Professional Documents
Culture Documents
On
Distribution Transformer
An internship submitted in partial fulfillment of the requirements for the
Award of Degree of
Bachelor of Science in Electrical and Electronic Engineering
At
Bachar Engineering Limited
By
Supervised by
MD:MIZANUR RAHAMAN
Lecturer & Program coordinator (Eve), EEE
This is to certify that this internship entitled distribution transformer at basic power
engineering limited in partial fulfillment of the requirements for the degree of Bachelor of
Science in Electrical and Electronic Engineering. The presentation of the work was held on 17
December, 2019.
Mithun Mitra
ID: 171030012
MD:MIZANUR RAHAMAN
Supervis
Lecturer & Program coordinator (Eve)
Department of Electrical and Electronic Engineering.
Faculty of Science and Engineering
Green University of Bangladesh, Dhaka
BOARD OF EXAMINERS
I Acknowledgement ---------------------------------------------------------------------------------07
2. Chapter 2 ----------------------------------------------------------------------------------------------12
3. Chapter 3 -----------------------------------------------------------------------------------------------14
4. Chapter 4 -----------------------------------------------------------------------------------------------18
6. Chapter 6 ------------------------------------------------------------------------------------------------50
7. Chapter 7 ------------------------------------------------------------------------------------------------54
References ----------------------------------------------------------------------------------------------56
Acknowledgement
The successful completion of this report is the outcome of the contribution of a number of people
to whom we are grateful and thank them from the very deep of my heart. So, we would like to
take this opportunity to thank all those people who helped me in preparing this practicum report.
At the very beginning we would like express my deepest gratitude to Allah for giving me the
strength and the composure to finish the task within the schedule time.
Then, we would convey my special thanks to my parents whose inspirations have enabled me to
complete this report of this particular course.
Then, we would like to express my warm gratitude and cordial thanks to my supervisor
MD:MIZANUR RAHAMAN, Faculty of Green University of Bangladesh (GUB) Faculty of
whose guidance & help was very much required to prepare the report successfully.
we like to give special thanks to Basic Power Engineering Limited to give me an opportunity to
do internship in this reputed Company. We are very grateful to my co-supervisor Engr. Md.
Amir Uddin (Technical), for giving his valuable time & guidelines about my report. we thank
all the employees for being friendly and cooperative. we would taught lots of important things
through-out my internship career because of their proper attention and co-operation. we would
like to express deepest appreciation to Engr. Md.Anisuzzaman Manik, Engr. Ariful Haque for
their humble co-operation for the completion of the report.
Finally, we would like to thank honorable Chairperson, department of EEE, Prof. Dr. Md.
Fayzur Rahman because he designated such an environment for learning through which we got
the opportunity to acquire knowledge under B.sc EEE program, and that will be very helpful for
my prospective career.
Executive Summary
Bachar Engineering Ltd. is the pioneer manufacturer of transformers and electrical goods in
Bangladesh. The company has always been contributing towards the advancement and
development of engineering sector in Bangladesh by introducing a range of quality of
distribution transformers with different ranges & other electrical equipment’s like – Switchgear
equipment, distribution board etc. we recently have done my internship in Basic power
Engineering Ltd. In which I got training from its transformer section. The internship is basically
on manufacturing, assembling, and testing process of distribution transformer.
The starting of this report with some fundamental data about introduction, background,
objectives, methodology and limitations are shown. Then we have discussed about distribution
transformers, its working procedure, its classifications based on its applicability, its efficiency
etc. The report includes manufacturing process step by step with core cutting, HT, LT winding,
assembling core and coil, tanking up, bushing, oil filling etc. we have tried to describe the whole
calculation process of the rated transformer with its testing procedure along with test reports
which was observed by me.
In this report, we have given a very brief review of what we saw and learnt during in our
internship period. We have mentioned all those things which we have learnt in our internship
period. This report will give its reader the knowledge about the Bachar Engineering Ltd. and
distribution transformer. We tried our level best to make the report simple but informative.
