JADWAL PERALATAN UTAMA

WAKTU PELAKSANAAN 120 HARI KALENDER


NO. Jenis Peralatan Jumlah BULAN KE - I BULAN KE - II BULAN KE - III BULAN KE - IV KET
1(7HK) 2(7HK) 3(7HK) 4(7HK) 5(7HK) 6(7HK) 7(7HK) 8(7HK) 9(7HK) 10(7HK) 11(7HK) 12(7HK) 13(7HK) 14(7HK) 15(7HK) 16(7HK) 17(7HK) 18(1HK)

1 Dump Truck 2 Unit 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0

2 Concrete MIxer 2 Unit 2.0 2.0 2.0 2.0 2.0 2.0

3 Generator 1 Unit 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

4 Snee Pipa 1 Unit 1.0 1.0 1.0 1.0 1.0

5 Mesin Las Pipa HDPE 1 Unit 1.0

6 Alat Tukang 1 Set 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

Kupang,21 Juli 2020


Penawar,
CV. AMFOANG JAYA

YOGANRI U.MAUTUKA
Direktur