POW & PROGRES PEKERJAAN GRANULAR TREG.

7 STO SUDIANG

Nama Mandor :
Nama Waspang :
Qty Team Work :
No. TARIKAN KABEL ITEM PEKERJAAN SATUAN VOLUME DURASI START

1 Buka HH & Roding m 922


2 Galian/Rojok/Subduct m 8,516
3 Pasang Pipa Jembatan m 95
4 Pasang Pipa SS m 10
5 Pasang Tiang m 1
Feeder-1
6 Pasang Acc.Tiang bh 27
7 Pasang Kabel Duct 288 m 10,788
8 Pasang ODC+Ground. set 4
9 Joint Core set 9
10 CommTest n2n 288
11 Buka HH & Roding m 2,345
12 Galian/Rojok/Subduct m 1,247
13 Pasang Kabel m 3,691
Feeder-2
14 Pasang ODC+Ground. set 2
15 Joint Core set 4
16 CommTest n2n 288
NG

MARET APRIL
FINISH 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 1 3 5 7 9 11 13
APRIL MEI
15 17 19 21 23 25 27 29 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 2
JUNI
4 6 8 10 12 14 16 18 20 22 24 26 28 30