Chapter 01: Introduction
1.1 Introduction
The purpose of a distribution transformer is to reduce the primary voltage of the electric
distribution system to the utilization voltage serving the customer. A distribution transformer is a
static device constructed with two or more windings used to transfer alternating-current electric
power by electromagnetic induction from one circuit to another at the same frequency but with
different values of voltage and current.
The construction of a transformer comprises two active components: the ferromagnetic core and
the windings. Within the transformer industry, the core and windings together are normally
referred to as the “active part”. The passive part of a transformer is the cooling system, in case of
liquid-immersed transformers consisting of the tank and the cooling liquid (mineral oil, silicone
fluid etc).
1.2 Background
As a partial fulfillment of the B.Sc. in EEE program I have done this practicum report on titled
“Manufacturing, Assembling, & Testing Process of 400kVA 11000/415 V, 3-Phase Distribution
Transformer” at “Bachar Engineering Limited ” under the instruction of Engr. Amir Uddin(Technical),
Engr. Md.Anisuzzaman Mank, Engr. Ariful Haque (Transformer Section).
Bachar Engineering Limited is one of the well know industry in assembling transformers and Electrical
Products. Basic Power Engineering Limited offers customers complete substation equipment and
transformers. Their main products are transformer, HT Switchgear, LT Switchgear, SDB board, DB
Board, PFI Plants, Motor Controlling etc. Since 2007, Bachar Engineering Limited has already become
best choice for its products and service to the customers countrywide.
Bachar Engineering Ltd transformer manufacturing has some characteristics as given as below:-
1) Bachar Engineering Ltd ensures guarantees of product by following code and
conducts of ISO 9001:2008.
Broad Objective:
The broad objective of this report is mainly to understand the manufacturing, assembling, and
testing process of distribution transformer and applying this knowledge for improving the ability
& increasing the capability of the power sector of our country.
Specific objectives
In order to obtain the broad objectives, I have to find out the following objectives. They are
follows:
To gather practical knowledge about working process of transformer.
To know the manufacturing procedure of transformer.
To know the calculation process of a transformer.
To know the assembling process of transformer.
To know the testing procedure of transformer.
1.4 Methodology
The project is concentrated of the Manufacturing, Assembling, and testing of Distribution
Transformer. Both primary and secondary data are being collected for the purpose of this report.
Primary data: Primary Data are collected from the practical work, maintenance chart and
the user manual handbooks.
Secondary data: Secondary data was collected from the online internet resources, books,
journals.
1.5 Limitations:
Though I have completed my report within my practicum period but three months are not
enough to learn all the things that are available in Bachar Engineering Limited. I faced some
problems which eventually became the limitations of my project,
They has less Engineers and Technicians for this reason they always remain busy with their
own work so it takes more time to me gather all the information from them. Even they have
not enough first aid facility. In case of any kind of accident the medical treatment won’t be
found immediately as the area is far away from qualified hospital. They have no fixed
calculation manual for transformers so, I got some problems for collecting this calculation
from engineers of transformer section.
Chapter-1 is the introductory chapter which gives a general idea about a Bachar Engineering
Limited (BPEL) and methodology of our Internship
Chapter-2 Describes the Background of Bachar Engineering Ltd. (BEL) and Mission
Chapter-3 Describe on the Classifications of Transformer and Basic Constriction and Working
Principle of Transformer
Chapter-4 Shows the Different Parts of Distribution Transformer and Transformer Losses
Chapter-5 Basic Calculation of Distribution transformer and Core Coil Assembling
Chapter-6 Describe on the Testing of transformer
Chapter-7 Recommendation and Conclusion
Chapter 02: Organizational Overview
2.1 Background
The Bachar Engineering Ltd, an organization in private sector was incorporated in 2003
under the leadership of qualified young and dynamic partners to fulfill the domestic
electrical requirements of almost every new organization of the country. Bachar
Engineering Ltd. is now the largest transformer and switchgear manufacturing company
in Bangladesh. The company has wide variety of Distribution Transformers, HT-High
Tension Switchgear, LT-Low Tension Switchgear, PFI- Power Factor Improvement
Panel, DB- Distribution Board etc. All these products are incompliance with
internationally recognized standards,
Including,
The company gives utmost importance to customer satisfaction in all respect is now
looking forward to global recognition by adopting internationally recognized quality
system.
