| Ref. bre. |: | 465927-50550200-028-0001
Procedure for Making Provision [new =a
for Saturated Steam links from Steam,
Drum to PSH Header e Page 1 of 3
04.08.2016
To lay down a procedure for making Provision for fitment of Saturated steam links from Steam
Drum to Primary SH inlet Header.
PROCEDURE:
Step 01:
{As per Drawing reference no: JG5927-50550200-028-0001, the insulation in the Drum area shall
be removed with proper temporary approach platforms.
Step 02:
The Steam Drum in its position shall be temporarily supported with Boiler structure. This
‘temporary support arrangement shall be released only after completion of the rectification
‘work and Post Weld Heat treatment (PWHT) cycle.
Step 03:
Both the side’s manhole doors shall be opened. The new nozzle area shall be punch marked for
identification as per drawing from outside. Inspection of the Punch mark shall be done and
verified. Refer sketch - 01
=> PUNCH MARKS.
_k—> Dia 850M
SKETCH: 01.
Step 04:
Oxy ~ Acetylene Gas cutting set shall be used to cut the nozzle hole of 85.0 MM dia. The Cutting
arrangement shall be made as per standard practice.
Step 05:
Before the final stage of cutting proper care shall be taken to make hold of the falling piece.
Please ensure that no cutting pieces should fall inside the Tubes inside the drum and Header.
Step 06:
Prepared by : VPS Approved by : PCRef, Dre, 4G5927-50550200-028-0001
Procedure for Making Provision ~
Issec Heavy for Saturated Steam links from Steam
exsereet Drum to PSH Header Page Page 2 of 3
Rev.No. |: | 00
‘Date + [04.08.2016
After removal of the piece, Flexible Shaft grinding machine with $5 tool bit shall be used to
surface smoothen the nozzle hole. Sample Too! Bits shown in Sketch: 02. Finalized hole 1D shall
be 87.32 MM afteé grinding,
7
Sketch: 02
Step 07:
After inspection of the nozzle hole for smoothness and dimensions the supplied nozzle shall be
welded as per the below details, for Drum to stub welding details refer Sketch 03.
fine caarree — xm
ti FIG = MIL/@5R Be
Prepared by : VPS Approved by : PC| ref. rg, | | 465927-50550200-028-0001
Procedure for Making Provision — —
‘ Rev.no. || 00
for Saturated Steam links from Steam 2 a
Drum to PSH Header Page 3 of 3
04.08.2016
WR IG = 205/208
Bar TER vn
‘HEADER 10_ STU WELD DSTA (0.1)
Step 08:
Selection of welding electrodes, Pre heating and Post heating procedures shall be as per the
WPS / POR suggested. The same shall be inspected and recorded.
Step 09:
‘As there are two stubs within a distance of more than 400MM from Center to center the
Welding and Post weld heat treatment shall be done one by one stub. Insulation for heating
band to be done for top 180’ coverage of Drum including each nozzle. After completion of PWHT
cycle DP test shall be done on the nozzle welds.
~-000~
[. Prepared by : VPS ‘Approved by : PC