from the very beginning to when it’s all done, using
pictures and timelines. It’s really good for finding problems and
LOB in Construction
ule.
ilar work, LOB can show how much work needs to be done at
key points to meet the project’s goals. When LOB is used, two
things happen:
wasted.
Scheduling LOB
ation.
9
• (iii) Choose buffer times that will guard against the risk of
itive project.
10
2. Reduces the amount of network planning and scheduling since
taken.
4 Development of network
Event
11
Merge Event: An event that represents the joint completion of
in Figure 1 (a)
gram must start from left (start of the project) to right (com-
12
pletion of the project) and top to bottom. Care should be taken
Activities
project.
the start of the activity and the head event j represents the
resents a specific task while the arcs represent the ordering be-
the nodes, and the arrows are used to indicate sequencing re-
13
Figure 2: Activity
and ending nodes for the whole project. The lack of dummy ac-
interpret.
14
time required for that activity to be performed. These diagrams
have a single beginning node from which all activities with no pre-
decessors may start. The diagram then works its way from left
to right, ending with a single ending node, where all activities with
ment.
(iii) AOA diagrams give a better sense of the flow of time through-
out a project.
The following are the two cases in which the use of dummy ac-
tivity may help in drawing the network correctly, as per the vari-
ous rules.
15
(i) When two or more parallel activities in a project have the
same head and tail events, i.e. two events are connected with
(ii) When two chains of activities have a common event, yet are
16
Figure 3: Dummy activity for parallel activities
17
Draw a network diagram of activities for the project.
Activity Description Predecessor Activity
A Open work order –
B Get material for X A
C Get material for Y A
D Turn X on lathe B
E Turn Y on lathe B, C
F Polish Y E
Solution
18
5 Critical Path Method
The main goal of critical path analysis is to figure out how long a
whole project will take and when each part of the project should
begin and end. This helps us see if the project is going as planned.
For each task in the project, we can either know exactly how
long it will take (if we use CPM) or have a range of possible times
tasks).
4. How much extra time some tasks can take without slowing
est time for an event to occur when all the preceding activities
19
have been completed, without delaying the entire project.
project completion.
• Lstij = Late starting time of an activity (i, j). This is the lat-
completion.
project completion.
• Lf tij = Late finishing time of an activity (i, j). This is the lat-
completion.
20
Forward Pass Method (For Earliest Event Time)
start and finish time for each activity that begins at that event
of the project.
point.
of these activities.
21
4. Time Calculation: To calculate the earliest occurrence time
activity.
22
any delay in these activities will directly impact the project’s
overall duration.
time ( L) and latest finish and start time for each activity that is
1. Start at the End: Begin with the last activity in your project
of these activities.
23
4. Time Calculation: To calculate the latest allowable time for
each activity, subtract its duration from the LAT of the ac-
tivity it leads to. This gives you the latest start time for the
24
the project’s overall duration.
Slack of an Event
latest occurrence time (Li ) and its earliest occurrence time (Ei
). That is:
Slack of an Activity
finish time and the earliest finish time for the activity.
in a project.
25
This is the length of time by which an activity can be delayed
sible time and all successor activities can be delayed until their
For each non-critical activity (i, j) the total float is equal to the
latest allowable time for the event at the end of the activity mi-
nus the earliest time for an event at the begining of the activity
Total float (T Fij ) = (Lj –Ei ) – tij = Lstij – Estij = Lf tij – Ef tij
26
(c) Independent float:
zero.
Critical Path
any of these tasks get delayed, the whole project will take longer.
These critical tasks are shown with a thick line on the project
plan, so everyone knows they are super important. The total time
27
• Look for tasks where the ”early finish time” (E) is the same
• The difference between the early start time (Ei) and early
as the difference between the late start time (Lsti) and late
Numerical on CPM
dicated the volume expected and the size of sales force required.
(c) For each non-critical activity, find the total and free float.
Solution
28
The forward pass method;
The critical path in the network diagram has been shown. This
has been done by double lines by joining all those events where
30