2.2 Mission:
We are committed to maintain our leading role in Power Sector; Power Transmission &
Distribution with the help of our skilled & professional staff members in order to execute
the challenging projects in timely manner with customer focused policy. The company
aims to achieve this mission not only through best quality products but also through excellence
in its service [6].
2.4 Scope
This report has been prepared through the assistance of the help of practical knowledge and
broad discussion of my selected supervisor, technical engineer and employees of this
organization. While Preparing this report, I had a great opportunity to have an in depth
knowledge of Manufacturing and Testing procedure of Distribution Transformer. This Practical
Knowledge will help me to apply my knowledge to related field.
di
EM
dt
Where,
e =induced emf
M = mutual inductance
If the second circuit is closed, a current flow in it and so electric energy is transferred
from the first coil to the second coil.
Power Transformer
Distribution Transformer
Auto transformer
Isolation transformer
Instrument transformer
Reactor transformer
Furnace transformer
Rectifier transformer
Distribution Transformers:
We are discuss only distribution transformer .They are used in the distribution networks
in order to transmit energy from the medium voltage (MV) network to the low voltage
(LV) network of the consumers. Their power is usually ranging from 50 to 1600 kVA.
Ampere rating is increased in a distribution transformer by increasing the size of the
primary and secondary windings; voltage ratings are increased by increasing the voltage
rating of the insulation used in making the transformer.
Chapter 04: General Concept of Distribution Transformer
Figure 4.3: Copper wire for HT Figure 4.4: Copper wire for LT
It is not considered that there is any significant material improvement available here.
They use of larger winding conductor cross section to reduce winding resistance and
hence load loss is a possible option for improvement. However larger cross section
conductor will also have the undesired effect of increasing eddy current loss when
harmonic current are present in the winding with nonlinear load. They will also add to the
weight and cost. Lower temperature operation and the attendant lower winding resistance
would reduce load loss, but would mean lower power capacity for the same size
transformer unit.
Insulation Paper:
Electrical insulation papers are paper types that are used as electrical insulation in many
applications due to pure cellulose having outstanding electrical properties. Cellulose is a
good insulator, having a dielectric constant significantly greater than one.
LT Bushing
HT Bushing
Tap number
Channel:
Channel need some help. That help is given by the help channel. Channel is a long pole
which is sliced by the size required. But Bacher Engineering Ltd. Bought the channel
from different companies. After the channel reached it sent to the hole drilling section.
After completing the drilling channel it sent to the core section to assemble the core on
the channel. Four channels are needed to make one complete transformer.
Channel to
Core
supporter
Core
Channel
Transformer Tank:
The transformer tank should be manufactured from steel and might be of hearty
development. Care should be taken at the assembling stage so as not have leaks during
transportation or when the transformer is continuously worked d at rated power.
Transformer tank envelop the active part, filled with completely with oil. The body has
no contact with the active part. The paint at the inward side is oil resistive and the
external paint is hostile to consumption. Even if it just a container but required much
consideration during design. Except for radiator components, every outside joint should
be crease welded. The bearing surface of the tank to which bushings are clamped should
be significantly level. E very single coordinating face of joints should be made oil tight
and completed with as mood surface to guarantee that the casketing materials make a
satisfactory joint.
Figure 4.10: Transformer Tank
Radiator:
Radiators are utilized as a part of a transformer to cool the transformer oil through normal
air or forced air streaming in these radiator fins. As the transformer oil temperature goes
down because of cooling it goes to the transformer tank from base, cool the winding and
gets warmed, and afterward come back to the radiator for next Cooling.
Transformer Oil:
Transformer oil or protecting oil will be oil that is stable at high temp erasures and has
superb electrical protecting properties. Transformer oil forms an exceptionally critical
part in the transformer protection system. Breakdown voltage strength is the basic
parameter of the transformer oil. Breakdown voltage should not be less than 50 kV after
filtration. The fundamental crude material for the creation of transformer oil is crude
Petroleum.
