knowledge, skills, tools, and techniques to project activities in order to meet project requirements”
III. Project management is the planning,
scheduling, and controlling of project activities to meet project objectives. IV. •The major objectives that must be met include performance, cost, and time goals, while at the same time you control or maintain the scope of the project at the correct level. V. Planning leads to improved performance in terms of cost, schedule and operations, balancing the competing needs of a project. Project scheduling requires to follow laid-out steps, in order, for the schedule to take shape
Project planning, as it relates to the scheduling
process, has been defined by the PMBoK
The scope of a project should remain constant
throughout the life of the job.
A project manager has a responsibility to
keep stakeholders informed about the impact of scope changes on the project, protecting them from surprises at the end of the job and protecting the project manager from being evaluated on original targets rather than on revised ones. مهمProject life cycle =The beginning & the end of the Project
Cost and staffing levels are low at the start,
higher towards the end , and drop rapidly as the project draws to a conclusion. A WBS takes the form of a tree diagram with the "trunk" at the top and the "branches" below.
Decomposes: the overall project scope into
clearly defined deliverables.
Defines: the scope of the project in terms that
the stakeholders can understand
Provides: a structure for organizing information
regarding the project’s progress, status, and performance. –Supports: tracking of risks to assist the project manager in identifying and implementing necessary responses Levels: The depth of the WBS is dependent upon the size and complexity of the project and the level of detail needed to plan and manage it. Performance: The quality of the work being done. •Scope: The magnitude of the work to be performed. •Cost: The cost of project work, directly related to the human and physical resources applied. •Time: The schedule that must be met.
The relationship between time and cost, however, is
not linear. As a rule, cost increases as the time to do the project decreases below a certain optimum time. • If the duration is shortened, it is often necessary to pay premium labor rates as a consequence
Strategy: The approach being used to do the
project.
Tactics: The steps taken to implement the
strategy or approach chosen. Managers often cite delivering projects on time as one of their biggest challenges Schedule issues are the main reason for conflicts on projects, especially during the second half of projects
An activity or task is an element of work normally
found on the work breakdown structure (WBS) that has an expected duration, a cost, and resource requirements
An activity list is a tabulation of activities to be
included on a project schedule that includes
A milestone is a significant event that normally
has no duration
A dependency or relationship is the sequencing
of project activities or tasks
A network diagram is a schematic display of the
logical relationships among, or sequencing of, project activities A resource breakdown structure is a hierarchical structure that identifies the project’s resources by category and type
Dependent Activities 3-point estimates or
analogous work well.
Gantt charts provide a standard format for
displaying project schedule information by listing project activities and their corresponding start and finish dates in a calendar format
The CPM is a preemptive strategy for keeping a
project within time constraints. (critical path methode)
CPM is a network diagramming technique used
to predict total project duration –A critical path for a project is the series of activities that determines the earliest time by which the project can be completed –Slack/float A buffer is additional time to complete a task
a project buffer or additional time added
before the project’s due date –feeding buffers or additional time added before tasks on the critical path
PERT is a network analysis technique used to estimate
project duration when there is a high degree of uncertainty about the individual activity duration estimates