You are on page 1of 6

PROJECT NAME : REHABILITATION OF RIO-HONDO-MARIKI BRIDGE

PROJECT LOCATION : ZAMBOANGA CITY


ONTRACT I.D: CW-20-0206-0195
EQUIPMENT UTILIZATION SCHEDULE
Total Duration=163 Calendar Days
EQUIPMENT / DURATION No. of
6 12 18 24 30 36 42 48 54 60 66 72 78 82 88 94 100 106 112 118 124 130 136 142 148 154 160 163
(WEEKLY) Units

Payloader 1 0 0 1 1 1 1 1 0 0 0 1 1 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 1
Telescopic Crane 7 Tons 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 0 0 0 0 1
Tractor Head with Trailer 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1
Cargo Truck 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Backhoe 1 0 0 1 1 1 1 1 0 0 1 1 1 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 1
Transit Mixer 2 0 0 0 0 0 0 0 0 0 2 2 2 2 2 2 2 2 0 0 0 0 0 0 0 0 0 0 2
Mini Dumpturck 2 0 0 2 2 2 2 2 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 0 0 0 0 2
Boom Truck 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Jack Hammer 2 0 0 2 2 2 2 2 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2
GenSet 1 0 0 0 0 0 0 0 0 0 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Welding Machine Set 2 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2 2 2 2 2 2 2 2 0 0 0 2
Oxygen/Acetylene Set 2 0 0 2 2 2 2 2 0 0 0 0 0 0 0 0 0 2 2 2 2 2 2 2 0 0 0 0 2
Water Pump 2 0 0 0 0 0 0 2 2 2 2 2 2 2 2 2 2 2 0 0 0 0 0 0 0 0 0 0 2
Conc Vibrator 2 0 0 0 0 0 0 0 0 0 2 2 2 2 2 2 2 2 0 0 0 0 0 0 0 0 0 0 2
Bar Bender 1 0 0 0 0 0 0 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1
Electric Bar Cutter 1 0 0 0 0 0 0 1 1 1 1 0 0 0 0 0 0 1 1 1 1 1 1 1 0 0 0 0 1
One(1) Concrete Bagger Mixer 2 0 1 1 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 0 0 0 0 0 0 0 0 0 1
Lighting Sytem/Tower Light 2 0 0 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Total Duration= 163 Calendar Days MANPOWER SCHEDULE
NO. OF
MANPOWER / DURATION
PERSONN 6 12 18 24 30 36 42 48 54 60 66 72 78 82 88 94 100 106 112 118 124 130 136 142 148 154 160 163
(WEEKLY)
EL

PROJECT ENGINEER 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

MATERIALS ENGINEER 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

GEODETIC ENGINEER 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

SAFETY PRACTITIONER 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

CONSTRUCTION FOREMAN 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

TIME KEEPER 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

STORE KEEPER 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

EQUIPMENT OPERATOR 5 2 2 4 4 4 2 2 2 4 4 6 6 6 6 6 6 6 4 4 4 4 2 2 2 2 2 2 2

STEEL WORKERS 6 0 0 2 2 4 6 6 6 6 6 6 6 2 2 2 1 1 0 0 0 0 0 0 0 0 0 0 0

MASONS / CARPENTERS 10 0 2 2 0 0 0 0 0 0 10 10 10 10 10 10 10 10 6 0 0 0 0 0 0 0 0 0 2

LABORERS 20 6 10 15 15 15 15 15 20 20 20 20 20 20 20 20 20 15 15 15 15 15 15 10 10 10 5 5 5

Submitted by: Approved by:

ONESTO I. BAYOT CHRISTOPHER Q. NAVARRO


Owner/Manager City Engineer
AMARRO CONSTRUCTION & REALTY DEVELOPER

You might also like