Maximum Level
Normal Level
Minimum Level
Conservator tank is transformer oil storage tank. Its function is to ensure that the
transformer tank is completely filled with oil every time. If the main tank oil reduces, the
conservator will feed the oil to main tank and if the oil gets expansion that oil will go to
conservator.
Horn Gap:
Arcing horn basically protected conductors used the insulators in high voltage.
Transmission Line may damage during flashover. Over voltage on transmission line may
occurs due to various real sons like- lightning strike, sudden load variety on, fault etc.
Due to this high voltage a flash over may take place which will blast the insulator. Horns
are normally paired on either side of the insulator, one connected to the high voltage part
and the other to ground. The horns can take different forms, for example simple
cylindrical rods, circular guard rings.
Horn Gap
Losses in the
transformer
Hysteresis Eddy
Losses Current
Losses
Whenever an AC magnetic field is generated in the steel core, it will cause an energy loss
in the core material. This is the “No Load Loss” or “core loss” of the transformer. There
are, in turn, two component of the No Load Loss:
Hysteresis loss
Eddy current loss
These both produce heat in the core material they do this in quite different way.
Hysteresis loss is a magnetic loss process whereas eddy current loss is an electrical loss
process.
Hysteresis loss:
Hysteresis loss is created because of the impact of the exchanging magnetic field on the
soft magnetic steel of the core. As the magnetic area in the steel endeavor to take after the
changing induction of the AC magnetic field they create frictional heat in the core; this is
hysteresis loss. Hysteresis losses are strongly material-dependent. For example silicon-
steel has much lower hysteresis loss than normal steel, but mu-metal has a much lower
hysteresis loss than silicon steel (it is also much more expensive). Thus hysteresis loss is
dependent on the frequency of the applied magnetic field, the AC power frequency and
on the particular material utilize for the core [4].
The eddy current losses depend on the electrical resistance of the core material and the
AC frequency. The resistance can be increased and the eddy current loss decreased by
using thin lamination or by using a core material with a naturally high electrical
resistance, such as undefined magnetic metal. Both of these components of core loss are
dependent on the AC frequency at which the magnetic field alternate, so that when
frequency increases, the core loss will increase. Hysteresis loss increases linearly with
frequency but eddy current loss scale as the square of frequency. The eddy current loss is
minimized by making the core with thin laminations [4].
These Losses happen in the windings of the transformer when heat is scattered because of
the current going through the winding and the inside resistance offered by the windings.
2
So it is also known as Ohmic loss or I R losses, where I is the current going through the
windings and R is the internal resistance of the windings. These losses varied according
to the load and known hence it is also known as variable losses. Copper losses vary as the
square of the load current. Although “copper loss” is a widely used term for Load Loss,
the winding are not always made of copper. In modern distribution transformer, the
secondary winding may be wound in the form of cylindrical sheet of aluminum. This is
an important consideration in adjusting loss for temperature variation.
Stray Loss:
The occurrence of these stray losses is due to the presence of leakage field. The
percentage of these losses is very small as compared to the iron and copper losses so they
can be neglected [4].
Dielectric Loss:
Dielectric loss occurs in the insulating material of the transformer that is in the oil of the
transformer, or in the solid insulations. When the oil gets deteriorated or the solid
insulation get damaged, or its quality decreases, and because of this, the efficiency of
transformer is affected [4].
Chapter 05: Manufacturing and Assembling Process
5.1 Basic Calculation:
HV LV
Connection Delta Star
type
Line Voltage 11000V 415V
Line Current =(kVA × 1000)/ (√3 × line =(kVA × 1000)/ (√3 × line
voltage) voltage)
=(400 * 1000)/ (√3* 11000) =(400 * 1000)/ (√3* 415)
=20.99A =556.48A
Power P= 400kVA
Primary /line voltage =11000 Volt
Secondary / line voltage = 415 Volt
At first we need to find out the Diameter of a Transformer
1/4
Diameter =3.96*(kVA) [ it can vary from 3.5-4]
1/4
=3.96*(400)
=17.70*10mm [1cm=10mm]
=177mm
We can consider 170mm for rounding process
Let, core width=170mm
The thickness of each stack pertaining to a particular core step is calculated as follows
Now, we need to select the Area,
At first we need to find out per core Area,
A1=Width*thickness
= 170*49
= 8330
A2=160*26
= 4160
A3= 150*19
= 2850
A4= 140*14.34
=2007.6
A5=130*12
=1560
A6=120*14.34
=1720.8
A7=100*16
=1600
A8=80*12
=960
A9=60*8.64
=518.4
Area=total area/100
=23706.8/100
=237.068mm
Per turns voltage = 4.44*f*Bm*A*10-4
[we can select Bm from 1.5-1.7]
-4
= 4.44*50*1.55*237.06*10
= 8.15v
Where, f= frequency
B m= Flux density
A= Area
LT Turns=240/8.15
=29.44
=30
Conductor Area Selected for 400kVA transformer:
Secondary Coil/LT Winding:
Secondary Winding type=Helical Winding
=203
SWG In mm SWG In mm
1 .300 7.620 21 .032 .813
2 .276 7.010 22 .028 .711
3 .252 6.401 23 .024 .610
4 .232 5.893 24 .022 .559
5 .212 5.385 25 .020 .5080
6 .192 4.877 26 .018 .4572
7 .176 4.470 27 .0164 .4166
8 .160 4.064 28 .0148 .3759
9 .144 3.658 29 .0136 .3454
10 .128 3.251 30 .0124 .3150
11 .116 2.946 31 .0116 .2946
12 .104 2.642 32 .0108 .2743
13 .092 2.337 33 .0100 .2540
14 .080 2.032 34 .0092 .2337
15 .072 1.829 35 .0084 .2134
16 .064 1.626 36 .0076 .1930
17 .056 1.422 37 .0068 .1727
18 .048 1.219 38 .0050 .1524
19 .040 1.106 39 .0052 .1321
20 .036 .914 40 .0048 .1219
= 3.1416×(2.337)2
4
= 4.289
Current density= 2.82A [maximum current density =3.5]
Tapping for 2.5% to -7.5%
Primary turns =LV turns* Ratio
A8 470 80 630 12
A9 470 60 590 8
B Core
B8 470 80 550 6
B9 470 60 530 4
C Core
After calculating the measurement of core we cut the core by using different machine to
get our required shape. The core is made of Cold-Rolled High Grained Oriented (CRGO)
0 0
silicon steel. The core cut of an angle 90 in rectangular shape and 45 for MITRED
shape also cut “V” notch. Staking and Wound core 0.27 mm thick M4 grade silicon steel.
C Core is
Open
Insulation
paper
Bottom
Separator
Figure 5.4: cotton tap rayed above core Figure 5.5: Insulation paper
and bottom Separator
5.4 Coil Windings:
There are two windings wound over the transformer core which is protected from each
other. Windings consists of few turns of copper coils packaged together an every package
are associated in series to form of windings.
The low voltage winding is in cylindrical shape, the high voltage winding is in cylindrical or
foil type. HT & LT windings are nothing but the calculated coil form of copper wire. So it
will have sufficient capacity secured against short circuit and make the magnetic circuit more
reasonable. The winding conductor is drawn to various sizes in round and rectangular shapes.
The choice of conductor and insulation covering depend on the voltage class, current, cooling
and insulation clearances. The cross section of the winding provides the necessary area to
handle the current. The conductor is wound into coils.
The windings are such designed so as to ensure reduced axial stresses in Short Circuit
conditions and also to withstand impulse and over-voltages. Some standard forms of coil
windings are spiral, helical, interleaved disc and plain disc. For Power Transformers, both
low voltage and high voltage windings are disc type, which give highest resistance
against short circuit forces. It is ensured that proper tension is given on the winding for
rigidness.
st
For our 1 value we pick up tap after 2.5% of total turns for 10V more or less. Because
we know primary voltage always not same sometimes it may vary. It will regulate the
output voltage by altering the number of turn and thereby changing the turn’s ratio of the
transformer. We brought out 1 wire after every 32 turns from the total turns of High
tension winding, after turn out six wires form four steps we will connect those by a tap
changer from 1 to 5 tap.
Generally the Transformers are either to Y or Y to connect. If High voltage side Delta
connected then low voltage side Y connected and vice versa. We connected HT side is
Delta connection and LT side is Wye/star connection.
Figure 5.10: LT side with LT Side Bushing Figure 5.11: HT side with HT Bushing
After arranging all these things finally the input and output points are connected with the
copper bars. Copper bars are covered very tightly with cotton tape after welding. Then
the transformer is ready to go for the next step of attaching bushing materials and for
going to heat chamber.
Heating chamber is a place where heat generates. It can controls temperature inside the
heat of the transformer. We can place 3 transformers inside this Heat chamber at a time.
Transformer is placing inside the heat chamber. Transformer is placing inside heat
chamber because of increasing insulating resistance.
Inside the transformer, coil creates magnetic flux so that heat will produce. If inside of
the transformer is not dry enough, then dielectric strength breaking down because of heat
and power losses occurs. For that reason it needs to dry enough the transformer.
0
Transformer is kept inside the heat chamber for 48 hours at 90 C. This heat chamber
0
temperature range 80 to 100 C.
Chapter 06: Transformer Testing
03 2.5mm 42 kV 30 sec
04 2.5mm 46 kV 60 sec
2.5mm Gap
**Voltage Ratio is measured by Raytech USA (TR SPY Mark II) Manufactured by USA.
6.3. Resistances Test:
For resistance test, Firstly we need to conduct the meter to measure H.T side resistance
then we just hold on the probe of the clamp on meter to the HT lead like - AB, BC, CA
and find the result for this side. We should repeat same procedure for getting the result of
LT side also.
30 sec 35G Ω 36 GΩ 32 GΩ
60sec 41 GΩ 41 GΩ 50 GΩ
6.5 High Voltage Test:
For doing High Voltage test at HV winding we need to short the three phase terminal of
HV side, LV side and body/tank with the main earthing. At first we have given 28kV
from High voltage test bench, then it come to Barrier. After that it was gone through high
voltage transformer’s HT side. We have to apply the 28 kV for 1 min too the transformer.
If the transformer remains withstand after keeping this voltage for 1 m in then it proves
that the transformer keep secure in voltage surges which may be caused by lightning or
other over voltage.
Figure 6.6: Transformer HV side shorted & Figure 6.7: High voltage transformer
LV side and tank shorted with earthing.
Chapter 07: Conclusion
7.1 Conclusion:
In our power system transformer plays an important roles for the industry. In our modern
industrial economy substation is needed for maintaining electrical sections. A substation
without transformer is not possible because it is necessary to step up or step down voltage
level according to our requirements.
7.2 Recommendation:
Within my internship period, I gather all practical knowledge about transformers manufacturing
from Bachar Engineering Limited. Although, they need to increase some facilities -
The Company mainly use manually operated machines in every section of transformers
which takes more times and more labor cost. They should use digital machines for their
betterment.
They have not enough technicians and manpower as a result they can’t deliver
huge amount of products at a time. So, they should appoint more manpower. They
did not have enough spacing facilities for keeping their products. They need to
increase those facilities also.
They have many transformer test functions. But some of them are carried out at
the time of manufacturing. They should increase their testing number for more
accurate efficiency.
They did not have sufficient amount of testing meters. So, they should increase
the amount of testing meters.
References:
4. Circuit Globe. (n.d.). Retrieved November 10, 2017, from Types of Losses
in a Transformer: http://circuitglobe.com/types-of-losses-in-
transformer.html
5. Windows to the Universe. (n.d.). Retrieved November 7, 2017, from The Role
of Transformer in out Electrical Power System:
https://www.windows2universe.org/physical_science/physics/electricity/
transfor mers_in_power_grid.html&edu=high
6. Basic Power Engineering LTD. (n.d.). Retrieved November 28, 2017, from
Mission, http://www.bpelbd.com/about.html
7. Custom Coils. (n.d.). Retrieved 11 10, 2017, from
https://www.customcoils.com/ images/single-phase-transformer-
schematic.jpg